Design and construction contract value $430 million awarded to Bouygues/Koop for 8 km-long, 14.9 m-diameter single-bore, twin-track tunnel below the water table in sand and alluvium using NFM Slurry TBM to be delivered in 2001. This will probably be the largest TBM built to date. Contract duration 5.5 years for railway commissioning in May, 2005. Visit www.framatome.fr January 2000.