TBM Grace
Tunnel boring machine (TBM) Grace arrived at Redcliffe
Station last month, breaking through the one-metre-thick eastern station box
wall to a cheering crowd of excited team members.
The TBM’s 15-strong crew guided her through the dry box, a
structure located adjacent to the station box and designed to correctly
pressurise the machine’s breakthrough. She made her final entry into the
12m-deep underground station around 2pm on May 9. This is the second time that
TBM Grace has surfaced since beginning tunnelling at Forrestfield mid-2017 – a
major milestone for the project. Click here to watch her big moment.
Since leaving Airport Central Station last year, TBM Grace
has tunnelled 2.6km and built more than 1600 concrete rings. She has now been
moved through the station box and will soon be ready to begin the final leg of
her underground journey.
Main escalators installed at Airport Central
Another major milestone has been achieved at Airport Central
Station with the installation of the main passenger escalators now complete.
The triple escalator system, which is 35m long and 15m high,
will connect the Skybridge to the concourse level. Once operational, it will
take 55 seconds to travel from top to bottom and a total of 8200 passengers can
be transported per hour. It is the longest single-span uninterrupted escalator
in the Southern Hemisphere.
View footage of the escalator installation here.
At platform level, concrete has been cast to form the walls
on both sides of the platform, with sections of the wall left open to allow for
the movement of multi-service vehicles (MSVs) while these continue to deliver
segments through the tunnel to TBM Sandy.
Redcliffe Station has welcomed TBM Grace
Recent works at Redcliffe Station were centred around the
scheduled maintenance of TBM Grace, including testing of mechanical and
electrical equipment, replacement of worn cutterhead tools and the installation
of a brand new screw conveyor. The 16m-long screw is used to transport
excavated material away from the front of the machine.
TBM Grace has also received a number of visitors since
resurfacing, including her namesake six-year-old Grace McPhee, as well as
Premier Mark McGowan and Transport Minister Rita Saffioti, who were on site to
announce this major milestone for the project.
Preparation works are now underway for the TBM to leave the
station box in the coming week. She is already lined up at the western station
box wall and installation of the thrust fame, used by the machine to push
forward, has commenced.
At the site of the station’s future 500-bay car park asphalt
works are ongoing and the first prime coat has been sprayed for both the
parking area and the entry.
Structural works underway at Forrestfield
At the northern end of the Forrestfield site, just above the
tunnel entries, bricklaying has been completed for the first level of the
tunnel portal building, allowing for the concrete slab of the next level to be
poured.
Also above ground, and clearly visible from Dundas Road, is
a large scaffolding structure in the centre of the station platform. The
structure was erected to support formwork for the suspended concourse slab.
With the concrete slab now poured, focus has shifted to preparation works for
the installation of the 11m-long escalator connecting the concourse and platform
levels.
Construction of the steel structure for the station's lower
roof has also commenced, with the main roof expected to be installed in the
second half of this year.
Earlier this week Transport Minister Rita Saffioti announced
the Metropolitan Redevelopment Authority’s (MRA) Midland Redevelopment Area
will extend to include areas around Bayswater and Forrestfield stations and
become METRONET East. More information on this development is available here.
Bayswater Junction pours near completion
With winter rains finally here, concrete pours for the dive
structure at Bayswater have been moved under cover. One of the remaining
sections of the base slab, located underneath the Midland Line overpass, was
finalised this week and is now curing. The final three pours are scheduled to
be completed by the end of the month.
Meanwhile work has commenced to construct the noise wall
located adjacent to Whatley Crescent. A mechanical rig is currently onsite
drilling the 3m-deep holes required to secure the post and panel structure to
the ground. The project team recently consulted with the local community
regarding the colour of the noise wall. A choice of three individual colours or
a pattern using all three colours intermittently was presented and, after all
votes were tallied, the community decided in favour of the alternating pattern.
The wall panels will be painted once installed, with works due to be completed
around the end of June.
Second cross passage fully excavated
The project's second tunnel-to-tunnel cross passage, located
east of Perth Airport's terminals 1 and 2, has now been fully excavated. After
spraying the cross passage's walls with concrete and installing steel fixings,
waterproofing works were completed. Construction of the concrete base slab for
the 10m-long link between the two tunnels will now occur, before the final
concrete lining can be installed.
While these works are ongoing until mid-July, a second cross
passage crew has cut through the diaphragm wall at Airport West Emergency
Egress Shaft and commenced excavation to TBM Sandy's tunnel.
Click here, here and au/34 for the tunnelbuilder archive.
Also visit https://www.forrestfieldairportlink.wa.gov.au/.
23/19.