On 26th November, a new record was set by a CREG TBM by boring 1318.7 m/month, The Gripper TBM with 8.03 m boring diameter has reached this new record while working on the Yinsong water supply Tunnel Lot. 4. The same TBM set a record back in May 2016 which was 1226 m/month.
The tunnel is 23km long and to date 16.657 km have been completed at an average rate of 710m/month. Since boring began, this TBM has passed 39 fault zones, 54 karst caves, as well as dealing with a large water inflow of 500 m³/h. The TBM and site team have had to contend with complex geology and hard working conditions at times in the winter it was -30℃. They have performed outstandingly well and have been highly praised for what they have achieved so far. For further information on CREG TBM please visit their website.
02.01.2025 Czech Republic
09.01.2025 Switzerland
14.01.2025 Poland
15.01.2025 Romania
15.01.2025 Germany
17.01.2025 Spain
17.01.2025 Switzerland
20.01.2025 Switzerland
23.01.2025 France
27.01.2025 Switzerland
31.01.2025 Norway
10.02.2025 Switzerland
20.02.2025 Germany
06.03.2025 Germany
01.04.2025 Poland
16.05.2025 Switzerland