Australia - Halfway mark reached on Western Sydney Airport project

13/03/2024
Australia - Halfway mark reached on Western Sydney Airport project

TBMs Catherine and Marlene are halfway to St Marys after each building 2.4 km of tunnel for the Sydney Metro - Western Sydney Airport project. They broke through at the Claremont Meadows services facility shaft, after launching at the Orchard Hills Station site in July and August 2023 respectively.

Tunnelling at an average speed of 120 m a week, the TBMs are carving out the twin 4.3-km tunnels to the new St Marys Metro Station site.

They have removed 600,000 t of spoil and installed 17,820 precast concrete segments as they tunnelled under the M4 Motorway to the 21-m-deep services shaft.

The TBMs have now traversed the 16-m-diameter services shaft, which is used to supply materials like concrete and steel and have been relaunched to complete their journey. They are expected to reach St Marys in mid-2024. 

A further two TBMs, Eileen and Peggy, are building the two 5.5-km southern tunnels from Airport Business Park to the Aerotropolis. 

When the new metro line opens, passengers will have a world-class transport option directly to the new Western Sydney International (Nancy-Bird Walton) Airport and major job hubs, including the new Aerotropolis.

 The Sydney Metro - Western Sydney Airport line is targeting to be operational when the new international airport opens for passenger services, with the end-to-end journey time between the St Marys Metro Station and Aerotropolis Station to take around 20 minutes.

For further information please click here to follow the journey of on Western Sydney Airport TBMs, here and au/11 for the tunnelbuilder archive. Visit https://www.sydneymetro.info and https://www.sydneymetro.info/westernsydneyairportline. 11/24.    

 