Kalininsko-Solntsevskaya metro line

24/08/2021

Tunnelling of the 2 km section between Pykhtino and Rasskazovka stations of the Kalininsko-Solntsevskaya metro line (Yellow line) in Moscow is 43% completed. To date, the TBM Rosa (6 m diameter) has driven 1153 m of the right running tunnel, and the TBM Natalia TBM - 717 m of the left tunnel. On the 5 km extension of the Kalininsko-Solntsevskaya line to the Vnukovo airport there will be two stations -  Pykhtino and  Vnukovo. They plan to complete the construction of both stations by 2023. The main structures of the Pykhtino station are 50% complete and the construction of monolithic structures at Vnukovo have begun. Work is now being carried out at all the construction sites for the new section of the yellow metro line. For further information visit https://stroi.mos.ru/ and https://mosinzhproekt.ru/. 34/21. 