The first two phases of turning the 3,000 t TBM Martina through 180 degrees have been completed at the Sparvo tunnel on the A1 motorway Variante di Valico, Italy.
Contractor Toto SpA Costruzioni Generali is employing an innovative moving system based on air cushion technology, designed and built by Palmieri Group. The Palmieri system of pneumatic sliding steel cradles on 80 air cushions is facilitating rotation of the 15.6 m-diameter TBM on a special low-friction sliding surface laid by Toto. The TBM will then be moved to the launch position for the second tunnel drive, towed by two trucks and stabilized by other motor vehicles as a drift checking system. With traditional techniques the operation would have taken some months, whereas the Palmieri moving system has reduced this to just a few days, maximizing TBM availability and minimizing overall excavation time. Excavation of Sparvo tunnel is expected to be completed by June, 2013. Click here for the video of first shifting phase on 27th September. For more click here and it/21. Visit www.totospa.it and www.palmierigroup.com. 42/12.
28.04.2025 Austria
28.04.2025 France
28.04.2025 Germany
30.04.2025 India
30.04.2025 Austria
30.04.2025 Switzerland
02.05.2025 Germany
05.05.2025 Macedonia
06.05.2025 Germany
07.05.2025 Germany
08.05.2025 Austria
09.05.2025 Germany
09.05.2025 Switzerland
09.05.2025 Poland
13.05.2025 Germany
14.05.2025 Poland
14.05.2025 Switzerland
16.05.2025 Switzerland
16.05.2025 Italy
22.05.2025 Austria
23.05.2025 Switzerland
26.05.2025 Norway
26.05.2025 Czech Republic
28.05.2025 Italy
05.06.2025 Iceland
16.06.2025 Spain
17.06.2025 Italy
17.06.2025 France
19.06.2025 France
19.06.2025 Italy
27.06.2025 Switzerland
28.07.2025 Brazil