Tunneling crews continue to make progress on both tunnels between the Roosevelt Station site and the U District Station site for the Northgate Link Extension in Seattle.
TBM Brenda is just south of NE 50th Street and Pamela is north of NE Ravenna Boulevard. Brenda is expected to arrive at the U District Station site in October and Pamela by early next year.
Crews continue to pour the concrete base and install drainage in the future northbound tunnel between Roosevelt Station and the Maple Leaf portal. Click here and us/42 for tunnelbuilder archive.Visit http://www.soundtransit.org/ . 40/15.
28.04.2025 Austria
28.04.2025 France
28.04.2025 Germany
30.04.2025 India
30.04.2025 Austria
30.04.2025 Switzerland
02.05.2025 Germany
05.05.2025 Macedonia
06.05.2025 Germany
07.05.2025 Germany
09.05.2025 Germany
09.05.2025 Switzerland
09.05.2025 Poland
13.05.2025 Germany
14.05.2025 Poland
14.05.2025 Switzerland
16.05.2025 Switzerland
16.05.2025 Italy
22.05.2025 Austria
23.05.2025 Switzerland
26.05.2025 Norway
26.05.2025 Czech Republic
28.05.2025 Italy
05.06.2025 Iceland
16.06.2025 Spain
17.06.2025 Italy
17.06.2025 France
19.06.2025 France
19.06.2025 Italy
27.06.2025 Switzerland
28.07.2025 Brazil