Excavation of the $140 million, 5.2 km-long El-Achir railway tunnel, 150 km southeast of Algiers, completed two years behind schedule due to tough regulations on the use of explosives, unexpected geological problems and travel restrictions imposed on Italian contractors Lesi and Dipenta. Tunnel part of the north bypass railway system, and longest of its kind in Africa. 44/01.