On 12.11.2013 TBM excavation started for the Maddalena survey tunnel in Chiomonte on the Lyon-Turin line. TBM parts were brought to site on 131 abnormal loads over the period July to September.
The 385 t, 2,205 KW, 200 m-long Robbins TBM has a cutting head equipped with 42 off 19 in-diameter cutters to tackle the 7.3 km drive over the coming two years. Click here for a video, here, fr/11 and it/80 for tunnel builder archive. Visit www.ltf-sas.com. 47/13.
28.04.2025 Austria
28.04.2025 France
28.04.2025 Germany
30.04.2025 India
30.04.2025 Austria
30.04.2025 Switzerland
02.05.2025 Germany
05.05.2025 Macedonia
06.05.2025 Germany
07.05.2025 Germany
08.05.2025 Austria
09.05.2025 Germany
09.05.2025 Switzerland
09.05.2025 Poland
13.05.2025 Germany
14.05.2025 Poland
14.05.2025 Switzerland
16.05.2025 Switzerland
16.05.2025 Italy
22.05.2025 Austria
23.05.2025 Switzerland
26.05.2025 Norway
26.05.2025 Czech Republic
28.05.2025 Italy
05.06.2025 Iceland
16.06.2025 Spain
17.06.2025 Italy
17.06.2025 France
19.06.2025 France
19.06.2025 Italy
27.06.2025 Switzerland
28.07.2025 Brazil