Excavation completed on Fv 714

30/01/2013

Construction work on three road tunnels for Fv 714 Mjones-Valslag, awarded to Kruse Smith, started in October, 2011. The job was completed on 08.01.2013 by breakthrough in the 2,601 m-long Valslag tunnel.

The 1,070 m-long Fenes tunnel, which saw daylight on 08.06.2012, will open in a few weeks time. The 215 m-long Brattstias tunnel, whose excavation ended on 08.08.2012, will open in May. Click here for the map and no/131 for tunnelbuilder archive. Visit http://www.vegvesen.no. 05/13.