Electric Power Company of the South (Egesur) has awarded the EUR102 million contract to build the Moquegua 1 and 3 hydroelectric power plants in Peru, which have a total installed capacity of 34 MW, to the consortium composed of Sacyr (Spain) and GCZ Ingenieros (Perù).

Duration of the contract is 30 months. The Moquegua 1 project a hydroelectric power plant (CHM1) will be 15.3 MW of power. This project will include connection work with the current Huaracane channel, a conduit of 8,360 m, with three tunnels totalling 1,800 m in length, the engine house, the electric substation and the transport line.

The Moquegua 3 project (CHM3), is to supply 18.7 MW of power, and includes a water intake on the Sajena creek, a conduit of 7,211 m, with a tunnel of nearly 2,660 m, a machine room and unloading works to the Sajena ravine. In addition, an electrical substation and a transport line will be also built.

Visit http://www.sacyr.com and http://www.egesur.com.pe. 30/19.

 

http://www.sacyr.com=>http://www.sacyr.com/es_en/Channel/News-Channel/news/featuresnews/2019/Adjudicacion/20190719_Hidroelectricas_Peru.aspx

 

http://www.egesur.com.pe=>http://www.egesur.com.pe/SitePages/Proyectos%20de%20Inversi%C3%B3n.aspx



Permalink