Contract notice, deadline 27.03.2019, for the design and
construction of underground structures (tunnels and stations) 4,591 km of
length (approx.) from South of Tannery Road station to North Ramp (km16,822.521
m to km, 21,413.298 m) including allied works and 4 Nos of UG Metro Stations
viz., Tannery Road, Venkateshpura, Arabic College and Nagawara in Reach-6 line
of Bangalore Metro Rail Project, Phase-2, (R6-CC-02)-RT04. The duration of the
contract is from 01.07.2019 to 31.12.2022 + DLP (defects liability
period) of 12 months. Contact BMRCL, Bangalore, tel
+91-80-22969300/301, fax +91-80-22969222, email contracts@bmrc.co.in. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=027743-2019.
Bid n.
BMRCL/Phase-2/Reach-6/UG/TNL&STN/(R6-CC-02)-RT04/2019/42. 04/19.