Tunnelbuilder Promoting the world's tunnelling industry to a huge qualified audience

View the Spanish Tunnelbuilder website View the Italian Tunnelbuilder website

Archive Search

Australia

Australia, Sydney - au/12

Northside Storage - Tunnel - TBM

  Interceptor sewer and access tunnels, in total 20km of TBM drive using three Wirth machines of diameters 6.57m, 6.33m and 3.8m. Access tunnels driven by roadheader. Spoil from North Head excavations will be transferred to a loading wharf. Small TBM started October 1998 and large machines early-1999. Completion 2000. Dec 1998.   First breakthrough recorded at Little Manly Point by 3.8 m Wirth after 1.2 km drive in 10 weeks. Advances of 40 m per 10 h shift, and cutter life consistently more than 200 m. Machine upgraded for 7.5 km Lane Cove tunnel starting June, 1999. The second and third Wirth TBMs will commence their drives in July and august, 1999. Northside Storage Alliance comprises Transfield, Montgomery Watson, Connell Wagner and Sydney Water. June 1999.   Connell Wagner reports project will capture sewage from four major overflow points for transfer to North Head STW and discharge through ocean outfall. Ten shafts, 3 km of access tunnels and two underground pumping stations completed. Project now has a fourth TBM, a Robbins remanufactured by Terratec and increased in diameter from 5.5m to 6.5 m. This is a double shield with multiple modifications by Terratec to suit the Sydney sandstones. Due to the tight delivery requested, CTS of Kent, WA, USA assisted with design services.   The Wirth 3.8 m and 6.56 m TBMs are consistently achieving 250 m/week, and all three are now on 2 x 12 h/day operation. The 180 m-high, 650 t/h vertical shaft conveyor at North Head is the longest in the southern hemisphere, possibly in the world. Most of spoil removed by barge for reuse inland. December 1999.Contractor reports final breakthrough on Sunday, 16th July to complete 20 km of storage tunnel and all other tunnelling on the project within a two-year span. Total excavation 1.8 million t, or 720,000 cu m, of sandstone and shale, one-third by roadheader and two-thirds by TBM. Visit www.connellwagner.com and www.wirth-drilling.com July 2000.



Permalink

Portugal

Portugal, Funcho - pt/17

Water Transfer

Connection between Funcho and Oudelouca dams planned by Instituto da Agua should be awarded late-2000. Traditional excavation with rockbolts and shotcrete for 8.3 km-long, 3 m-diameter tunnel expected to commence February, 2001 at budgeted cost of $20 million. October 1999. Open tendering for 8.15 km-long, 3 m-diameter headrace tunnel, deadline 21st May, 2000. Contact Instituto de Agua, Lisbon fax +351 2184 80825. Note change of area code. April 2000.  Award of design/build contract for 8.1 km-long, 2.3 m-diameter aqueduct to consortium of Spie Batignolles, Rosa Ramalho Cobetar, and Etermar. Visit www.inag.pt 19/01.Spie Batignolles Europe reports completion of tunnelling and good progress with 2.4 m-diameter concrete lining using 3 x 24 m-long CIFA formworks. 8 km-long tunnel was completed in 15 months using a Terratec-refurbished Robbins 3 m-diameter hardrock TBM and Clayton 8t battery locomotives with Valente rolling stock. TBM averaged 27.5 m/day, with best day of 96.8 m and best month of 1,062 m. Heavily folded schistose ground and 258 m-wide fault negotiated with 1.8 m-long Swellex bolts, steel arches and shotcrete applied using Aliva 262 and 246 machines. More from www.spiebatignolles.fr/entreprise/europe.asp 38/03.



Permalink