Three private-sector teams will be invited to submit
technical proposals and prices to design and construct improvements to the I-64
(Interstate 64) corridor between I-664 in Hampton and I-564 in Norfolk to provide additional capacity
throughout the corridor, including a new four-lane bridge-tunnel complex
approximately 5.63 km (3.5 miles) long and generally parallel to the existing
Hampton Roads Bridge Tunnel (HRBT) which is to be widened.
The Virginia Department of Transportation (VDOT) has
concluded its evaluation of Statements of Qualifications (SOQs) with the
shortlisting of private-sector teams, with three submitting SOQs to the
department on March 2, 2018, in response to a Request for Qualifications (RFQ)
dated Dec.15, 2017.
The RFQ gave the teams the option of submitting an SOQ under
both or either a Bored Tunnel construction method or an Immersed Tube Tunnel
construction method. Both construction methods are currently under
consideration by the department. The shortlisted teams, in alphabetical order,
are:
1. Hampton Roads Capacity Constructors: Lead contractors:
Fluor Enterprises Inc. / The Lane Construction Corp. / Traylor Bros. Inc. /
Dragages Civil Works Virginia Inc; Lead designer: AECOM Technical Services Inc;
Design support: Michael Baker International / Royal HaskoningDHV and Witteveen+Bos
Joint Venture / Mueser Rutledge Consulting Engineers
*Shortlisted for Bored Tunnel and Immersed Tube Tunnel
construction methods.
2. Hampton Roads Connector Partners: Lead contractors: Dragados USA Inc./ VINCI
Construction Grands Projets SAS / Dodin Campenon Bernard SAS Joint Venture;
Lead designer: I-64 Design Joint Venture (HDR Engineering Inc. / Mott
MacDonald); Design support: Whitman Requardt and Associates LLP / Harris Miller
Miller & Hanson Inc. / Precision Measurements Inc. / AI Engineers Inc. /
GET Solutions Inc. / Mattern & Craig / Athavale Lystad & Associates
Inc./ Diversified Property Services Inc.
*Shortlisted for Bored Tunnel and Immersed Tube Tunnel
construction methods.
3. Skanska Kiewit Joint Venture: Lead contractors: Skanska
USA Civil Southeast Inc. / Kiewit Infrastructure Co.; Lead designer: WSP USA
Inc. Design support: COWI / Vanasse Hangen Brustlin, Inc / CAPITA
*Shortlisted for Immersed Tube Tunnel construction method
All three teams will be invited to submit detailed technical
proposals and binding prices in fall 2018 for one tunnel construction method.
Further information on the procurement will be provided in a draft Request for
Proposals (RFP) targeted for release in May 2018.
The HRBT expansion construction will build a new four-lane
bridge-tunnel and widen the existing four-lane segments of I-64 between
Settlers Landing and I-564, to ease congestion between Hampton and Norfolk. The
contract award is anticipated in early 2019 with project completion targeted in
2024.
For further on the HRBT Expansion Project procurement
process, visit http://www.p3virginia.org/projects/hampton-roads-bridge-tunnel-2/.
For more about the Hampton Roads Bridge-Tunnel Expansion Project, visit http://www.hrbtexpansion.org/ and http://www.p3virginia.org/projects/hampton-roads-bridge-tunnel-2/.
19/18.