On April 26, TBM Elsie arrived at Arbutus Station and completed her journey from the future station Great Northern Way-Emily Carr for the Broadway subway project in Vancouver. Click here and ca/38 ...
More Information
TBM Phyllis arrived at Cypress Street near the future Arbutus Station on March 20, completing her journey from the tunnel portal at the future Great Northern Way-Emily Carr Station. TBM Elsie is ...
More Information
The Broadway Subway Project Corporation (BSPC) is extending the Millennium Line from VCC Clark Station to Arbutus Street. The Project scope includes 700m of elevated guideway extending west from the ...
More Information
The first of two TBMs has broken through at the future Oak-VGH Station, achieving another milestone for the Broadway Subway Project.
The machine, named Phyllis, has reached the fourth ...
More Information
On 26/05/2023 Phyllis, the second of two massive TBMs that are excavating twin tunnels for the Broadway Subway Project, broke through to the future Broadway-City Hall Station, marking another ...
More Information
On April 14, 2023 Elsie, one of two TBMs constructing the twin tunnels for the Broadway Subway, brokethrough to the future Broadway-City Hall Station, that will be the busiest and largest station on ...
More Information
Press Release - Phyllis, the second of two tunnel-boring machines (TBMs) that are constructing twin tunnels for the Broadway Subway Project, broke through to the future Mount Pleasant Station early ...
More Information
A first major milestone has been reached by the Acciona Ghella Joint Venture on the Broadway Subway Project. Elsie, the first of two 150-m-long TBMs that began excavating for the Broadway Subway ...
More Information
Last week on the 14/10/22 Elsie, Broadway Subway Project Corporation's first TBM, was launched at GNW (Great Northern Way)-Emily Carr Station. This was the start of the tunnel excavations to ...
More Information
At the end of May the 2nd and final shipment of TBM parts for the Broadway Subway Project arrived! Now assembly of the first TBM is under way at the future GNW-Emily Carr Station site. On 14/06/2022 ...
More Information
The first shipment of parts for the TBM that will dig the Broadway subway project tunnels has arrived in British Columbia.
The TBM components left Germany on 25/02/2022 and sailed ...
More Information
The Broadway Subway project is an extension of the
Millennium Line and a key link in Metro Vancouver’s transportation system. The
5.7-km line will extend the existing SkyTrain system ...
More Information