On the 24.02.2016 TBM 6 arrived in Sports City Station on the Gold Line Doha Metro Project. The TBM has excavated 1614 m in 73 days, with 10 Fridays on maintenance, with an average of 22meters per day and 15 rings per day.
The maximum monthly advancement was in January 2016 with 730 m, the maximum weekly advancement was from 6 to 11 February with 201 m in 6 days with an average of 33 meters per day and 22 rings per day. In 30 days, from 16.01.2016 to 16.02.2016, the TBM was driven 920 m which was 28.7 meters per day. For further information visit http://www.selioverseas.com/. 10/16.
24.03.2025 Austria
24.03.2025 Croatia
24.03.2025 Greece
24.03.2025 Romania
26.03.2025 Finland
27.03.2025 Spain
28.03.2025 France
31.03.2025 Sweden
01.04.2025 Poland
01.04.2025 Germany
04.04.2025 Austria
07.04.2025 France
07.04.2025 Germany
07.04.2025 Spain
08.04.2025 Netherlands
11.04.2025 Italy
11.04.2025 Switzerland
14.04.2025 Switzerland
14.04.2025 Austria
24.04.2025 Romania
25.04.2025 Norway
25.04.2025 Switzerland
30.04.2025 Austria
14.05.2025 Switzerland
16.05.2025 Switzerland