Invitation for Expressions of Interest, deadline 23.07.2009, for participation in 38-42 MW Mtkvari Hydro Power Plant Construction Project at Samtskhe-Javakheti Region on the river Mtkvari. The project includes a 9.5 km-long derivational tunnel and an 80 m-long tailrace tunnel. For more information contact Mtkvari HPP LLC in Tbilisi, Georgia, tel +995 32393256, mob +995 95309950. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=178403-2009 29/09.
Robbins 5.3 m-diameter main beam TBM with continuous conveyor underway on 5.5 km-long headrace drive through slate, sandstone and malm at difficult location in Kazbegi mountains, 1,700 m ASL and 160 km from capital Tbilisi. 60 MW plant, which will draw water from Tergi river near Russian border, will be operational in 2016. Read the press release and visit www.robbinstbm.com. 23/12.