On the 24.02.2016 TBM 6 arrived in Sports City Station on the Gold Line Doha Metro Project. The TBM has excavated 1614 m in 73 days, with 10 Fridays on maintenance, with an average of 22meters per day and 15 rings per day.
The maximum monthly advancement was in January 2016 with 730 m, the maximum weekly advancement was from 6 to 11 February with 201 m in 6 days with an average of 33 meters per day and 22 rings per day. In 30 days, from 16.01.2016 to 16.02.2016, the TBM was driven 920 m which was 28.7 meters per day. For further information visit http://www.selioverseas.com/. 10/16.