Tunnelbuilder Promoting the world's tunnelling industry to a huge qualified audience

View the Spanish Tunnelbuilder website View the Italian Tunnelbuilder website

Corbulo Tunnel Press Release

08/03/2021
Corbulo Tunnel Press Release


Before they can build cross connections in the Corbulo tunnel 2.5 km of poles have been installed in the walls. They will then be used to freeze the ground between the two tunnels before building the 8 cross connections needed for the project. 

A cable channel/duct has also been prepared which is 2.5 m high and 2 m wide. It has been made large enough so that all cables, pipes and systems for the tunnels runs under the road, along the entire length of the tunnel. There are alcoves every 50 m with technical cabinets that run the systems.  This is to ensure that all technical installations such as lighting, fire alarm systems and cameras are connected to each other. The fire extinguishing pipes and the waste water discharge pipes will also be in this underground space.  



At the end of April, the transport of the tunnel technical installations (TTI) from the test hall in Eindhoven to the Corbulo Tunnel will start. Project manager Benjamin Mooijaart of construction consortium Comol5 explains what is involved.

Benjamin is well versed in the field of tunnels. He did his HTS graduation project during the construction of the new Coen tunnel in Amsterdam, after which he continued to work there as project manager, among other things. He was also involved in the Velser Tunnel and the Maas Tunnel. While still working on the latter project, he got on the moving train of the Corbulo tunnel in mid-2019.

Testing in Eindhoven was already about to begin then.

"That's right. When we have completed that, it will have taken 14 months. At the moment, the final tests are taking place, including the retesting of findings. This concerns systems of which not everything worked properly during the first test. One example is that certain actions on the fire alarm panel in the tunnel service buildings were not visible at the traffic control centre in Rhoon. While that is precisely where the overview should always be. So this is being adjusted and tested again, with the client present, so that we can check that it works.

By the end of February, all tests in Eindhoven will have been completed. And then?

"Then we will demobilise. The 26 modules with TTI systems are connected to each other with various cables for the testing. We are going to loosen these on one side, roll them up and attach them to the module in question. Then we will pack the modules and place them on the lorry in a watertight seal. From mid-April onwards, 16 of the 26 modules will be transported in a fortnight to the East service building near the mouth of the tunnel on the A4 motorway. The remaining ten modules will be transported to Service Building West, near the A44 motorway, in the summer.

Those modules are pretty big. How do you get them in there?

"From above. That's why the roof isn't on yet. So we hoist the modules from the lorries into the service building, to the ground floor and the -1 level. This has to be done in a certain order. Fire-resistant walls are also installed between the modules. Once everything is in place after two weeks, the roof can be put on."

The modules in the service buildings will soon control the TTI components in the tunnel, such as the matrix signs, cameras and fans. How will the connection be made?

"A cable duct runs under the road along the entire length of the tunnel. Every 50 metres there are recesses, in which technical cabinets hang. On the one hand, we connect these cabinets to the service buildings. On the other hand, the cabling runs from the cabinets to the components in the tunnel. Laying all these connections is more than a year's work. So we'll also be working on that for part of 2022. After that, the final tests will take place, all emergency services and road traffic controllers will receive training and the structural inspections will follow. If all this is in order, we will advise the competent authority. In this case, the Mayor and Aldermen of Leiden. If the advice is in order, they issue the permit to open the tunnel."

What makes the Corbulo tunnel different from all those other tunnels you have worked on?

"It is a lot longer! The Maas Tunnel is over 1 kilometre long, compared to the Corbulo Tunnel which is over 2.5 kilometres long. And testing all the TTI so long in advance; that is really new on this scale. It was the Province's wish as client. We, the contractor combination, responded to it and are now carrying it out. So far, we are still right on schedule."

For further information please click here and nl/41 for the tunnelbuilder archive and also visit https://rijnlandroute.nl  and https://www.comol5.nl/. 10/21.

 




NEED QUALIFIED PERSONNEL?