On 26th November, a new record was set by a CREG TBM by boring 1318.7 m/month, The Gripper TBM with 8.03 m boring diameter has reached this new record while working on the Yinsong water supply Tunnel Lot. 4. The same TBM set a record back in May 2016 which was 1226 m/month.
The tunnel is 23km long and to date 16.657 km have been completed at an average rate of 710m/month. Since boring began, this TBM has passed 39 fault zones, 54 karst caves, as well as dealing with a large water inflow of 500 m³/h. The TBM and site team have had to contend with complex geology and hard working conditions at times in the winter it was -30℃. They have performed outstandingly well and have been highly praised for what they have achieved so far. For further information on CREG TBM please visit their website.
25.11.2024 Austria
27.11.2024 Poland
28.11.2024 Austria
03.12.2024 Austria
05.12.2024 France
05.12.2024 Germany
06.12.2024 United States
09.12.2024 France
09.12.2024 Austria
12.12.2024 Belgium
12.12.2024 Switzerland
13.12.2024 Norway
13.12.2024 Germany
15.12.2024 Austria
09.01.2025 Switzerland
15.01.2025 Germany
17.01.2025 Spain