Metrosur Construction Contracts - Text Only
The following project reports are available for free reproduction by arrangement with Comunidad de Madrid. For permission to reprint, and for suitable pictures to accompany each article, contact manuel_melis@metromadrid.es
From Leganés to Alcorcón and Mostoles
Contract 1, Sectors XI, XII and I
Contractor ACS Vias
The XI, XII
and I sectors of Contract 1 add up to 9.637 km, and comprise 23.6% of the total
length of the Metrosur circle line. The project will cover the transport demand
of 50% of the Alcorcón town population of about 141,000 inhabitants.
These important works were awarded to a joint venture between ACS and Vías
y Construcciones. ACS was originally involved in the Madrid Metro Line 9 extension,
between Pavones and Puerta de Arganda, and is using the same 9.38 m-diameter
EPB TBM at Metrosur. This has been a great advantage to the present joint venture,
not only for production planning, but also for the availability of experienced,
skilled personnel, for both operations and maintenance. This previous experience
has improved both the startup and the construction rates, as the main soil characteristics
are very similar to those encountered on Line 9.
Project Description
This sector of the Metrosur line passes through the towns of Leganés,
Alcorcón and Mostoles, starting with the Leganés 6 station at
San Nicasio, and ending at the entrance to the Mostoles 1 station at Los Rosales.
The Mostoles 1 station itself is part of the contiguous contract 2.
The first section of 1,726 m in length, starting at the Leganés 6 station
and ending at the first shaft, is being constructed using the cut and cover
method in open country, outside the town's boundaries. The remaining 7,911 m
of tunnel are being constructed using the TBM.
Contract 1 also involves the construction of five stations. One of these stations,
Alcorcón 1, is the connection point between Metrosur and the Madrid Metro
Line 10. Another one, Alcorcón 3, is the interchange with the metropolitan
surface railway network.
The project allows for the construction of two future stations, one in Leganés
and the other one in Mostoles, providing suitable horizontal and rectilinear
sections. The Metrosur stations are designed for cut and cover construction,
and are located to offer a maximum cover of the transport demand. The cut and
cover method permits closer control of the construction costs and deadlines,
reducing the risks of time and cost overruns.
According to the principles and criteria devised for the earlier Madrid Metro
extensions undertaken between 1995 and 1999, the stations' functionality is
increased through avoiding long connection corridors, and through integrating
all the facilities within a unique volume, delimited by diaphragm walls. According
to the same philosophy, the Metrosur stations were designed in suitable locations,
at about 14 to 16 m of depth from surface to the rail elevation. The planned
depth is governed by the minimum soil cover required at the TBM breakthrough
positions. The TBM also determines the ticket hall slab elevation of about 7
m above the rail level.
The project also provides three electrical sub-stations, one located in the
first shaft, and the other two in the Alcorcón 1 and Alcorcón
3 stations.
The most important of the affected facilities is the military railway, parallel
and coincident with the tunnel in its first 500 m. The railway will be diverted
temporarily, and then repositioned on its initial location after completion
of the Metrosur works.
Among the remaining stations, the positioning and characteristics of Alcorcón
1 station affect a number of important facilities. Prior to the start of the
works, the diversion of facilities such as water and gas pipelines, electrical
lines and wastewater conduits was undertaken, and several traffic restrictions
had to be imposed at different stages.
The first shaft is located within Leganes town limits, at about 1.7 km from
the start point of the contact. Work on the second shaft started early, at a
location situated at about 5 km from the first shaft, in order to reduce the
supply lines length during the tunnel completion. The TBM will be taken out
through a third, much smaller shaft, before reaching the Mostoles 1 station.
Railway Design
The EPB tunnel is being excavated in a 9.38 m circular section with a reinforced
concrete lining of 8.43 m internal diameter rings, each formed by 7 curved elements,
0.32 m thick. The annulus between the concrete rings and the excavation is injected
with cement grout.
The cut and cover tunnel is being built with diaphragm walls and superior and
inferior vaults. The tunnel width, or horizontal distance between the diaphragm
walls, is 7.8 m, and the maximum height is 6.5 m. The height of both types of
tunnel is designed to allow twin-track railway passage of the new 6000 series
trains.
The railway design criteria have been established by Metro de Madrid. The design
is constrained by the location of the stations; the geotechnical characteristics
of the soils; the connection and design conditions compatible with contiguous
sectors; the Metrosur - Line 10 crossing; and functional aspects, such as facilitating
the users' access from the exterior by placing the platforms as close to the
ground level as possible. The urban structure, and particularly individual building
foundations, have to be taken into account, together with the geography of existing
facilities. It is also intended to minimise the distances inside the Metrosur
- Line 10 and Metrosur - metropolitan railway interchanges.
The design criteria are: minimum curve radius 300 m, exceptionally 280 m; maximum
gradient 3.5%; minimum vertical connection radius: Kv = 2,000 m; length of stations:
minimum 115 m; transversal level difference of the railway: max. 150 mm; uncompensated
transversal acceleration: 0 m/s, exceptionally a maximum of 0.65 m/s; transversal
acceleration variation in transition sectors: 0.17 m/s³, exceptionally a maximum
of 0.20 m/s³; heights corresponding to the 6,000 series train; railway transversal
slope: 1.5 mm/m, exceptionally 2.0 mm/m.
The geotechnical study carried out for this sector defined the ground as typical
Madrid subsoil, with sands, clayey sands and sandy clays.
Difficult Structures
Leganés 6 station is located on the limit of the San Nicasio neighbourhood,
in a zone characterised by a high urban development process. It has two accesses
from the street level to an underground hall that forms the first station level.
The access to the station platforms from the hall is by means of stairs and
mechanical elevators.
Passengers' routes were minimised, and facilities integrated, to provide a unitary
vision from inside the station. The architectural solution is based on the double
height perception, which allows a better survey of the traffic.
The cut and cover solution was chosen in order to place the station below the
military railway, which has been diverted. The dimensions of the station structure
are delineated by the 0.8 m-thick diaphragm walls, which form an enclosure some
129.4 m-long, with a maximum width of 33.8 m. The roof slab of the station is
calculated to support both a 1.30 m-deep earth embankment, and the anticipated
military railway traffic loads.
Alcorcón 1 station is the most difficult construction, due to the requirement
for a double station, as the interchange between Metrosur and Line 10. It is
a cross-shaped station, where the lower line corresponds to Metrosur, and the
upper one to the metro Line 10.
The Metrosur section of the station is 128 m-long, and is at depths ranging
from 22.13 m to 22.55 m from the ground level. The Line 10 station has a total
length of 120 m, and is located between 13.52 m and 14.10 m-deep.
The structure is a continuous, 0.8 m-thick, diaphragm walled enclosure. The
roof is formed by prefabricated beams, which support the loads from a 0.80 m
to 1.50 m thick earth embankment, as well as from traffic and other urban facilities.
The station has three accesses to its two main halls serving Line 10, and the
Metrosur platforms are accessed by means of stairs and mechanical elevators
in both circulation directions.
The TBM excavated through the Alcorcón 1 station. The complexity of the
station structure, and its proximity to the first shaft, resulted in the machine
reaching the station before excavation of the box had been completed. The prefabricated
segmental rings of the tunnel lining were removed once the station excavation
reached the invert elevation of the tunnel.
Alcorcon Stations
Alcorcón 2 station is 125.20 m-long, and is positioned some 13.57
m to 15.84 m deep, below the Avenida de Leganés, and between the Principe
Don Juan Carlos and Avenida de Lisboa streets. It has a unique access, located
in the Avenida de Leganés. It is a rectangular-shaped station, due to
its proximity to the neighbouring buildings, and was roofed with a cast in-situ
reinforced concrete slab.
Alcorcón 3 station is an interchange station between Metrosur and the
existing metropolitan railway station. It is located in the Avenida de Mostoles
Street, and also caters for the Alcorcón Hospital demand. Its shape is
similar to most of the Metrosur stations: rectangular with a sensible widening
to permit the staircase location. The roof is formed of prefabricated beams,
and the mezzanine level was cast in-situ from reinforced concrete. An underground
passage will allow access to both platforms of the station from the metropolitan
railway station.
Alcorcón 4 station is located within the Juan Carlos I University and
next to the Alcorcón Parque Oeste commercial centres. It is placed completely
underground, and has one access covered by glass pavilion, linked to the platforms
by means of mechanical elevators. The general concept is similar to the Alcorcón
3 station.
EPB Excavation
For the tunnel, the choice of the construction processes was based on previous
experience, acquired during the completion of the Metro de Madrid extension
plan from 1995 to 1999.
In this particular case, this expertise has a special significance, not only
in terms of geotechnical properties of the soils, but also with regards to what
is considered to be the best experience to date, worldwide. The previous works
yielded exemplary results, with high construction rates and early completions,
bettering the most optimistic predictions. The costs were substantially lower
in Madrid than those of the closest available references in London, Athens and
Lisbon.
The Metrosur Contract 1 sector is being constructed using a 9.32 m-diameter
EPB TBM, working with or without earth pressure, to produce a tunnel with an
8.43 m internal diameter reinforced concrete segmental lining.
Each lining ring is made of seven curved segments, 0.32 m thick and 1.50 m wide.
The gap between the excavation surface and the concrete rings is injected with
cement grout, having the double function of spreading the ground pressures evenly,
and waterproofing the tunnel. Waterproofing is also enhanced by means of neoprene
gaskets on the segments.
The segment fabrication facility is located close to the first shaft. The plant
is designed for a daily production of 18 rings/day, and has a storage capacity
of 585 complete rings.
The total length of the TBM is 125 m, and its weight is around 1,500 t. To advance,
the machine uses the forward pressure generated by 13 pairs of hydraulic cylinders,
which react against the last-placed ring. To get excavation underway from the
start shaft, a steel reaction frame was erected at the tunnel portal.
Cut and Cover
The section of tunnel between the Leganés 6 station and the first
shaft was constructed by the cut and cover method. First, the diaphragm walls
were installed, followed by placing of the concrete roof. Once the upper vault
was completed, excavation between the diaphragm walls was possible, and the
invert could be concreted.
Two construction methods were used. The one method involved excavating a trench
down to the top of the diaphragm wall, or to the covering vault level. The main
advantage with this method is that no shear stresses are transmitted to the
diaphragm walls. In the second case, braces are placed across the diaphragm
walls in order to support the vault and transmit the shear stresses from the
ground. The diaphragm walls and upper vault are 0.60 m thick, while the inferior
vault is 0.50m thick.
The stations are constructed from the surface in a diaphragm walls and piles
enclosure. After removing the piles and diaphragm heads, the ground is excavated
down to the main hall elevation, and the station roof formed using prefabricated
beams. Excavation is then undertaken to reach the invert elevation.
The Alcorcón 2 station is covered by a concrete roof which was placed
in-situ before excavation commenced, in order to keep any deformation within
an acceptable range. With the exception of the Alcorcón 1 station, all
of the stations were completed before the TBM drive reached them.
Contract 2, Sections II and III
Contractor FCC Construccion, SA.
Section II
of Metrosur contract 2 runs beneath the urban neighbourhood of Móstoles,
with a length of 3,173.8 m, starting at the screen wall entering the siding
yard located before the Móstoles-1 station, and ending at the entry gable
of the Móstoles-4 station. Section III is located within the districts
of Móstoles and Fuenlabrada, with a length of 4,128.8 m, starting at
the entry gable of the Móstoles-4 station and ending at the P.K. 4/160
to the west of Loranca.
In total, the length of Contract No. 2 is 7,302.6 m, in which five stations,
five tunnel ventilation shafts, four emergency exits and two pumping shafts
have been projected, as well as a link tunnel to access the future wagon sheds,
located in Loranca.
Route and Sites
The contract began with the construction of the Móstoles 1 station, located
close to the Rey Juan Carlos I University Campus, underneath the Tulipán
and Alcalde de Móstoles streets, where its access is situated. Four sidings
have been projected within the station enclosure, for the temporary parking
of rolling stock on both sides of the platforms. The depth varies between 14
and 22 m to track level.
The line tunnel that runs underneath the Parque Estoril II residential area,
at a depth of between 12 and 28 m, begins at the exit of the station. The ground
route traces a left-hand curve with a radius of 300 m, which connects with a
right-hand curve with a radius of 310 m, until reaching the entry gable of the
Móstoles 2 station, located behind the Renfe tracks of the C-5 Suburban
network line. The length of the tunnel between stations is 1,122.5 m. A continual
incline of 2.1% is maintained in terms of elevation. One emergency exit, and
one ventilation shaft in the PK 0/820, are located in this inter-station section.
The Móstoles 2 station occupies a space between buildings in Paseo de
Goya, next to the existing Renfe station in Móstoles, at a depth of 18
m, and involves a passenger interchange, with widening and restructuring of
the existing Suburban station.
The line tunnel ground route at the exit of the Móstoles 2 station traces
a right-hand curve, with a radius of 545 m, for 612.90 m until the Móstoles
3 station, located under the Plaza del Pradillo, in the historic centre of Móstoles.
The tunnel elevation begins with a 3.5% slope in the initial section, ending
with 0.5% on the final section, at a depth varying between 18 and 25 m. There
is a ventilation shaft in the PK 1+680.
The exit tunnel of the Móstoles 3 station traces a right-hand ground
plan curve, with a radius of 375 m, changing to a left-hand reverse curve, with
a radius of 300 m, connecting with the straight track of the Móstoles
4 station. The length of this tunnel between stations is 932.60 m, with a depth
varying between 13 and 24 m. The section starts with a 3.5% slope until it reaches
the PK 2+787, where a low point is created. From here, a 3.5% incline begins,
climbing to the station gradient, running underneath the buildings in the old
quarter of Móstoles. There is a tunnel ventilation shaft in the PK 2+569,
and a pumping shaft in the PK 2+788, in this inter-station section.
The Móstoles 4 station is located underneath the Villa Europa Park, situated
between the Río Sella and Río Ebro Streets, at an average depth
of 16.5 m. The needs of passengers visiting Móstoles General Hospital
have been taken into account when locating its access.
The tunnel section between the Móstoles 4 and Móstoles 5 stations
is 1,376.8 m-long. It starts with an extension of the station track into a left-hand
curve, with a radius of 300 m. This connects with the straight alignment of
Río Guadalquivir street, under which it runs until it reaches the building
land known as PAU-4. Here it turns to the left, on a curve with a radius of
700 m, to connect with the Móstoles 5 station. In terms of elevation,
the tunnel begins with a 0.82% incline, and ends in the last 500 m with 2.14%.
The tunnel depth varies between 9 and 26 m to track level. There is a ventilation
shaft in the PK 0+897, and an emergency exit in the PK 0+904.
The launch shaft for the TBM is located in the entry gable of the Móstoles
5 station, on the alignment of a future false tunnel. The Móstoles 5
station itself is located in the PAU-4 area, at a depth at track level of between
10 and 12 m.
From the exit of Móstoles 5 to the end of the route, 2,496 m of tunnel
are projected. This section starts with a 650 m radius right-hand curve until
the PK 2+400, connecting with a 710 m-long straight track that runs parallel
to the road from Móstoles to Humanes. This connects with a left-hand
curve until joining the Loranca Avenue alignment at the boundary line between
the districts of Móstoles and Fuenlabrada. This alignment then extends
to the intersection with the Pablo Iglesias Avenue, where the work in Contract
2 ends. The link tunnel for the proposed future wagon sheds in Loranca is located
on this last part of the alignment.
Rising from the exit of Móstoles 5 on a 0.5% slope, this increases to
2.65% at 590 m until it reaches the PK 2+875, where there is a low point from
which a 0.1% incline starts at 765 m, increasing to 3.3% in the last section.
There are two emergency exits in the PKs 2+533 and 3+256; a pumping shaft in
the PK 2+892; a tunnel ventilation shaft in the PK 2+977; and two rivers are
channelled over the tunnel in PKs 2+920 and 3+705, to avoid erosion. The average
depth of the tunnel varies between 12 and 14 m.
Geotechnical
Description
The land traversed by the new Metrosur line includes formations that are typical
of Madrid. Specifically, in the project section, detritus material is located
included in the facies of Madrid. This originated from the erosion of granite
and metamorphic reliefs in the Sierra de Guadarrama, produced by widespread
flooding. This is partially covered by other quaternary materials of colluvial
origin, and by anthropic fillings.
In terms of the research carried out, together with existing data, 30 exploratory
boreholes, with the continuous extraction of samples, were carried out at the
design stage, and another 20 boreholes at the work stage.
In agreement with the classifications of ground in Madrid, four types of different
material have been distinguished corresponding to the Tertiary age, as well
as quaternary anthropic fillings and alluvial deposits. The nomenclature used,
and the classification criteria, are as follows: Fillings; Alluvial; Miga sand
(fine < 25%); Tosquiza sand (25% < fine < 40%); Sandy Tosco (40% <
fine < 60%); and Tosco (fine >60%).
In the projected section, the sandy and clayey levels alternate. At the start,
and up to PK 2+100, alternations of sandy tosca and tosquiza sand predominate.
Between PK 2+100 and PK 2+800, toscos prevail. Between PK 2+800 of Section II
and PK 1+100, strata of miga sand alternating with tosquiza sand have basically
appeared. Between the latter point and PK 3+100, there is a succession of tosquiza
and sandy tosco levels and, in the final section, alternations of miga sand
and tosquiza sand prevail. On the surface, anthropic fillings of up to 8 m in
thickness have been located, along with alluvial soils with a depth of up to
5 m. Numerous water levels have been detected, which are retained over more
impermeable lower substrates.
Design Criteria
The design criteria established for the Metro Plan 1999-2003 have respected
the parameters defined in the previous plan, improving the geometric route parameters
to adapt them to type 6000 rolling stock, considering all of the improvement
determinants for the user, in terms of both functionality and safety. The sites
of the stations have been specifically studied, along with the geotechnical
characteristics of the soil, and the functional aspects of ease of access from
outside. Platforms are as close to the surface as possible, minimising runs,
and making easier interchanging with existing suburban networks, services, and
the urban structure.
The geometric parameters for the design of the route and the track are: minimum
ground plan curve radius, 300 m; maximum incline, 3.5%; minimum vertical agreement,
Kv 2,000 m; alignment at stations, horizontal and straight, minimum length 115
m.
Construction
Methods
The construction methods determined for Contract 2 are differentiated in two
large groups, according to effects on the surface. The underground section,
comprising EPB tunnels and four stations between screen walls, accounts for
63% of the work. The cut and cover section, comprising false tunnel, tunnel
between screen walls, and one cut and cover station accounts for 37% of the
works.
The underground section begins at the Móstoles 1 station and ends at
the pilot shaft located next to the Móstoles 5 station, with a length
of 4,958 m.
The tunnelling methods employed along this section are: line tunnel - EPB TBM;
shaft and gallery - traditional Madrid Method; stations - screen wall enclosure
using the upward-downward system and cut and cover.
Line tunnel boring is carried out using a 9.38 m-diameter EPB tunnel-boring
machine, which is the safest method for both operators and buildings. This method
presents the complete mechanisation of the processes of excavation, lining and
injection.
TBM Excavation
The machine consists of a large cutting head with the same diameter as that
to be excavated, 25% of its surface being taken up by the cutting discs. When
the cutting head turns on its shaft, whilst pushing against the ground, the
excavated ground is forced into the EPB chamber. Here it is treated with biodegradable
foam, creating a mousse that maintains the pressure on the working face.
The cutting head is followed by a shield, within which the tunnel lining is
erected. The lining consists of seven precast reinforced concrete segments that
form cylindrical rings, with an internal diameter of 8.43 m, 1.50 m in length
and 0.32 m in thickness. The segments are fitted with waterproofing gaskets
around their perimeter, and are joined together with steel bolts.
Forward motion is generated by means of hydraulically-powered jacking cylinders,
which push against the last ring of the positioned lining.
The process is as follows: the shield is launched from the pilot shaft using
an anchored steel reaction frame; ground is excavated by the rotating cutting
head discs under pressure from the jacking cylinders; the lining ring is erected
once the excavation cycle is finished. This process is repeated until the tunnel
is completed.
The main characteristics of the machine can be summarised as follows: pushing
jacks, 26 cylinders with 320 mm-diameter pistons; total pushing force, 10,000
t; feed rate 0-80 mm/min; cutting tools, 148-pick cutting wheel, double 17"
disks and two copy cutters; cutting wheel drive, 16,000 KNm torque; initial
starting torque, 20,000 KNm; installed output, 2,000 Kw; maximum rotation speed
2.4 rpm; 4,950 mm diameter bearing; electrical installation, 15 KV feed; installed
output, 3,700KVA; guidance system, Leica electronic laser.
The extraction system is a spiral auger conveyor with an external diameter of
1,000 mm. The spoil transport capacity is 663 cu m/h on a 1,200 mm conveyor
belt with 1,200 cu m/h capacity. The mortar injection system has double injection
pipes between the rings of segments and the ground and has a capacity of 5.6
cu m/h.
Madrid Method
This method is used to excavate connections from the line tunnel to the ventilation
and pumping shafts and emergency exit. The manual excavation rate can be adjusted
to the ground conditions, using planks, metal bracing and wooden props for temporary
support. The construction sequence is as follows: excavation of an auxiliary
advancing gallery in the top of the tunnel, shored with planks, wooden props
and metal bracing; widening of the advancing gallery until the entire section
is excavated, completing the shoring; lining and concreting of the arch; benching
excavation with a phase difference in relation to the face; excavation and concreting
of the sidewalls, using abutted supports to prop two adjoining half-rings of
the arch; excavation and concreting of the tunnel roof; and roof annulus injection.
The length of the ring, or incremental advance, is decided according to the
ground conditions.
Stations Between
Screen Walls
In the Móstoles 1, 2, 3 and 4 stations, a large screen wall enclosure
has been designed and configured, covered by reinforced concrete slabs, using
the cut and cover technique.
The planned construction stages are: service siding, service platform formation
and rail kerbs; excavation and concreting of screen walls and pile stacks; support
surface preparation, steel reinforcing and concreting of the roof slabs; restoration
of the surface for urban use; interior excavation up to concourse slab support
height; repair of support surface, steel reinforcing and concreting of the concourse
slabs and rams; excavation to roof height; shuttering, steel reinforcing and
concreting of the roof ready for passage of the tunnel-boring machine; construction
of interior structures, stairs and platforms; and masonry, installations and
finishes.
Cut and cover
The cut and cover section begins with the launch shaft located next to the Móstoles
5 station, and finishes at the end of the Contract in Loranca. It comprises
entirely false tunnel through open country, housed in a cutting excavated for
the purpose. The construction stages are: excavating up to the lower height
of the slab; reinforced slab shuttering and concreting; installation of the
shuttering formwork for the entire section; frontal shuttering; steel reinforcing
and concreting; waterproofing of sidewall and roof extrados; and filling and
compacting of ground to natural land height.
Tunnel Between
Screen Walls
Within the excavated section for the false tunnel, there are various areas with
isolated buildings that prevent the excavation of the cutting necessary for
the construction of the false tunnel. In these places, screen walls are necessary,
with the following work components: formation of service platform and rail kerbs;
excavation, reinforcing and concreting of the screen wall constituting the sidewalls
of the tunnel; installation of fastening beams at the crown of the screen wall;
open-pit excavation to lower surface height of roof; support surface preparation;
shuttering, steel reinforcing and concreting of the roof; filling and compacting
of ground to natural land height; internal excavation of the tunnel to roof
height; and floor cleaning, reinforcement, screen wall anchoring and concreting.
In the case of tunnels at any great depth, intermediate shoring is required.
Station With
Open-pit Excavation
This system was used in the construction of Móstoles 5 station, with
the following stages: cutting excavated to lower slab height; foundation shoe
and slabs laid; perimeter walls cast in the concourse area, and roof on station
body; centring and laying of concourse and roofing slabs; and ground filling
to natural land height. The method is completely opposite to that of the screen
wall station.
Ground Treatment
The detailed study of the buildings affected by the tunnel alignment was translated
into the definition of the areas with a potential risk of settling, in which
land treatments were projected to counteract possible subsidence induced by
construction of the tunnel. Four types of treatment have been used: compensation
grouting - underneath buildings crossed by the tunnel with little lining; jet-grouting
columns - next to buildings affected by settlement coverage; micro-pile screen
walls - next to buildings with superficial foundations cutting settlement coverage;
mortar piles and screen walls - EPB TBM repointing.
The period for work implementation is 30 months as of signing of the location
record on 23rd May, 2000, work completion being foreseen for 23rd November,
2002. The programmed terms are being met, with the situation at 15th July, 2001
being that listed in the chart.
Cut and Cover Between Fuenlabrada and Mostoles
Contract 2 - Section III - B1
Contractor Necso Entrecanales Cubiertas
In
April 2001, part of section III between km 2.84 and 4.16 was awarded to Necso
Entrecanales Cubiertas. This section is 1,320 m-long, of which roughly 1,100
m is in Mostoles, and 220 m in Fuenlabrada. It includes the line tunnel, two
emergency exits, a pumping shaft, a ventilation shaft and three junctions for
the future depot.
In the Fuenlabrada area, the tunnel runs at depths of 16 to 18 m under developed
areas, with buildings of heights up to four floors. In the Mostoles area it
runs beneath undeveloped land, and crosses the Fregacedos and Reguera gullies,
and the future Radial V road.
Geology
and Geotechnics
The catchment area, which occupies most of the province, is known as the Cuenca
de Madrid, and forms part of the Tagus river basin. It is filled with layers
of Tertiary sediments of significant thickness, whose character varies according
to the position in the catchment. Three types of facies can be readily distinguished:
the Madrid facies, consisting of arkosic sand of varying grain size, and grey-brown
or brown clay, locally identified with coarse sand and hardpan; the Intermedia
facies, consisting of highly-plastic brown and green clay, or peñuelas,
with intermittent layers of micaceous sand; and the Central facies, of a chemical
nature, consisting of chalk and chalky marl.
Section III is entirely located in areas of hardpan and sandy soils associated
with the Madrid facies. One of the main characteristics of these materials is
the structure. They cannot be classified as different strata, but appear as
a group of lenticular deposits of differing lateral continuity, which overlap
and alternate with sandy and clayey deposits. This makes it difficult to correlate
their position at different points.
On this section, the clayey soils predominate over the sandy layers, although,
in some areas, the latter are present in considerable thickness. Quaternary
alluvial deposits overlie the Tertiary material in the bottoms of valleys, accompanied
by anthropic fill, usually of little thickness, in urban areas and their surroundings.
The lithological features are as follows: Quaternary: compacted fill; uncompacted
anthropic fill; and alluvial. Upper/lower Quaternary: coarse sand; hardpan sands;
sandy hardpan; hardpan. These features are shown in the geological-geotechnical
profile.
Alignment
Design Criteria
The rolling stock that will be used on Metrosur is the 6000 type, which is the
latest design, and has the greatest capacity. This determines the minimum geometric
characteristics of the alignment, and the larger size allows carriages to be
evacuated faster in the event of accidents.
To provide sufficient cross-section for the 6000 Series rolling stock, the alignment
has to comply with stricter conditions than for the rest of the network.
The contract can be divided into two clearly different parts - in kilometre
order. The first 1.1 km, between the Reguera Gully and Paseo de Loranca, runs
at a depth of 14 m beneath undeveloped land in Mostoles. The tunnel is being
constructed using cut and cover. This section crosses the Fregacedos and Reguera
Gullies, which have been diverted. From Paseo de Loranca to the end of the contract,
for 220 m, the tunnel is being constructed between cut-off walls. This section
runs under Calle Alegria in Fuenlabrada, and has buildings on either side.
Monitoring equipment will provide information on movement, on the water table,
and on other data which help to detect the behaviour of the structure, and measure
any possible deviation from the anticipated parameters.
This equipment includes levelling benchmarks on the surface, gauges on buildings,
convergence marks in tunnels, ceramic pressure sensors where water is expected,
and pressure cells in the roof and floor. These devices have been fitted to
all of the buildings affected by construction.
The principal quantities of the contract are as follows:
False
tunnel
Tunnel between cut-off walls Excavation Fill Cut-off walls Prefabricated beams Concrete Steel bars Rail Elastic spikes |
1,100
m
220 m 449,000 m³ 270,000 m³ 6,131 m³ 1,080 m 70,000 m³ 2.8 t 5,500 m 5,500 u |
The
official estimate came to E21,577,330 and the contract was awarded at E20,463,940
(E = Euro). The contract duration is 20 months from the date of the survey on
24th May, 2001, so work should therefore be completed by 24th November, 2002.
The contract planning was based on the following outputs: open cut tunnel, 100
m/month; cut-off walls, 80 m2/day per team; superstructure, 700 m/month.
The construction methodology for open cut is sequenced as follows: floor slab;
haunches using traditional formwork; roof using mobile formwork. After construction
has been completed, the excavation is back-filled and the surface restored.
For tunnel between cut-off walls, the procedure for the excavation is cut and
cover. It consists of the following steps: the cut-off walls; roof slab; excavation
down to arch soffit level; construction of the arch.
For the depot junction the construction steps are: foundations; walls; placement
of prefabricated beams; upper slab; back-fill.
Loranca to Fuenlabrada in Cut and Cover
Contract 3 - Section IV - Sub-Section IV-B
Contractor OHL
Sub-section IV-B, which forms part of Section IV of Metrosur Contract 3, consists of a cut and cover tunnel from the Loranca football ground to the Fuenlabrada 2 station, and includes construction of the station. The entire route lies within the bounds of the Borough of Fuenlabrada, and, throughout its length, it runs either under land for which planning permission has been granted, or where construction has already taken place. Construction has already been carried out above the first 118 m of the route, and building is scheduled to take place along the remainder.
Project Description
The works commence at km 0 + 820, at a point opposite the outer walls of the
Loranca football ground, and they finish at the exit to Fuenlabrada 2 station,
which is located at km 2 + 687.75. The total length of the section is 1,867.75
m. The contract estimate is Pta 6,509,544,735, and the works are being carried
out over a period of twenty months.
The alignment runs through two distinct zones. As far as km 0 + 938, it runs
within the Loranca Residential Area. Beyond that point, to Fuenlabrada 2 station,
it runs through open country, where only a few isolated buildings are currently
located, but plans have been made for construction here in the future.
The first section of the tunnel is straight as it leaves the football ground.
This is followed by a bend, and a reverse curve of radius 500 m. At this point,
the tunnel leaves the Loranca Residential Area and enters the open country zone.
In this section, crossings beneath the municipal football ground at km 0 + 910,
and the Paseo de Loranca at km 0 + 925, have to be dealt with. Once the line
is beyond the residential area, the alignment makes use of a gap between a cafeteria
and an electricity substation, causing no inconvenience to either of the two
facilities.
In the open country zone, the alignment has to take account of the isolated
buildings that already exist, while the tunnel also has to be straight. It will
run level, as close as possible to the centre of gravity of the zone for which
development plans have been made, so that when these building plans materialise,
a station can be constructed. This will give future residents easy access to
the metro system, once the size of the population warrants building the station.
With a view to this, the section of tunnel between km 1 + 502 and 1 + 740 has
been laid out with a straight alignment that is both sufficiently long and horizontal,
within which the station can be located. Both location and layout are suited
to the development that is to eventually take place. It is planned that the
station will lie at a depth of 16 m to the running rail.
Following on this straight stretch, the tunnel will once again have a layout
in the form of an "S" with two bends that have radii of 500 m and
300 m, leading to the entrance to the Fuenlabrada 2 station.
Fuenlabrada
2 Station
This station is located between Fuenlabrada Hospital and the Rey Juan Carlos
I University campus, both of which are currently under construction. It lies
on a straight stretch of alignment, with a horizontal gradient, and a depth
of 15.5 m to the running rail.
Emergency exits and shafts will be located at the following points: emergency
exit at km 0 + 936; pumping and ventilation shaft at km 1 + 624; emergency exit
at km 2 + 140.
Fuenlabrada 2 station is located within the confines of the new hospital plot.
One of the station exits will lead directly into the hospital grounds, and the
other one will be located on the opposite side of the new Molino road linking
Fuenlabrada and Loranca, where it will provide access to the University campus.
The structural design has made it possible to develop a station area that lies
within one single space, formed by a box enclosed by the concrete walls. The
passenger access routes have been made as simple as possible. There is only
one intermediate level between the platforms and the street, and this is where
the station foyer is to be situated. The passengers will be able to see the
station platform level from the foyer, which will help them to get their bearings.
The platforms are 5.3 m wide, and their working length is 115 m. Two 1 m-wide
escalators are located halfway along the platforms, on either side of a 2.75
m-wide staircase.
The emergency staircases are located at the end of the platforms. Access is
gained to them from two separate hallways, so the staircase constitutes a protected
evacuation area. A gate located at ground level will provide access out into
the street. It will be operated by counterweights.
Geological
Characteristics
The geological and geotechnical characteristics of the ground are a result of
the different types of materials encountered by the excavations, and the following
units can be distinguished.
Anthropic fills: this type of ground has been found sporadically, and the maximum
thicknesses that have been detected are 2.5 m. They are made up of sand with
a variable clay content, and the density of the deposits is slight to average.
Colluvial and alluvial deposits: these are Quaternary deposits that are up to
5 m thick. They are made up of material that is of average thickness in most
cases.
Miga Sand: this is characterised by its coarse grain size, its very low fines
content, and its light beige colour. Its relative density is high, and maximum
thickness is 3 m. Miga sand containing water has been observed on the odd occasion.
Tosquiza Sand: these units are lens-like in nature, and consist of sands and
a fines content ranging from 25% to 40%. The relative density is generally very
high. A maximum thickness of more than 4 m has been detected. Some of these
sandy levels are saturated with water, thereby constituting aquifers that are
suspended in the heart of the levels with the highest clay content.
Sandy Tosco: this formation is rather abundant throughout the entire zone, and
it is composed of dense to very dense sands, and hard to very hard sandy clays.
As a general rule, the plasticity of these materials is average, but the it
is high in specific zones, and the fines content ranges from 40% to 60%. The
maximum thickness is 10 m.
Tosco: there is also considerable evidence of this formation throughout the
section. This material is made up of clays, together with a variable sand content,
hard to very hard, the colour of which is brown to reddish brown. This formation
is virtually impermeable and the plasticity is average to high.
From a hydrogeological perspective, it is not possible to talk of a ground water
table in Madrid in the strictest sense of the term. The aquifers are located
in the sandiest levels lying in the heart of the clays. The depth is variable,
in view of the alternating and irregular nature of these deposits, and as many
as four levels saturated with water flow and water content have been detected.
Construction
Processes
For line tunnel between walls, all the services throughout the length of the
section have been diverted to allow the walls to be constructed. Excavation
work is performed as far as the lower face of the tunnel roof, which is constructed
by embedding it into the walls. The excavation is then backfilled with earth
over the cast roof and to street level, and the pavement is then replaced. The
soil in the tunnel is then excavated, until the lower level of the tunnel invert
is revealed. The bottom slab is cast on this floor, and the finishing work is
then carried out.
For line tunnel excavated in the open, first, the services have to be diverted.
A strip of ground approximately 90 m-wide is required to accommodate the works,
which include 15 m-wide work roads to each side of the tunnel. One of these
roads is for earth works movements, and the other is for transport of construction
materials, such as concrete and reinforcement steel. There is also a 10 m-wide
construction road at the top of the slope for traffic through the site.
Points of Access
The excavation comprises a large trench that is approximately 20 m-deep, and
50 m-wide at the top of the cutting. Any potential problems in gaining access
to the bottom of the excavation were overcome by preparing three types of access.
Firstly, a permanent access to enable materials to be brought in, which is to
be created running roughly crossways to the tunnel layout, making use of the
zone that will be taken up by the emergency exit. This access point was prepared
with a concrete surface together with necessary drains, ditches and kerbs, to
ensure that access can be gained in all types of weather. This access point
overlooks 500 m of the tunnel, and the Fuenlabrada 2 station on one side, and
the rest of the layout in the opposite direction. An attempt will be made to
create another access point at the emergency exit situated at km 1 + 600, with
a view to reducing the length of the access to the work site, depending on the
room available.
Secondly, an access point for extracting the spoil, which under normal circumstances
is located in front of the excavation, through which the entry of materials
is not permitted, because this would obstruct the work being carried out on
the inverted vault where there is a 90 cm step.
Thirdly, an access point at the end of the excavation. This has extra width
throughout the length of the ramp so that spoil can be removed from the end
of the excavation zone. As this type of access point is not provided with a
surface area that is large enough for it to be constructed crossways, the excavation
levels depend on the length of the ramp. The excavation zone is to be longer
than normal, to avoid a greater amount of intermediate stockpiling, with the
associated negative environmental impact.
The inverted vault for the section is V-shaped. The back diggers that are to
be used for the excavation works cannot be used to achieve the correct alignments,
because the restricted width at the bottom of the excavation means that it will
not be possible to use them crossways. Back diggers are to be used that can
excavate from the side, because these vehicles are equipped with a carrying
device for this purpose. This type of machine generally has a lower capacity,
which makes the activity more laborious than is desirable, given that the tosco
to be excavated is particularly hard.
Access will be gained for the filling activities via the fixed ramp until the
area at the back of the sidewalls has been filled up. Then ramps will be constructed
running parallel to the slope, along similar lines to the access ramp at the
bottom of the excavation.
Shuttered Concreting
Once the bottom of the excavation has been trued up or aligned, the cleaning
concrete is laid, and the formwork and shuttering is prepared for the inverted
vault, and the reinforcement installed, followed by concreting.
The sidewalls are built separately from the roof, with a view to making construction
easier. If the roof were to be concreted at the same time as the side walls,
it would be difficult to install the reinforcements, and the volumes of concrete
involved would be as much as 200 m³. A suitable rate for laying concrete in
this type of construction is 35 to 40 m³/h. Laying concrete at rates exceeding
100 to 120 m³/h would involve a risk of reduced quality, not least because the
personnel involved would be tired when performing repetitive work day after
day.
To prevent any potential stoppages due to the mobile crane not being able to
enter the site to move the formwork panelling, pre-assembly of the reinforcement
has been undertaken. This allows it to be moved by specially-equipped trucks.
The roof is constructed with the aid of two units of metallic formwork, which
are transported on a specially-designed gantry. This runs on a rail and hydraulic
racking device, so that it can be located at the back of the sidewalls, inside
the module to be concreted. This gantry will allow lorries to pass through to
transport reinforcement, concrete, and other material. The formwork has been
designed in such a way that it will be possible to lay the concrete without
using the gantry as a support. This allows the second unit of formwork to be
repositioned while the first unit is being concreted.
The geometry of the roof, which has a double radius, and an almost vertical
zone running on from the sidewalls, makes it very difficult to place reinforcement
in-situ. A prefabrication technique is being employed, using roof frames that
have exactly the same geometrical characteristics as the upper and lower vaults.
As the only room available is the zone inside the tunnel itself, it will obstruct
movement inside the tunnel while it is being erected, impeding the entry of
materials for the inverted vault and sidewall work areas.
These reinforcement panels are positioned with the aid of a portico that moves
along the exterior of the tunnel, and this device is equipped with four hoisting
blocks. This portico is also used to position the formwork, which has been provided
with windows to allow for the right degree of vibration.
The two units of formwork are put in place alternately, so that they can both
be worked on at the same time. With this in mind, the first unit of formwork
will be provided with two taping devices for the concrete. These also support
the water-stop type joint that is located between modules. The second unit of
formwork lies against the two roofs that have already been concreted. If the
two units of formwork are located correctly, this method ensures that there
is no interference caused between the reinforcement and the taping devices,
and the length of the open section of excavation is reduced to a minimum.
Because the minimum radius of the layout is 300 m, there is a difference in
length in each module of up to 30 cm between the inner and outer sidewalls.
To counter this, a series of 25 cm-long sliding metal strips have been designed
for the ends of the formwork. These telescope, in order to adjust the formworks
to each bend along the section.
Station
The station will comprise an area enclosed by the walls, and is being constructed
by cut and cover. The outer walls were installed and topped, and then the roofing
slab was constructed. When this slab was finished, it was waterproofed and the
surface reinstated. Excavation beneath the slab was then undertaken to the flooring,
or bracing, level, and then on downwards, beneath the flooring to the invert
elevation.
Prefabricated reinforced concrete pillars are installed as the intermediate
supports for the station, and these have been founded upon piles that were concreted
in-situ. The pillars were installed from the surface, before the roofing slab
was cast. The following construction sequence was used: drilling for the pile;
installing pile reinforcements; putting the pillar in place; concreting the
pile; packing hollow sand around the pillar.
Main Quantities
Length
of the section
Tunnel between walls Tunnel in the open Number of stations Excavation Embankment Concrete Steel for reinforcement Walls |
1,867.75
m
335.00 m 1,400.00 m 1 unit 905.054 m³ 637.978 m³ 83.338 m³ 6,873,718 kg 21,529 m³ |
Mining Beneath Fuenlabrada to Getafe Suburbs
Contract 4, Sections V & VI
Contractor Necso Entrecanales Cubiertas
Contract 4
covers sections V and VI of Metrosur, and was awarded to Necso Entrecanales
Cubertias in April, 2000. This contract is 6.517 km-long, roughly 5.2 km of
which are in Fuenlabrada, and 1.3 km in Getafe. It includes four complete stations,
one of which connects to the suburban railway system, together with a fifth
station position, prepared for future use. It also includes 12 vertical shafts,
of which four are for ventilation, two for pumping, one for ventilation and
pumping, and five for emergency exits.
The contract was awarded at a value of Pta 25,103,910,736 with a duration of
30 months from the date of the survey on 24th May, 2000, so the work should
be completed by 24th November, 2002.
Tunnel Alignment
The alignment starts at the exit of Fuenlabrada 2 station, which services the
King Juan Carlos University. It intersects the M-506 main road, and runs along
Calle Francia to Fuenlabrada 3 station. It curves right, and changes to a left
curve to reach the existing Fuenlabrada station on the suburban railway system.
Here, Fuenlabrada 4 metro station and the corresponding interchange with line
C-5 will be located. The alignment continues through old Fuenlabrada district,
north of the previous town hall, and follows Calle Miguel de Unamuno. Fuenlabrada
5 station is located where this street joins Avenida de Venezuela. The line
then runs along the latter avenue, crosses Avenida de la Hispanidad, and then
heads across open country towards Getafe. On its way, it crosses the Culebro
gully, which has been diverted as part of the works. The future Fuenlabrada
6 station is located on this stretch.
In the Getafe municipality, the line crosses beneath the M50 ring road to Getafe
1 station, which is located in Sector 3. This part of the line continues through
Sector 3, and finishes in Avenida de Arcas de Agua, at the entrance to Getafe
2 station.
The tunnel runs at considerable depth of 20 - 25 m under the developed areas,
where the buildings are up to four storeys high.
Geology and
Geotechnics
The catchment area, which occupies most of the province, is know as the Cuenca
de Madrid, and forms part of the Tagus river basin. It is filled with layers
of Tertiary sediments of significant thickness, whose character varies according
to the position in the catchment. Three types of facies can be readily distinguished:
the Madrid facies, consisting of arkosic sand of varying grain size and grey-brown
or brown clay, locally identified with coarse sand and hardpan; the Intermedia
facies, consisting of highly-plastic brown and green clay, or peñuelas,
with intermittent layers of micaceous sand; and the Central facies, which is
of a chemical nature, consisting of chalk and chalky marl.
This section is entirely located in areas of hardpan and sandy soils associated
with the Madrid facies. One of the main characteristics of these materials is
the structure. They cannot be classified as different strata, but appear as
a group of lenticular deposits of differing lateral continuity which overlap,
and alternate with, sandy and clayey deposits. This makes it difficult to correlate
their position at different points.
On this section, the clayey soils predominate over the sandy layers, although
in some areas, the latter are present in considerable thickness. The main features
of this section are, first, the hardpan or sediments with high plasticity and
properties similar to peñuela green clay, with an appearance of smooth
areas, high plasticity and traces of sepiolite, especially at the end of the
section. Secondly, important thicknesses of poorly-compacted sandy soil corresponding
to the feldspathic sandy inclines appear at higher levels.
Quaternary alluvial deposits overlie the Tertiary material in the bottom of
valleys accompanied by anthropic fill, usually of little thickness, in urban
areas and their surroundings.
The land affected by the project is upper/lower Quaternary in nature, except
for the Quaternary soils, comprising anthropic fill, compacted fill and alluvial
deposits, which have been identified locally on some sections of the alignment.
The lithological features are as follows: Quaternary: compacted deposits; uncompacted
anthropic fill; alluvial. Upper/lower Quaternary: coarse sand; hardpan sands;
sandy hardpan; hardpan; sepiolite; chalk.
Contract Components
The contract can be divided into three clearly different parts - in kilometre
order.
The initial 3.2 km, between the new hospital and the by-pass, are located more
than 20 m below the surface, under the Fuenlabrada town centre. This will be
excavated using an EPB TBM, the safest method, with total support of the soil,
including at the face. Settlement will be minimised. This section contains three
stations, F3, F4 and F5, and four vertical shafts.
The machine will be introduced outside the urban area, close to the by-pass,
using a ramp, and access is good. It will work from west to east, and be removed
near F2, in the area of the hospital.
The next following section, up to the M50 ring road, runs through open land,
and the tunnel can be excavated in open cut. This section crosses the Culebro
gully, which has to be diverted. It also includes the future F6 station, of
which only the hall will be constructed. This station will be completed when
the area is developed.
Lastly, from the M50 to the end of the contract, a distance of 1.4 km, the tunnel
will be constructed using the traditional Madrid method. This part contains
the G1 station and two shafts.
The contract planning was based on the following outputs:
Tunnel
with tunnelling machine
Common Madrid tunnel (per face) Open cut tunnel Cut-off walls (per team) Tunnel section driving Superstructure |
350
m/mth
40 m/mth 100 m/month 80 m2/day 1 mth 700 m/mth |
Stations
The design criteria for the stations are based on the organisation of space.
The idea is to create a sense of order, where the user has a physical reference,
which helps him or her to relate to the otherwise dark, underground world, where
his or her sense of direction tends to evaporate. The chosen finishes and lighting
are also aimed at achieving this goal.
The entrances consist of glass pavilions with stainless steel frames, which
house the stairs and the escalators. These pavilions, and the corresponding
lifts for the handicapped, will receive special attention in the quest for a
Metrosur corporate image, creating a reference point on the surface.
Any solution will pursue transparency as a fundamental idea, to avoid the passenger
reaching street level visionless. These are particularly significant elements
in the urban landscape, so a search was made for a design which would have a
low impact.
F4 includes the interchange with the C-5 suburban railway. Here, a vestibule
will be built under the tracks, with access to the platforms.
Ground Treatment
The goal of the ground treatment is to prevent excessive settlement in sensitive
areas, mainly near buildings. This section of the project contains five micropile
cut-off walls, three grout curtains, and three operations to compensate for
settlement. This is apart from various fencing, pipe support work, special detection
equipment and side slope stabilisation. Except for the side slope stabilisation,
which is associated with the section in open cut, all of this work is located
in the Fuenlabrada town area.
The detection equipment will provide information on movement and on the water
table, and other data which help to monitor the behaviour of the structures,
and any possible deviation from the anticipated parameters.
This equipment basically consists of levelling benchmarks on the surface, gauges
on buildings, convergence marks in tunnels, strain gauges on the tensile reinforcement
of two sections at each station, ceramic pressure sensors where water is expected,
and pressure cells in the roof and floor.
These devices are fitted to all buildings affected by the construction, at all
the stations, and to the tunnel cross-section at approximately 400 m-centres.
Construction
Methodology
The cross-section of the driven tunnel is circular, with an 8.43 m clear diameter
and 9.07 m external diameter. There are seven liner segments of 0.32 m thickness
and 1.50 m in length per ring.
The machine to be used is called La Paloma, made by Herrenknecht. It can work
in a closed environment, controlling the pressure at the face to prevent decompression
of the soil, and avoid settlement of buildings on the surface.
The cutting wheel loosens the soil using rotating teeth and discs, and mixes
it with foam to make it easier to handle. Soil is removed from the pressure
chamber via a worm screw, which discharges onto a belt. This in turn discharges
into locomotive-hauled muck cars, running on tracks to the portal, where the
spoil is tipped into a pit. It is later reloaded and taken to the tip by truck.
Lining segments are produced off-site by the carousel method, are steam-cured,
and their quality is strictly controlled.
The main features of the tunnelling machine are:
SPECIFICATION |
REMARKS
|
|
Type, model or series | EPB / OPEN MODE |
Herrenknecht
|
Excavation diameter (mm) | 9360 |
With
new tools
|
Total power (kW) | 3250 | |
Total length (mm) | 8025 |
+
725 mm cutting wheel
|
Minimum radius of curvature (m) | 250 | |
Articulations (no.) | 1 | |
Back-up length (mm) | 57,000 |
Depends
on feed train
|
Total weight / TBM & back-up (t) | 1350 | |
Cutting tools (no.) | 150 | |
Gauging tools (no. / mm) | 3 / 10-20-30-40 |
hydraulic
/ mechanical
|
rpm | 4.1 | |
Pushing force (t) | 10,000 | |
Travel (mm) | 2000 |
For the open cut section, an excavation was first made from the TBM launch pit in the opposite direction, towards Getafe. The open cut tunnel is constructed according to the following steps: floor slab; haunches using traditional formwork; roof using mobile formwork. After construction is complete, the excavation is back-filled, and the surface restored. The total volume of excavation is 1,300,000 m³.
Traditional
Method
The final section will be constructed using the Madrid method. This method is
traditional and requires considerable workmanship. The cross-section is similar
to cut and cover, but it is constructed in three steps: arch, haunches and floor
slab.
The arch construction is the most complex, and the most important. It is in
turn divided into two parts: the pilot gallery, which is an excavation 2 m-high
and 1 m-wide, using props, longitudinal bearers and boards; and the widening,
totally propped, using the same methods, until the upper third of the cross-section
that forms the curved roof is exposed. This is then concreted, using a pump
from the outside, while maintaining the shuttering in position. The central
part of the bench is excavated, and then the haunches are excavated in intermittent
vertical sections, staggered with regard to the arch, so it is always supported.
The floor slab is constructed in lengths of 20 m.
Stations
The cut and cover procedure was used for stations F3, F4 and F5. This consists
of the following construction sequence: cut-off walls; roof slab; excavation
down to vestibule level; the vestibule; excavation down to the metro roof level;
metro roof; and platforms and finishes
Stations F6 and G1 are the deepest, and they are covered with an arch, which
has a 17 m span. This type of arch covers half of G1, and completely covers
F6. The arch was concreted on the ground in the case of G1. At F6, where there
are pillars at 5 m-centres, mobile prefabricated formwork was used.
Jacking Under
Railway Lines
At the Fuenlabrada 4 station, there will be an interchange with the suburban
railway system, consisting of a 40 m x 20 m reinforced concrete vestibule. This
structure was fabricated in one part of the Metrosur station, and then jacked
under the five existing suburban lines.
This box construction and jacking sequence is as follows. First, the displacement
bed is prepared and the thrusting base constructed. Then the box structure,
consisting of a rectangular cross-section with two cells separated by a line
of columns, is constructed. The attack face has two triangular sections in cantilever,
extending the haunches, to provide soil support during the jacking process.
Longitudinal propping of the tracks is undertaken, by groups of rails placed
either side of each rail in use, and notched below to take a length of rail
at right angles to the tracks. This length is suspended from the first groups
of rails, using special brackets. These supports rest perpendicularly on the
soldier beams (RSJ sections), which in turn are supported by the rear of the
structure. The far end rests on the soil.
Movement of the box structure is achieved through the thrust provided by jacks
reacting on the thrust base. Prior to each jacking cycle, the soil is excavated
using conventional means from inside the structure. This is followed by removal
of propping, and restitution of the tracks, following which the auxiliary construction
is demolished.
By mid-July, 2001 some 45% of the contract time had expired and progress was
as follows:
stations: concrete 85%, excavation 65%; vertical shafts 70%; ground treatment
50%; open cut tunnel 70%; traditional 40%; TBM under assembly.
The principal quantities of the contract are as follows:
TBM
tunnel
False tunnel Traditional Madrid tunnel Liner segments Excavation Fill Total length - soil treatment Consolidation grouting Cut-off walls Piles Precast columns Concrete Steel bars Rolled steel sections Rail Elastic spikes Cement gravel track bed Cladding panels |
3,300
m
1,750 m 1,325 m 14,000 u 2,000,000 m³ 1,350,000 m³ 4,700 m 2,800 m³ 65,000 m³ 1,600 m³ 1,700 m 205,000 m³ 17,700 t 380 t 26,100 m 31,000 u 53,000 m³ 11,000 m2 |
Connecting Loranca in Fuenlabrada District
Contract 4, Subsections IIIB and IVA
Contractor Sacyr S.A.
Contract IV, sub-segments IIIB and IVA of Metrosur were awarded to Sacyr S.A. in April, 2000, and are situated in Loranca, in the district of Fuenlabrada. The budget is Pta5,371 million, with an expected duration of 18 months. The contract includes civil work, rail-laying and station architecture, and is 821m long, of which 413.13m are being excavated using the traditional Madrid method, 275.17m are being excavated between supporting walls, and 133m are station. The route follows the main streets and avenues, and the station is located in the heart of the urban area, next to the municipal building, the Cultural Centre, a school, and a new Health Centre which is still under construction.
Project Description
The route of segment IIIB starts 275.17m before the entrance to Fuenlabrada
1 station in Loranca. Between km 0+0.00 and km 0+0.275.17, the tunnel runs below
Alegría Street, and is formed by retaining walls covered with an in-situ
slab. The station is situated between km 0+0.275.17 and km 0+406.87, next to
the District Council Buildings. The average depth of the station relative to
the track varies between 13.8 m and 16.8 m. An electricity substation is incorporated
into the design.
Subsegment IVA runs from km 0+406.87 to km 0+820.00 where the local football
ground is located, and a 16% gradient ramp next to the civil gardens provides
access to the tunnel from Alegría Street and Pablo Iglesias Street. The
section is 114 m-long, of which 73 m run straight and 41 m are curved, with
a radius of 150 m. The curved section was built using the traditional Madrid
method, once there was more than 8 m of cover. The point where the ramp meets
the tunnel is formed using supported arches.
The ramp provides access to the tunnel, and once the tunnel reached the station,
it facilitated the clearing of the station as well. The tunnel also provides
access to the station for materials and finishes, as well as for tracklaying.
Once the contract is completed, this ramp will be closed and filled to where
it joins the tunnel.
From km 0+406.87 the tunnel runs straight, following Alegría Street,
and at the end of this street it turns south in a curve with a 300m radius.
Between km 0+620 and km 0+710 the tunnel passes beneath the Fregacedos School
sports ground, and from there runs under Gabriela Mistral until it reaches the
Municipal football ground at Loranca.
The track superstructure is a 54 kg/m rail, which is laid on reinforced concrete
blocks which are covered on both sides by a Corkelas type elastomer made by
Edilón, and fixed by the Pandrol clip system. The blocks are designed
support a 12.5 t axle load.
Plans are for two types of rail switching at either side of the station consisting
of 0.125 TG crossings, 7.90m elastic points and 10.523m points, supported by
a set of pre-fabricated concrete blocks and shims with Corkelas type elastomers
between blocks and shims. Pandrol clips fix the crossings and adjacent tracks.
The crossing comes with four rail posts pre-welded under pressure.
Methodology
The whole of the section IIIB tunnel was constructed with retaining walls. Each
wall is 0.8 m-thick. Tunnel width is 8.2 m covered by a 0.8 m-thick slab with
0.9 m supports.
The entire sub-segment IVA was excavated using the traditional Madrid method,
8.2 m-high and 7.8 m-wide. It begins with an excavated gallery, which is then
progressively cleared to form the upper part of the section. An average advance
of 2.5 m/day was achieved.
From the geotechnical point of view, the main worries with this project are
subsidence and settlement, which can affect existing buildings or structures
close to the route of the tunnel.
Thankfully, due to both the route of the project running beneath existing roads,
and the types of construction used, possible adverse effects are minimal.
As part of the Metrosur project, a complete geotechnical, geological, and hydrological
analysis was carried out, and the best method of construction was chosen. This
study included identification of the quickest remedies for all foreseeable problems,
such as lack of cohesion, slides or water ingress. The soil encountered is predominantly
tosca arenosa, a weak sandstone with limited standup time.
A comprehensive series of tests and controls is used to check and detect the
least movement in soil, buildings and structures, and to ensure that any such
movement remains within acceptable limits, both during and after the construction
work.
Tunnel Construction
For tunnel sub-section IIIB the construction sequence was as follows: first
of all, existing services along the route were re-routed; then the horizontal
work platform was prepared, from which first the guides, and then the retaining
walls, were sunk; then excavation commenced to the level of the underside of
the roof slab. Concrete was then poured to form the slab on top of the walls
and the ground. The soil was in-filled up to street level, and the asphalt relaid
to facilitate renewed traffic flow, as early as possible.
Once the above-ground slab was laid, the tracks, installations and finishes
could begin.
The traditional method of tunnel construction, used in Madrid since the 1920s,
was applied to sub-segment IVA in successive phases according to the following
sequence.
Using pneumatic drills, a 1 m-wide by 2.5 m-long gallery was opened at roof
level in the axis of the tunnel, supported initially with boards, and then with
longitudinal beams at 1.0 m separation, supported by 1.5 m to 2.5 m-high timber
props to pin the boards to the crown. Once this gallery is formed, the excavation
is widened using pairs of boards and beams. To excavate a twin track metro tunnel
of 8.2 m x 7.8 m, four separate compartments are used.
Once the roof excavation is complete, it is concreted to between 0.8-0.9 m-thick
using HEB 140s with the size and shape of the interior of the tunnel. To minimise
the deformation of the ground, concrete is pumped at 20 Nm and transmits the
weight to the roof almost immediately.
Once finished, mechanical excavation can be used down the middle of the tunnel,
with the face of the excavation some 15 m beyond the limit of the last ring,
but leaving 1.5 m at either side to guarantee the transfer of weight from the
roof to the floor. This ground is later removed in 2.5 m-wide panels, alternating
from one side of the tunnel to the other. These places are propped by hand,
then shuttered with metal, and 0.9 m-deep concrete is poured. Finally mortar
is injected at low pressure to fill all possible gaps and small holes.
This method has many obvious benefits, including the stability of the tunnel
face, accurate control, minimised deformation of terrain, and tunnel support
immediately after excavation. It is adaptable to almost any type of terrain,
and is versatile in the event of unexpected problems. It is also sufficiently
flexible to accommodate variations in mid-excavation, such as changes of width,
shuttering, or excavation face advance.
Down sides include slow forward progress of 12.5 m to 15.0 m per week, coupled
with the need for specialised trades, which are increasingly scarce.
The ramp for access to the tunnel was constructed mainly by the traditional
Madrid method. It was started by piling, using 1.0 m, 0.8 m, 0.6 m and 0.45
m-diameter piles, to 23 m-depth. The traditional Madrid method took over for
42 m of tunnel at 8.2 m width, once the depth got below 8.0 m.
Once the tunnel reached the station, the utility of the ramp access increased,
as it was further used to aid removal of excavated material from the station,
and from the areas of tunnel excavated between retaining walls. The ramp access
is also a useful delivery route for finishing materials and track installation.
Fuenlabrada
1 Station
This station is right in the middle of the borough of Fuenlabrada, in which
the only noticeable change after completion will be the entry and exit points.
It has been placed in line with two streets, Alegría Street and Libertad
Street, which means the exits are in a square in front of the new District Council
Buildings, on a plot destined for commercial use.
The structure uses pre-cast beams and slabs spanning an open plan area 29 m-wide
between retaining walls. Access has been kept as simple as possible, using a
single intermediate level between streets and platforms where the ticket gates
will be located. From this point, the platforms dominate the view, helping to
avoid passenger disorientation and aiding flow by keeping ticket machines perpendicular
to the platforms. These platforms are 115 m-long and 5.3 m-wide.
The electricity substation has been incorporated into part of the space above
the platforms. This will house eight transformers, each weighing 13 t, in a
separately ventilated environment. Access to the substation and cables will
be shared with the emergency stairways.
Located between km 0+275.17 and 0+406.11, the station is formed by 0.8 m and
1.0 m-thick concrete retaining walls, using cut and cover. The roof was formed
in two different ways: in-situ slabs for the ventilation and substation areas;
and pre-cast 1.85 m beams over the vestibule. Excavation started once the walls
were in place.
The excavation for the walls was carried out in 2.5 m segments of up to -29.60
m. Due to the local soil conditions, and with a water table below the level
of the works, the use of bentonite was unnecessary, permitting excavation rates
of between 100-140 m2/team/day, and avoiding the environmental problems associated
with bentonite residues.
Once the walls were completed, and the guides removed, soil was removed from
the inside face of the wall, which was then cleaned and prepared for the pouring
of the slab. Once the slab was up to strength, the vestibule area could be excavated
to the level of the vestibule floor. Here, the steel in the retaining wall was
exposed, to interlock with the rebar of the floor slab. The slab was poured
onto the soil, and the excavation process repeated to track level. Another 8
x 1m-diameter piles support the span of the vestibule slab.
PRINCIPAL STATISTICS
m³
retaining walls and piles
m³ Traditional Madrid Method excavation m³ excavated material Kg reinforcement m³ Concrete Linear metres, tunnel between retaining walls Linear metres, Traditional Madrid Method tunnel Linear metres, Station Linear metres, Track Budget sub-segment III B Budget sub-segment IV A Construction Period |
14,414
33,247 78,041 3,471,822 49,986 275 454 133 3,280 3,341,277,490 pts 2,029,685,350 pts 15 months |
Tunnelling Beneath Getafe Town
Contract 5
Contractor Ferrovial Agroman
Contract 5
of Metrosur is located entirely within the municipal district of Getafe, and
comprises 7.36 km of tunnel, including six stations, ventilation structures,
emergency exits, drainage system, track installation, and tunnel lighting with
service specifications. It also involves replacement of services and restoration
of places where the project might affect the environment.
The whole section is underground, bored by EPB TBM, leaving a tunnel with an
inside diameter of 8.43 m. The award budget for the works is Pta26,636 million,
with an average cost of Pta2,278 million/km of tunnel, and Pta2,196 million/station.
EPB Tunnelling
Machine
In this type of ground, composed of soils and soft rocks, the tunnel is being
driven by means of a Herrenknecht EPB shield tunnelling machine, which applies
pressure at the face and keeps the excavated soils under pressure. Its main
function is to guarantee the stability of the face of the tunnel, and the section
where the construction stages are being carried out, thereby assuring minimal
surface subsidence.
The tunnel diameter is determined by the operational requirements of the Metro,
which requires an inside diameter of 8.43 m. This is obtained with an excavation
diameter of 9.38 m using the Madrid type lining of 32 cm-thick reinforced concrete
segments.
The Metrosur Contract 5 TBM Mares del Sur was purchased new for this project,
and possesses the latest advances in this type of machine. It has total automation,
a laser guidance system, and automatic remote data transmission to the site
office. The machine has a mixed cutting head with discs for rock cutting, and
is expected to achieve an average advance of 15 rings/day. This equates to a
forward movement of 22.5 m/day, with peaks close to 22 rings/day, or 33 m/day.
It is an EPB earth pressure shield with a watertight screen designed for an
operating pressure of 3 bar. It comprises a cutting head, shield middle body,
and tailskin. Its weight is 454 t. A base segment is installed at the bottom
of the ring, on which the construction railway track is built.
The tunnelling machine specification is described briefly below.
Propulsion cylinders .......... | 13 pairs (26 cylinders) with 320 mm. piston diameter, total thrust force 10,000 t, forward speed 0-80 mm./min. |
Cutting tools .......... | Cutting wheel with 196 teeth, 16 peripheral rakes, 21 17-inch double discs and 2 copy cutters, which also perforate rock. |
Cutting wheel drive .......... | 0-3 rpm. Torque 20,236 kNm. Initial starting torque 24,000 kNm, with two directions of rotation. Installed capacity 2.800 KW. 17 Rollstar G269 hydraulic gear motors. 17 pinions with dual housing. Diameter 5,000 mm. |
Electrical system .......... | 15 KV voltage supply, installed capacity 4,000 KW, 2 transformers 2,500 KVA each. |
Guiding system .......... | Electronic Laser System (ELS) with the active objective installed on the shield liner. |
Extraction system .......... |
Extending, helical worm conveyor with a travel of 1,500 mm., Outside diameter 1,000 mm., 22 helices 630 mm. apart. Conveying capacity 550 m3/h, output 400 kw. Conveyor belts 1,200 mm wide with a capacity of 800 m3/h. |
Mortar injection system .......... | 6 pipes for injection between lining and ground (5.64 m³ approx.). Output 45 KW. |
The tunnelling
machine launch point is in the area where the Getafe 8 station, also known as
El Bercial, will be located. A stocking yard has been built for the segments
at this access, and installations for compressed air, mortar plant, and ventilation
are also located here. The excavated spoil will be removed from this point.
During the third quarter of 2001, when the tunnelling machine will have reached
Getafe 4, the launch point installations will be transferred to this station.
The tunnelling machine will then continue on its path until reaching Getafe
2 station, where it will be dismantled and removed.
The tunnel lining is formed of Madrid type rings consisting of seven different
trapezoidal segments, six of them occupying 2/13 of the development, and the
frustoconical keystone 1/13 of the circumference.
The segments are of prefabricated reinforced concrete type, 0.32 m thick, with
an average length of 1.5 m, which ranges from 1.459 m to 1.542 m. The rings
are joined together by means of 13 equidistant (i.e. 27.692o apart) zinc-plated
pin bolts, with two bolts per segment, with the exception of the keystone, which
has only one bolt.
The alignment passes through mixed Quaternary and Tertiary strata of the Madrid
facies, comprising mainly stone, black clay and chalk of 130-150 kg/sq cm compressive
strength. It runs below, or crosses, the water table at all times, with an approximate
head over the crown of 14 m.
The track superstructure planned complies with the criteria specified by Metro
de Madrid for trains composed of 6000 type cars. It is plate track, with naturally
hard 54 kg/m rail, resting on reinforced concrete blocks covered on their inner
and side faces with Corkelast type elastomer. These blocks will have to withstand
a load of 12.5 t per axle, and their anchorage with the rail will be Pandrol
type.
Stations
Metrosur contract 5 includes six stations: Getafe 2, Getafe 3, Getafe 4, Getafe
5, Getafe 6 (El Casar) and Getafe 7 (Espartales).
The distribution of all the stations in the section is similar, and they each
have an entrance concourse floor and a lower platform floor. They all have one
or two street accesses to the concourse, equipped with fixed stairs, a pair
of mechanical escalators, and a lift. They are all provided with one emergency
exit and ventilation shafts.
There are two stations that have special features as interchanges offering access
both to the Metro and to the suburban train system: El Casar, which interchanges
with Renfe C-3 line; and Getafe 4 which interchanges with Renfe C-4 line. In
addition, these stations are equipped with electricity substations.
El Casar station is a shared interchange concourse for access to Renfe (Spanish
Railways), for which the station has to line up as closely as possible with
the run of the railway line, and with an orientation parallel to it. At an intermediate
level between the suburban station and the Metro platform, there is a concourse,
which serves as an interchanger between both lines, besides providing access
from the outside.
The Getafe-4 station forms part of the Getafe-Suburban complex. The Metrosur
track axis lies transversely to the Suburban track axis and at a lower level.
The station is designed with a concourse over the tracks at a midway level with
respect to the Suburban station platforms. Access to the concourse is gained
directly from the Suburban platforms, via two facing stair cores. From the concourse
level, access to the platforms is also indirect, by way of two vertical communication
cores.
Structure
Construction of the stations starts before the tunnelling machine passes through
the complex. This offers a number of advantages such as casting the floors against
the ground, with the resultant saving on falsework; execution of the roof slab
in a short period of time, so that the streets involved may be re-opened for
normal use; and saving the tunnelling machine from mining the ground and installing
the segmental lining; and saving the costs of demolishing the lining, when excavating
the station.
The procedure for carrying out the cut and cover excavations is as follows:
installation of the screen-walls; casting in situ of the roof slab; excavation
of the concourse level; casting of the concourse level; excavation down to inverted
vault level; casting of the inverted vault; and platforms and finishes.
Screen Walls
The screen walls were constructed using different procedures, depending on the
type of ground in each case.
At Espartales and Getafe 5 stations a hydrocutter was used. This method of excavation
is used when the subsoil contains materials such as hard chalks. At Espartales
station, about two weeks were needed to install and assemble the machine, tanks
and sludge circuit. Excavation started on 20th July, 2001 on the first screen-wall,
while the last one was excavated and concreted eight weeks later, on 14th September.
For the primary panels it took around seven hours to complete the three passes
needed for excavation; on the secondary panels around three hours were required
for the single passage. In total, some 5,000 m³ of earth were excavated in the
49 working days spent on this job.
The system of excavation consists of steadily reducing the size of the material
to be excavated, and mixing it with a bentonite suspension. The mixture is then
pumped through a system of pipes to a sand removal plant, and may be used until
the successive cycles make it unfit.
The bentonite supports the earth wall, and prevents cave-ins. In addition, it
does not mix with water, so it does not permit its entry by seepage through
the excavated walls.
A complex centrifugal pump, located immediately above the cutting wheels, removes
all the excavated material and propels the mixture of soil and bentonite to
the plant.
Conventional
Bucket at Getafe-2
This method of excavation is used when the subsoil contains such medium resistance
earth materials as roughs. The system consists of guiding the bucket by means
of cables, which are used for raising, lowering and opening it. The bore bit
is used on hard layers of ground. This implement is provided with teeth at the
bottom and it is attached to the sides of the bucket for raising and releasing
and in this way breaking up the hard layer so that the earth material may then
be removed with the bucket.
Pile Drivers
with Casing at El Casar
This method of excavation is used when the subsoil contains such hard earth
materials as chalks, but in the upper layers the ground is soft and not very
cohesive, with a tendency to crumble. Its main advantage lies in its high performance.
To prevent the crumbling of the ground in the first 5 m, casing is installed,
with recoverable metal liners. No further shoring is required, once the layer
of anthropic waste fill is passed.
Conventional
Screen with Pre-bores at Getafe 3 and 4
This method of combined excavation is used when the subsoil contains such hard
materials as chalks. First, two or three preliminary bores are made with the
pile driver to break up the columns of hard earth in each screen module, to
assist subsequent excavation with the conventional bucket.
In the particular case of these stations, thixotropic sludge is used, as there
is a layer of water-saturated sand in the subsoil. The placement of reinforcement
frames, and subsequent concreting, is done by traditional methods.
Roof Slab Construction
Once the screen-wall enclosure is built, the roofing slab is cast on the ground,
using plain formwork consisting of grooved and tongued wooden sheathing.
The roofing slabs for the narrow areas of stations are of reinforced lightweight
construction, so as to reduce their actual weight and edge. This method is used
for wide areas of stations, in order to be able to dispense with the pile pillars
that would support the floor units, due to their large spans. A more open-plan
space is thereby achieved inside the stations. In some cases, this space is
not completely free, because metal ties are installed to anchor the concourse
hanging from the upper slab. In these situations, concrete pillars are not erected
on the inverted vault to support the concourse deck.
Concourse and
Inverted Vault
In those stations where the tunnelling machine is scheduled to pass immediately,
or in the event of it not being able to pass through the space between the inverted
vault and the concourse, excavation is carried out down to the level of the
inverted vault. Construction can then carry on while waiting for the tunnelling
machine to arrive. The concourse slab is then built resting on concrete pillars
on the inverted vault, as in the case of Espartales station (Getafe 7).
In those stations where the tunnelling machine is not scheduled to pass immediately
and it can pass through the space between the inverted vault and the concourse,
excavation is carried out down to concourse level. The floor of the concourse
level can then be cast on the ground, and anchored by means of metal ties hanging
from the upper slab. Hollowing out is then completed to the inverted vault level,
so that this may be built while waiting for the tunnelling machine to pass.
This is the case at El Casar (Getafe 6), Getafe 5, Getafe 3 and Getafe 2 stations.
Performance
Table updated on 11/12/00 | CASED PILES | HYDRO CUTTER |
CASED PILES | HYDROCUTTER | CONVEN. SCREEN+ PREBORES | CONVEN. SCREEN |
|
Implementation shaft | Getafe 7 Espartales | Getafe 6 El Casar | Getafe 5 | Getafe 3 | Getafe 2 | ||
Unit | Piles 1,500 | Screens 800 | Piles 1,500 | Piles 1,000 | Screens 800 | Screens 1,000 | Screen 1,000 |
Starting date | 04/07/00 | 21/07/00 | 18/07/00 | 28/08/00 | 26/09/00 | 08/08/00 | 21/08/00 |
Completion date | 27/07/00 | 14/09/00 | 12/09/00 | 10/10/00 ** | 30/11/00 | 17/11/00 | 27/11/00 * |
Nº panels | 60 | 68 | 156 | 181 | 82 | 82 | 154 |
Total measurement | 1.393,2lm. | 6.150,1m2. | 2.852,1 lm. | 2.326,0 lm. | 7.785,5m2. | 7.503,9m2. | 6.796,7m2. |
Total calendar days | 23 | 56 | 49 | 39 | 66 | 101 | 98 |
Total useful days | 18 | 48 | 39 | 30 | 45 | 46 | 60 |
Panels/calendar day | 2,6 | 1,2 | 3,2 | 4,6 | 1,2 | 0,8 | 1,6 |
Panels/useful day | 3,3 | 1,4 | 4,0 | 6,0 | 1,8 | 1,8 | 2,5 |
Measurement/ calendarday | 60,6 | 109,8 | 58,2 | 59,6 | 118,0 | 74,3 | 69,3 |
Measurement/useful day | 77,4 | 128,1 | 73,1 | 77,5 | 173,0 | 163,1 | 113,3 |
*
Update day. Pending execution of 10 remaining panels (120 m2).
** Pending diversion of RENFE tracks to execute
52 remaining panels
Ground Monitoring
For monitoring movements a system is needed that will provide sufficient knowledge
of the way the ground, structures and installation respond to the operations
that are being carried out, in order to gauge excavation safety during the execution
of the works. All the instruments should be installed before starting excavations,
in order to be able to read the movements that take place as the excavation
face approaches the site of the instrument.
Section lengths with stations.
SECTION | LENGTH | STATIONS | ACCESSES | DISTRICTS | ZONES |
VII | 1,346 m. | Getafe 2 | Senda de Mafalda. | El Artesón, Cerro de la Herradura | Sector 3 |
Getafe 3 | El Greco. | Fátima, San Isidro, Nuevo Hogar | |||
VIII | 4,022 m. | Getafe 4 | Calle del Muelle. | Casco Antiguo, La Alhóndiga | Getafe Centre |
Getafe 5 | Avda. España. | Juan de la Cierva, Universidad Carlos III | |||
IX | 1,894 m. | El Casar | Avda. del Casar. | El Casar | Getafe North |
Espartales | Rigoberta Menchu. | Los Espartales, Ventorro Bardalón |
Main project details
UNIT | MEASUREMENT | TOTAL MEASUREMENT | |
Lm. Total length | EPB tunnel | 6,484 | 7,360 |
False tunnel | 98 | ||
Station pass length | 778 | ||
Kg. Reinforcement steel | Screens and piles | 6,107,544 | 18,697,154 |
Tunnel voussoirs | 4,765,467 | ||
Other structural work | 7,824,143 | ||
M³ Excavation | Screen-walls and piles | 128,144 | 1,016,816 |
Tunnel | 441,934 | ||
Other excavations | 446,738 | ||
Lm. Piles | 11,556 | 11,556 | |
M2 Screen-walls | 51,210 | 51,210 | |
M³ Concrete | Screen-walls and piles | 52,727 | 191,546 |
Tunnel voussoirs | 59,004 | ||
Other concrete work | 79,815 | ||
Lm. Rail 54 kg/ml | 29,444 | 29,444 | |
U. Elastic blocks for 12.5 t | 32,680 | 32,680 | |
M2 Vitrex type panels for covering vertical facings of stations | 7,836 | 7,836 | |
M2 Italfilm panel for covering vertical facings of stations | 6,781 | 6,781 | |
M2 Concourse and platform paving | 22,081 | 22,081 |
Serving the Population Centre of Leganes
Contract 6
Contractor Dragados
Contract 6
of Metrosur stretches for 6.99 km through the town of Leganes. It is completely
underground, with some 6.11 km in tunnel, and the remaining 780 m forming the
stations.
The alignment runs under the principal routes within the town, serving the most
populated suburbs and activity centres, such as the Parquesur mall, the bullring
"La Cubierta", the Carlos III University, the Severo Ochoa Hospital,
and the railway station, which will become a new transport interchange.
There are six stations, each of which is positioned in a travellers zone of
radius 500 m. The population in the catchment area of the metro is 115,000,
a figure that will rise to 125,000 by 2010. The municipality has 175,000 inhabitants
in total, so the metro will provide accessible transport service to 70% of the
local population. Leganes 2 station, in the neighbourhood of Zarzaquemada, will
service 49,000 potential travellers, one of the highest usages in the whole
Metrosur system.
The tunnel is under construction at 8.43 m inside diameter using an EPB shield.
At Leganes 1 and Leganes 5 stations, electric traction substations will be built.
Along the alignment, a total of six ventilation shafts, six pumping shafts,
two launch and retrieval shafts for the TBM, and one intermediate shaft for
spoil extraction, will be built.
The works include concreting of the invert to support the rail superstructure,
and assembly of the rail track, as well as the lighting and power installations
for the tunnel and stations.
The budget is Pta29,400 million, and the construction term is 29 months.
Construction
The TBM has 9.38 m external diameter and a length of 11.58 m. It has 26 cylinders
with a total maximum thrust of 10,000 t. Its unblocking torque is 2.217 tm.
It was launched from a 200 m-long x 10 m-wide shaft, installed in open fields
using pile walls. Later, the shaft will be reinstated as a part of the tunnel,
with cover of around 6 m. Its length allowed complete assembly of the TBM and
its backup and also accommodates the muck pit from where the material will be
removed with back-hoe and trucks.
The tunnel will be supported and lined using the universal Madrid-type ring
of six segments, keystone, and with an invert segment fabricated and placed
to support the twin track railway. The segments will be handled by a 35 t gantry.
The excavation diameter is 9.38 m, and the segments have a trapezoidal shape
suitable for describing the minimum radius of 150 m. Each ring comprises seven
segments, of which one is a tapered keystone, and the other six with angle in
the centre.
The rings have 9.07 m external diameter, 1.5 m length, and 320 mm of thickness.
They are connected together using 13 bolts spaced equidistantly, with two for
each segment and one for the keystone. The annular space between the segments
and the soil is injected immediately with dry-mix mortar, in order to reduce
to the risk of surface subsidence to a minimum. This mortar has low cement and
high ash content, to ensure easy pumping.
The TBM cutting head is continuously monitored and inspected every third day,
when any worn or missing tools are replaced. Earlier, two rows of tail brushes
were replaced in a delicate operation which involved pulling the TBM tailskin
into a completed ring.
The stations are constructed with perimeter walls and concrete roofs, with secure
excavation or anchoring of the walls, and finally the concreting of the invert
to allow passage of the TBM.
After that event, the structures of the hall, accesses, technical rooms and
platforms will be completed.
In order to avoid problems that might provoke collapse under buildings, a subsidence
monitoring plan has been developed, as well as a programme of special ground
treatment in the zones where it is found to be necessary.
Typical Geology
The soils along the alignment of the new line are very typical of Madrid. Until
leaving El Bercial station, the route passes through colluvial-alluvial soils,
micaceous sand and miocenic peñuelas. From there on the TBM encounters
highly compact sandy clays.
The upper part of the tunnel will be excavated in tosco sands and tosco, with
the invert in sands in the beginning, through micaceous sands later, and in
peñuela in the final stretch. TBM boring will be affected by the heterogeneity
of the cut.
Although the water table will be permanently around level 615, high pressures
are not expected. Apart from the water table, there are water pockets of different
sizes overlying watertight strata, which could drain the sand where they lie.
The project includes a budget of about $2 million for ground monitoring, and
for the control of ground movement and subsidence along the route. Along the
alignment of the tunnel, there will be a levelling point every 50 m, and a profile
with extensometers and eight levelling points in the most sensitive areas. Levelling
points will be placed in the façades of all buildings in the vicinity
of the works.
In the stations, four instrumented profiles will be set up in the concrete diaphragm
walls, each with four pressure cells, inclinometers and extensometers.
The tunnel lining will be constantly watched through instrumented segments,
with pressure cells and extensometers, and regular control of the geometric
deformation of the section with convergence nails.
Besides these measures, before the TBM tunnel construction commenced, several
treatments of the subsoil were undertaken in order to avoid settlements or collapses
on surface.
To determine the countermeasures, a study was carried out to define the possible
movements of all the buildings located within one tunnel-depth laterally of
the alignment. To facilitate this study, all available data about the buildings
were collected, such as year of construction, nature and depth of foundations,
type of structure, floor and basement area, and the existence of cracks. Collector
sewers, large diameter water pipes, high-tension towers and old wells were all
inspected and mapped. In addition, an extensive campaign of geotechnical tests
was carried out in all the potential problem areas.
At all points where the tunnel was excavated with less than one diameter of
cover, and in less consolidated alluvial soils like those found in Leganes,
it was necessary to carry out several high pressure jet grouted injections of
cement to consolidate the ground. Under problematic buildings, the injection
was carried out through screwed, orificed steel pipes in order to have better
control of the pressure and cement admission, and to avoid lifting the structure.
In one case, because of lack of space, injections were carried out from a pile
well.
Finally, some work was required to seek out old wells along the alignment, and
fill them with mortar as a safety measure above the TBM.
The TBM has already driven successfully under several buildings and an underground
car park some 180 m-long, and with just 5 m clearance.
Progress
At the time of writing in July, 2001 the TBM had bored 5,538 m at an average
of 19 m/day.
Since its launch on 5th October, 2000, some 281 days earlier, both the total
advance and the average rate were the highest of all the TBMs currently involved
in Metrosur.
The TBM is now in Leganes 5 station, and preparing for the last 950 m of tunnel
to the final shaft.
Stations are structurally nearly complete, except for the L1 and L2 stations
where the TBM arrived in advance of excavation. These two must wait for the
completion of the tunnel before they can be excavated, and the lining rings
demolished. This delay is necessary because of the high traffic density of passing
muck trains coming from the TBM.
Geotechnical conditions have remained more or less as expected, with sand and
tosco, accompanied by a fair amount of water, thankfully without pressure.
Work commenced in June, 2000, and to date, the following quantities have been
completed: walls, 65,000 sq m (97%); concrete, 170,000 cu m (60%); excavation,
800,000 cu m (70%).
The tunnel drive commenced on 5th October, 2000 and the following progress has
been made: length built, 4,500 m (72%); daily average, 22 m; maximum daily advance,
45 m; monthly average advance, 540 m; maximum monthly advance, 741 m.
Major Quantities
Length of the
alignment…………6,990 m
Tunnel with EPB……………......6,068 m
Open-cut tunnel……………….......142 m
Number of stations………………….6
Excavation…..………......1,100,000 cu m
Concrete……….………......310,000 cu m
Steel………….……….......24,000,000 kg
Walls…………………..….....60,000 sq m
TBM Dimensions
External diameter
9.38 m
Length of head
..11.58 m
Total length
..127.84 m
Total weight
...1,470 t
Contractor Ferrovial Agroman and ACS
By widening
the gauge of Line 10, type 6000 rolling stock can be introduced to replace the
existing 2000 series trains, thereby increasing the capacity of the line. This
project has been in development by the Community of Madrid over a number of
years. The construction of the Príncipe Pío Interchange in the
late 1990s enabled commuters to transfer from Line 6 to Line 10, maximising
the use of both lines. The work to connect and extend lines 8 and 10 also resulted
in an increase in capacity demand for Line 10. The latest decision to extend
Line 10 to Metrosur to give access to the capital for commuters from the municipalities
of Alcorcón, Móstoles, Fuenlabrada, Getafe and Leganés,
made the need for an increase in capacity critical.
The Metro trains operating on Line 10 are known as type 2000. These trains are
made up of six 2.3 m-wide coaches, with a total train length of 88.32 m. For
this type of train, 90 m-long platforms were required.
The gauge-widening project includes the following work: widening tunnels, widening
stations, modification of the superstructure, and so on, to enable the type
6000 rolling stock to pass. The new trains comprise six 2.8 m-wide coaches,
with a total length of 108.06 m. The platforms will need to be extended to 111.60
m in length. These modifications will facilitate a 63% increase in line capacity,
and other improvements will allow the trains to run more frequently.
The objective of this project also entails modifying Line 10 to connect it to
Metrosur. To do this, as part of the project, a new station, Puerta de Batán,
is under construction between Campamento and Batán stations. This new
station will become an interchange for Lines 5 and 10, thereby substituting
the existing one in Aluche.
Geotechnical
Description
The land on which the city of Madrid stands has been well studied, even more
so after the intense ground investigation work and the numerous analyses carried
out to classify the ground during previous projects to extend the Metro network.
In order to identify the ground where the construction work is to take place,
an extensive investigation programme has been carried out, including boreholes
with intact core samples. From this investigation it can be inferred, not surprisingly,
that the ground in the study area is made up of alternating layers of mainly
granular material (miga sand) to markedly clayey material (tosco).
The following strata have been identified:
Miga Sand: contains less than 25% fine material and has low plasticity. The
Casagrande classification system situates this material within the silty sands
(SM) and clayey sands (SC) groups. It has an angle of shearing resistance of
about 35º and a cohesion intercept varying between 0.5 and 1 t/m2.
Tosquiza Sand: contains between 25% and 40% fine material and has an intermediate
plasticity. The Casagrande classification system situates this material within
the clayey sands (SC) group. It has an angle of shearing resistance of about
33º and a cohesion intercept varying between 1 and 1.5 t/m2.
Tosco Sand: contains between 40% and 60% fine material and has a low-intermediate
plasticity. The Casagrande classification system situates this material in the
category of low-plasticity inorganic clays, soils containing proportions of
clays, gravels, sands, and silts (CL). It has an angle of shearing resistance
of about 32.5º and a cohesion intercept varying between 2 and 2.5 t/m2.
Tosco: contains more than 60% fine material and has a high-intermediate plasticity.
The Casagrande classification system situates this material within the category
of low to intermediate plasticity inorganic clays (CL), and high-plasticity
inorganic clays (CH). It has an angle of shearing resistance of about 30º
and a cohesion intercept varying between 3 and 4 t/m2.
Principal Work
Firstly, it should be pointed out that a great deal of the following work has
been made possible thanks to the temporary suspension of trains on the line
between Alonso Martínez and Campamento stations, from 1st June, 2000
to 18th April, 2001. Along this stretch, the line was completely renewed. To
limit the trauma caused by closure of such a heavily used line, the construction
process was optimised to reduce the time necessary to complete the work. As
a result, partially re-opening of the line was achieved by bringing the Alonso
Martínez and Tribunal stations into service on 20th December, 2000. It
is worth noting that during the time the line was out of service, a special
local bus service was established, which operated during the hours of the Metro
as an attempt to ease the inconvenience caused to passengers.
A blind-end tunnel about 760-m long, which will be needed until the inauguration
of the extension to Line 10 towards Metrosur, was mined using the traditional
tunnelling method, with multiphase excavation.
Removal of tracks between El Lago and Puerta de Batán stations was necessary
as a consequence of the increased width of the rolling stock that will have
to run along this line. It needs to be widened by 0.5 m between the aforementioned
stations. Both tracks are removed to minimise the work on the station platforms.
Masonry work is extended, the hard-standing area is worked on, and retaining
walls and new drains are constructed.
Widening the gauge also demands an increase in the tunnel section in various
places. This sometimes requires removal of the tunnel lining and replacing it
with one of reduced thickness, and elsewhere, simply scabbling to remove high
spots.
Lengthening to 111.6 m and widening the Plaza de España, Alonso Martínez
and Tribunal underground stations using the German method is being undertaken
for the new type 6000 trains. Lengthening and widening of Batán and El
Lago stations involves demolishing the central platforms, and lengthening and
widening the side platforms. Lifts are being installed for people with restricted
mobility, and the toilets and accesses are being redesigned.
Puerta de Batán comprises a new station constructed on Metro land at
Casa de Campo Park, which will serve as an interchange between Lines 5 and 10,
and will connect with Line 10 extension to Metrosur. This station is being constructed
in the open air, using piles and prefabricated or in-situ concrete segments.
Line Tunnel
It is important to note that the section is greatly restricted by the geometry
of the tunnel and the existing stations, and the aim of the work, to enable
type 6000 rolling stock to pass through, should be carried out with the minimum
work possible in the tunnel.
About 120 m of tunnel needs to be enlarged, between PKS 21+080 and 21+200. In
this way, the new route and the new gauge can run together. To do this, the
tunnel arch needs to be enlarged by 90 cm at the worst point, and by 40 cm in
the area of the Plaza de España Station. The phases necessary are as
follows (Fig. 2): partial demolition by sections of the existing side walls,
and excavation to the new level of the roof (carried out without ever undercutting
the tunnel arch, in 2.5 m sections which are abutted underneath; excavation
of a side wall never coincides with an opposite one, and continuous sections
are not permitted); concreting and shuttering of the new side wall; excavation
of the tunnel roof - after undercutting and concreting all of the side walls,
the roof is demolished in 10 m sections, and excavated to the new level; concreting
the tunnel roof; injection of fill material at the joints of concrete sections
of different ages; and scabbling the tunnel wall, depending on the needs of
the section.
In the case of the straight, horseshoe-shaped El Lago tunnel, it was possible
to prop with a unique type of support to enable the work. In this case, the
tunnel arch only needs to be reduced by 70 cm along a 540 m length, between
PKS 23+210 and 23+750.
In some areas, to modify the tunnel cross-section for the new gauge, it just
needs to be scabbled, along both the side walls and the shoulders of the tunnel,
without needing to excavate the roof of the tunnel. This occurs in six different
sections, in total about 225 m long.
After completing this work, and in all the sections where work had not previously
been done, the present track, generally on ballast, has to be dismantled, and
the new line is laid on slabs with the sleepers establishing the new gauge.
Lengthening
Stations
Lengthening of the underground stations involves a 20 m extension of one of
the end walls in Tribunal and Alonso Martínez, and 10 m at each end wall
in Plaza de España. The work at Alonso Martínez and Tribunal stations
is being carried out simultaneously, by excavating a circular cavern in the
tunnel section, using the German method, and then by demolishing and reconcreting
the roof. The phases of work are as follows (Fig. 3): excavation of the upper
section of the side-wall gallery, and shoring with trusses and wooden planks;
excavation of undercut, immediately followed by concreting of the side-wall
gallery; excavation of the advancing gallery together with shoring by planks
and trusses; excavation for 2 m wide struts, from the side-wall gallery, shoring
with wooden planks, stantions, and metal bracing, concreting of struts, connecting
gallery and set-back upper gallery; excavation in phases of the invert, protected
by the ring already constructed, and demolition of existing tunnel; excavation
and concreting of the tunnel arch in phases; injection of fill material into
the extrados.
The process followed in both tunnels has been very similar, only with a variation
in the dimensions of the struts. They are less than 1.5 m in the Alonso Martínez
Station because they were excavated in miga sand, with abundant water. In this
station, it was also possible to excavate the connecting gallery from an existing
ventilation shaft.
In contrast, even when the Tribunal Station was excavated in firmer ground,
given the existence of old buildings at the surface, some with significant symptoms
of previous problems, it was considered necessary to carry out compensation
injection, after completing an analysis of the building affected and estimating
the surface settlement.
Although the construction of the Plaza de España Station is essentially
considered to be the same method as previously described, the reality is quite
different. Firstly, as already indicated, the station is extended at the two
end walls. Secondly, the station access "crabs" and the escalator
exit halls were symmetrically constructed. Thirdly, it was a station with side
platforms and a central platform, so it had the corresponding connection tunnels.
As a result, although moving away from the strut method previously explained,
it would be adapted to the different circumstances, making use of the existing
construction, and optimising the geometry of the cross-section of the extension
(Fig. 4).
The connection tunnel was enlarged, making use of the existing tunnels to construct
the side walls of the new section of tunnel, and excavating the roof by the
Belgian Method.
Compensation
Injection
Extension of the Tribunal Station is also included within the project to Adapt
the Gauge of Line 10 of the Madrid Metro. The corresponding excavation work
and concreting of the struts, demolition of the old station, and construction
of the new roof to complete the station, was completed under an area of old
buildings, located between La Palma and San Vicente Ferrer streets, behind the
National Audit Office.
Although the studies characterised the possible damage to affected buildings
as "unappreciable" or "very slight", the state of the buildings,
their age, and the type of structure, made it advisable to take special measures
to limit possible settlement. To protect these structures, the necessary compensation
injection was calculated and carried out, together with the installation of
suitable equipment to constantly monitor the possible movements induced by the
nearby excavation work.
For the purpose of monitoring both the movements of the buildings and the ground
in the possible area affected by compensation injection, 55 monitoring strips
in buildings, and 14 bench marks in the ground, were established. Two bench
marks were set for height reference, and to check the precision of the instruments.
After that, targets were fixed at the top of the façade, and a measuring
strip fixed to the base of the building, to measure any change in verticality
of the building.
The results were analysed on a daily basis and compared with the previously
established limits of movement, and summarised in a weekly report. During the
pre-treatment phase, the objective was to produce heaving of between 0 and 3
mm. Afterwards, the limit for more compensation injections was set at a settlement
of 2.5 mm, with respect to the end of the pre-treatment injections.
The observations for verticality have shown that the buildings have not suffered
any inclination that could have proven harmful to the structural integrity of
the buildings at any time.
Station Restoration
The Lago and Batán stations are beautiful examples of restoration of
old stations. Beyond the strictly geometrical considerations, and adaptation
of the gauge, the functionality of the surface level halls has been improved
within the fabric of the old buildings.
The Lago Station building is founded on the connecting tunnels of the station,
such that the trains entering and exiting the station pass below the building.
(Fig. 5).
The columns of the floor below were supported on the side walls of these tunnels,
with the space between the supports being the correct distance for type 2000
rolling stock. The results of a topographical study showed that the columns
had been constructed in groups at the lower section of the side walls, without
any space to increase the tunnel width to allow the type 6000 rolling stock
to pass through. It was therefore necessary to modify the foundations of the
building.
It was decided not to alter the position of the points of support, in order
to conserve the existing buildings as well as possible. As a result, a slab
was constructed beneath the existing foundations, to support the loading previously
taken by the tunnel walls. This slab will be the upper part of a double-cell
frame, which will act as a false tunnel at the exit wall of the station.
The solution consists of the following phases: construction of an auxiliary
metal shoring frame for each of the columns, to transmit the load to the lower
level of the future slab; hydraulic jacks used to apply a load on the superstructure
which is equal to the load on the shored columns, but in the opposite sense,
thus leaving the existing columns completely unloaded; construction of the double-cell
frame, including the upper slab; unloading the auxiliary metal frame and returning
the loading to the original columns, now supported by a double-cell frame.
In the Batán Station, the building is at one side of a platform, so the
previous process is not necessary. It can simply be redesigned.
By eliminating the central platform, the side platforms can be extended and
thereby have sufficient space for panoramic lifts, at both Lago and Batán
stations.
Puerta Batan
Station
The new station, between the existing Batán and Campamento stations,
is situated within the section of land presently occupied by Line 10 of the
Metro, near where Paseo de la Puerta de Batán road crosses over the line,
from which it takes its name. As both lines 10 and 5 of the Metro pass through
the station, the transfer of commuters will remain the same. The station has
four tracks: the outer lines for Line 10; and the central lines for Line 5.
In the first phase however, it is planned to use only one of the two available
tracks for Line 5.
Amongst the various criteria established for the design of the project, two
directly affect the Puerta Batán Station, and both are related to land.
The first states that the station should be located within railway land, and
the second states that the barrier effect should be minimised as the line passes
through Casa de Campo Park.
With respect to these criteria, a long section of the railway line passing through
Casa de Campo Park was covered to reduce the barrier effect, thereby giving
continuity to this urban park. In this area, which is approximately 800 m long,
the new tracks, with an axis precisely coinciding in plan view with the axis
of the old route, run below the level of the old track. The station is also
completely integrated within the aforementioned covered area.
As can be seen on the plan view and the cross-sections enclosed (Fig. 6, 7a
and 7b), the length of this covered area is limited by two lines of piles, the
upper sections of which are capped by interlinking beams, and an earth retaining
screen wall. The characteristics of the retaining wall are as follows: 1 m-diameter
piles in situ; 1.2 m between centres of piles; 19 m minimum depth; 32 m maximum
depth; lower section gunited with 70-mm thick layer covering metal mesh pinned
to the piles.
The pile capping on the interlinking beams supports the roof construction. This
consists of a series of pre-stressed bevelled beams, lights, and variable separation,
and a 250-mm concrete slab cast in situ, with light reinforcement.
The new tunnel, which will be excavated using the traditional Madrid Method,
commences at the end of the covered section, at a depth of about 20 m. The extension
to Line 10 will run through the tunnel, to the connection with Metrosur.
Extension of Line 10 from Colonia Jardin to Cuatro Vientos
Section 1A
Contractor FCC
The extension of Line 10 is underway, with two sections currently being built. The first, which is discussed here, was awarded to FCC. It is worth Pta11,348,959,338 and has a duration of 20 months. It will include the future stations of Colonia Jardín and Cuatro Vientos, supporting the north-centre-west Madrid axis, and helping, in the short term, to complement public transport services in the La Latina district. It will serve as the basis for future development of the Campamento town planning operation that involves building two new stations, Darío Gazapo and Parque Europa.
TBM to Cuatro
Vientos
The contract was awarded in May, 2000, and commences with a 50 m-long tunnel
excavated by the traditional Madrid Method as far as the future station of Colonia
Jardín. This area then acted as a launch pit for the TBM La Adelantada,
which has since bored 2,791 m of twin-track tunnel in an east-west direction
(Madrid-Alcorcón) with an internal circular section measuring 8.43 m
in diameter. The TBM was dismantled in a pit located at the Cuatro Vientos station,
where the twin-track tunnel connects with an 89 m-long double telescope, executed
between continuous screens and pile walls. This section crosses the M-502 and
N-V highways, and involved diverting three important water-distribution arteries
as well as two major telephone ducts.
The emergency exits from the tunnel, and the ventilation shafts, are being utilised
during the operational phase before the start-up. They will be required in the
future for passenger safety, when the distances between the four stations will
be 593 m, 1,027 m and 873 m. This entails a large air extraction shaft, and
compatible dimensions on emergency exits 1 and 5 for future ventilation requirements.
Stations
The stations will be cut and cover, using reinforced concrete continuous screens.
The Colonia Jardín station will be located under the M-502 Carabanchel-Aravaca
highway, which had to be re-routed during its construction in phases. An unusual
feature of this station is that, even though it has three levels due to the
depth of the tunnel, it will have direct access from Calle Sedano to the vestibule.
This will allow it to become a future interchange with the inter-urban bus line,
and the Pozuelo-Boadilla-Carabanchel light railway.
The Cuatro Vientos station has two levels, and will act as an interchange with
Renfe Cercanías Line C-5. This will involve building a 50 m-long tunnel
using the traditional Madrid Method under the N-V to execute the north access,
and a caisson sunk under the C-5 for the interchange.
Construction
The excavation of the tunnel between Colonia Jardín and Cuatro Vientos
is being carried out using a 9.38 m-diameter NFM EPB TBM known as Adelantada.
One of the main features of this type of shield is the capability of keeping
pressure at the front of the machine, using the spoil treated with biodegradable
foams.
Counter-pressure at the front is obtained by using the stored material in a
chamber located immediately behind the cutter wheel. This chamber is kept permanently
full of material with a plastic-fluid consistency. This is extracted from the
chamber at the same rate that the spoil enters, using a screw ring to unload
spoil onto a conveyor, to be transported to muck skips hauled by diesel or battery
electric locomotives.
Care must be taken to manage the counter-pressure used at the front of the excavation,
to keep it within precise limits. Insufficient earth pressure in the mixing
chamber will produce decompression at the front, and result in settlement. Conversely,
too much pressure could lead to uplift. Earth pressure should be controlled
inside the chamber, to balance the speed of the TBM as it moves forward with
the speed of the screw extraction.
The shield moves forward using a series of powerful hydraulic jacks that thrust
against the last ring of the segmental lining. The jacks are fastened to the
front section of the shield liner, and their free ends have a footing that pushes
on the lining.
Segmental Ring
The TBM has an erection system that can position the lining, which is built
of seven reinforced precast concrete segments, with a thickness of 0.32 m and
an average length of 1.5 m. The mucking train carries the segments to the front
of the TBM in each cycle. The internal diameter of the lining is 8.43 m, in
accordance with the gauges the Madrid Metro requires, and the external diameter
is 9.07 m.
The universal ring of trapezoidal arches is used. Each ring is made up of seven
different segments, the key segment being tapered, and the other six at an angle
of 332.308º to the centre. The width of the rings varies from 1.459 m to
1.542 m.
The rings are joined together using 13 steel bolts set at equal distances apart,
with 27.692º between each. There are two bolts per segment, except for
the key, which only has one. The ring, therefore, has thirteen different positions
of the key segment. Radially, each segment is linked to the next one by four
galvanised straight bolts. The basic function of the radial and longitudinal
bolts is to ensure the ring remains stable during assembly, and before it is
loaded when the shield moves forward. A flexible elastomer seal has been fitted
to all radial and longitudinal joints, to make the tunnel waterproof.
The longitudinal bolting and, to a lesser extent, the radial bolting, generate
an initial state of compression in the joints, which improves the tunnel's waterproofing.
The segment strengths were calculated taking account of their positioning, storage,
transport and manipulation, as well as the force from the jacks during the excavation
of the tunnel.
The annulus between the excavated section and the external lining contour is
injected quickly, to reduce the risk of subsidence as much as possible. Injection
is performed from the tailskin of the shield, and is undertaken during the excavation
phase of each work cycle as the shield moves forward. Injection allows the earth
to recompress, partially compensating for the relaxation that occurred during
excavation. The gap between the excavation contour and the extrados is between
7 and 10 cm thick.
Colonia Jardin
Launch
The TBM was launched at the Colonia Jardín station, where a thrust structure
helped in the excavation of the first metres of the tunnel, and the installation
of the first segmental rings against which the TBM's hydraulic jacks thrust
it forward.
The Colonia Jardín station will also be used to extract spoil through
an access ramp installed for that purpose, and to load segments directly onto
the service train. All the installations needed for the TBM to work are available
in the area adjoining the station, including crane, gantry crane, transformers,
water-regulator deposit and the repair workshop.
The TBM will be removed from the walled area established for that purpose, next
to the Cuatro Vientos station.
La Adelantada TBM has exceeded planned progress in this section, reaching an
average of 20 m/day, and a best day of 42 m. It also established a world record
monthly advance for EPB TBMs of this diameter, completing 939 m in 30 consecutive
days.
Typical Geology
The soils in which this section of the work is taking place are typical of Madrid.
At the beginning of the section there is an old riverbed, which features tosco
sands with thin layers of very clean micaceous sands that contain suspended
water pockets and grainy, alluvial soils. There is an aquifer in the key of
the tunnel, made up of alternating levels of sandy tosco and clay tosco that
release water when they are cut by the section of the tunnel.
The situation in the rest of the section is similar, but the thickness of the
waterproofing layer decreases as the tunnel heads towards Alcorcón. The
water table continually crosses the TBM at different heights of the machine's
cutter section.
There is no appreciable change in soil type, and sandy soil, tosco sands, and
sandy tosco and tosco continue to prevail. At the end of the section, where
it reaches Cuatro Vientos station, the tunnel cuts the wall of the super-adjacent
quaternary deposits, at which point the water table is below the section, but
maintained by a 2 m-thick waterproofing layer.
The project includes a budget of around Pta120 million for subsidence monitoring
and instrumentation, both in the tunnel and in particular station walls. Three
rings have been used for the TBM tunnel, and extensometers and pressure cells
have been placed there, along with regular convergence control.
Four wall modules have been positioned in the stations with different extensometers,
inclinometers and pressure cells, and their data is checked during the various
execution phases of the work.
M³ of excavation of screens/piles | 33,538 |
M³ of earth excavation | 366,500 |
Kg of iron | 5,708,408 |
M³ of concrete | 104,600 |
LM of tunnel (twin track) | 2,782 |
LM of rails | 12,126 |
Budget | 11,384,359,338 ptas |
Execution time | 20 months (June 2000-January 2002) |
Twin Tubes from Cuatro Vientos to Alcorcon
Section 2
Contractor Dragados
The extension
of Line 10 Metro of Madrid is split into two sections. Section 1 starts in the
station of Puerta of Batán, and ends at Cuatro Vientos. Section 2 between
Cuatro-Vientos and Alcorcón. The extension will complete the train infrastructure
required for the public transport system in the towns around the N-V highway.
It will also facilitate the connection of Metrosur with the Centre of Madrid,
while improving the utilisation of Renfe Line C-5.
The connection between Alcorcón and Madrid will be much improved, leaving
open the possibility of a further extension south. It will also promote future
urban construction projects. Interchanges will be effected with the lines to
Cuatro Vientos, Príncipe Pío, Nuevos Ministerios and Chamartín,
to Metrosur at Ondarreta, and also with interurban bus services at Cuatro Vientos.
The project comprises 6.123 km of tunnel, one station of 121 m, a telescope
and a 377 m-long twin-track manoeuvring zone. It also includes 835.6 m of single-track
branch lines that connect Line 10 with the train parking facilities for Metrosur
and Line 10. The contract value is Pta16.583.275 and the duration is 19 months,
from July, 2000 to January, 2002.
Constraints
There are three types of constraints on this contract: those posed by the alignment,
foundations of buildings, and existing services.
It has been necessary to co-ordinate the alignment with adjacent facilities,
particularly with Section I of the Line 10 extension where the telescope forms
the way out of Cuatro Vientos station, changing from twin-track tunnel to twin
single-track tunnels. It was also necessary to define the best way to retrieve
the tunnelling machine at the completion of its drive.
The alignment has also, of course, been dictated by the need for the connection
with Section XII of Metrosur, that traverses Leganés Avenue.
The following are the main parameters of design: minimum radius of track curves
300 m, reducing to 80 m along the access route to the train parking facility;
maximum ramp slope 3.5%; parabolic parameter, Kv = 2,000 m; alignment of stations
horizontal, straight, minimum 115 m-long.
Construction
This section of the Line 10 extension project starts at the end of the telescope
at the Cuatro Vientos station. The telescope was necessary in order to change
over from Section 1 twin-track tunnel to Section 2 twin single-track tunnels.
The first part of the project covers the tunnel between the N-V road and the
railway Line C5, near the Cuatro Vientos Station. The twin single-track tunnels
start from this point and cross under the railway line, and the south part of
the military installations of the Regimiento of Zapador Ferroviarios, going
towards the Valley of The Mimbreras, passing under the M-40 and the Golf Course
of Club Deportivo Militar Barberán.
Along the Mimbreras section, two big telescopes have been constructed between
pile walls that will permit the connection between Line 10 and the branch lines
to access the train parking sidings for Metrosur and Line 10. These are situated
between the airport of Cuatro Vientos and the M-40. In order to facilitate this
connection, three single-track branches have been designed using piled walls.
These will allow movement of trains in both directions, towards Alcorcón
and Madrid.
From this worksite, the alignment passes under a village of gypsies, as it moves
from the municipality of Madrid to Alcorcón. It passes under the M-40
to the N-V, through the park and river of the Canaleja, and the Circumvallation
North de Alcorcón Avenue, before entering in Alcorcón.
The route into the town of Alcorcón is south along the Alcalde Joaquín
Vilumbrales Avenue, and the tunnel continues along similar avenues until its
conclusion. It crosses de Castillos Avenue, between the streets of Mercurio
and Carballino, to reach the Alcorcón North Station, where the twin tunnels
will be completed and a telescope junction will be built.
Beyond the telescope is the manoeuvring zone, which will have sufficient length
to park trains if necessary, without the need to enter Metrosur.
The design of the tunnels provides four emergency exits, all of which are connected
to both tunnels. Two of these also act as ventilation points, the third houses
a transformer room for the Mimbreras complex, and the fourth a pumping well
situated in the lowest point of the tunnel.
Also, independently of the four emergency exits, there are three other connections
between the twin tunnels in order to maintain the distances between connections
below 500 m.
The project specifically includes the following works: station infrastructure;
ventilation system, wells and ventilation rooms; emergency exits; draining and
pumping of water; station architecture; Line 10 extension tunnels to Metrosur;
stations and tunnels illumination and power of station; replacement of affected
services; traffic management; and environmental works.
Geology and
Geotechnics
The alignment of contract 2 of the Line 10 extension passes through the Madrid
facies, on which are occasionally superimposed more recent soils which are sometimes
difficult to distinguish because they are of similar origin. These comprise
artificial fills and some small parts of recent alluvial flows, with fine and
coarse sand and other materials originating in the decomposition of granites
and gneisses from the Guadarrama mountains. Their composition is principally
of feldspar sand in a matrix of yellowish clays.
Simply put, the major part of thick materials is present in the upper section,
thinning at depth. These major parts do not exclude the participation of one
in another. Sand sections have blocks of clay, and in the thin parts there are
zones mainly made of sand.
At the start of the alignment, there is mainly fine sand. This was detected
continuously in the drilling tests, with high water levels in the area of Cuatro
Vientos. This general continuity carries through towards Arroyo de la Canaleja,
with occasional lenses that have more coarse sand.
Construction
The station is being constructed with concrete walls and large pile columns
that will support the concrete cover slab. Once the cover slab was cast, the
traffic could be rerouted over it while work continued beneath. Excavation of
the ground between the walls beneath the concrete cover slab was undertaken,
and the wall ties at the intermediate levels were installed.
The sequence of work was as follows: excavation of the surface area of the station;
installation of the concrete walls; casting of concrete cover slab; excavation
under the concrete cover slab, construction of the invert.
The station is designed with the approximate measurements of 121 m length and
26 m width, with central platform of 115 m-long and 16 m-wide.
For the tunnel drive a Lovat EPB is being used, with a closed front and ground
pressure balance. This permits a minimal decompression of the ground, and avoids
the formation of chimneys. By means of a concurrent injection system that fills
up the annular space between the ground and the machine, any slump behind the
machine is avoided.
A precast segmental concrete lining is built within the tailskin of the machine,
formed by rings of seven pieces and a key. The interior diameter of the ring
is 6.7 m, the thickness is 25 cm, and it has a length of 1.208 m.
The type of ring is left-right, and the invert segment is prepared to mount
the rails of the TBM backup. To drive in a straight line, alternate left and
right rings are erected. The cement grout injection is carried out simultaneously
with the excavation, but there is also the possibility of a post-grouting through
the threaded hole used to engage the erector.
The well was excavated downwards within concrete walls installed from surface,
and the connections between tunnels and well is being excavated by the traditional
Madrid method of tunnelling.
Provisional works are necessary works at some places: like the Mimbreras complex
for the execution of the tunnel; pits for extraction of machinery; and ramps
required for station excavation.
Two TBM retrieval pits have been constructed using pile walls: one at Cuatro
Vientos and the other at Alcorcón station. The telescope of Mimbreras
was used for launching the TBM in both directions, and will be used for its
final extraction.
Muck trains comprising seven 10 cu m Muhlhauser skips, two segment cars and
a grout transfer car are too heavy for conventional locomotives on the 3.3%
maximum gradients, so rubber tyred Zephir locomotives are used. These have tracking
bogies front and rear, and derive their traction from four rubber-tyred wheels
travelling on the invert, which has high-friction paths for the purpose. One
ring of advance requires 6.5 cars, and takes between 30 and 45 minutes to complete.
The Lovat has achieved a best day of 53 m, and 938 m in one month.
The new Dragados segment plant at Talavera is supplying 21 rings/day to Line
10 contracts.
Line
10 extension of Madrid Metro, Contract 2 Cuatro Vientos - Alcorcon |
|
m³ of wall excavation/piles | 42,558 |
m³ of ground excavation | 518,979 |
Kg of steel | 9,307,044 |
m³ of concrete | 156,210 |
m of tunnel | 6,123 |
m of rail | 16,039 |
Cost | Pta13,881,616,385 |
Contract duration | 19 months (July, 2000 - Jan, 2002) |
Boxed Item
Lovat EPB TBM
Cibeles
Earth pressure balance allows tunnel advance with minimum decompression of the
ground and avoidance of collapse. The excavation diameter is 7.38 m and the
precast segmental concrete lining produces an internal free section of 6.7 m-diameter.
The segments are bolted together within the TBM tail shield, using high-strength
bolts.
The TBM advances using 24 hydraulic cylinders that push on the last-erected
ring.
The contact surface between the ring and each cylinder is a plate of 700 mm-long
by 150 mm-wide in order to spread the load as evenly as possible. If any angularity
occurs between the thrust plates and the lining, it is necessary to use wedges.
The maximum force of each thrust cylinder is 125 t, which represents a maximum
thrust on each completed ring of 3,000 t.
Model: Lovat
M-288SE Serial 13000
Boring Diameter: 7.35 m
Total length: 8.30 m
Total power: 6 electric motors x 300 hp, total 1,800 hp
Transmission: 16 hydraulic motors (max 4.8 rpm).
Grippers: 24 x 125 t
Total thrust: 3,000 t
Cuatro Vientos Depot and Access
Line 10 Depot
Contractor Cocheras UTE
The project
to build the new depot to serve Metro line 10 was awarded in December, 2000
to Cocheras, the Temporary Union (UTE) formed by the firms Sacyr and Corsán-Corviam.
The contract has a period of 12 months and the budget for the award is Pta 6,446,964,415.
The job can be subdivided into the following sections: access tunnel to the
railway yard, comprising tunnel between screens and traditional-method tunnel;
railway yard and tunnel superstructure; main depot bay; auxiliary building and
substation; blowing, washing, go-devil and dock bays; and facilities and sundry
features.
Railway Yard
Access
The access tunnel to the railway yard requires two types of tunnelling: between
screens and traditional. Three junctioning branch lines are being built into
the current extension of line 10, just north of the Mimbreras complex, and this
is where the Cocheras tunnels commence. These are single-track branch lines,
with lengths of 90 m, 20 m and 15 m respectively, which converge in a telescope
into a twin-track tunnel with a length of 677 m. Despite being a small part
of the total tunnelling involved for line 10, the depot access tunnels are on
the critical path because they are needed for the delivery of the new 6000 class
trains. These will start appearing in Autumn, 2001, and will be tested using
the proposed line 10 signalling and 1,500 V electrical systems.
The tunnels were constructed by the cut and cover method, using 80 cm-diameter
piles to an average depth of 14 m. The slab that covers the tunnel is of reinforced
concrete with an edge of 0.8 m and a width of 8.2 m in single-track tunnels,
and width of 5.2 m in the rest, reinforced by 140 kg/cu m steel rebar. Excavated
muck from the single-track tunnels was brought out via a purpose-built dirt
ramp.
Once the pile screen was cleaned off, a mat was placed on the surface and shotcreted
with three layers, reaching a final thickness of 15 cm.
Part of the twin-track tunnel was excavated in four phases beneath the M-40
highway, which is a major ring road around Madrid. The same system of excavation
was successfully employed, and lane diversions ensured that the traffic was
never stopped.
On the side where the railway yard converges, 70 m of tunnel were executed using
the Madrid traditional method. The portal of the tunnel was established with
a row of micropiles of 127 mm-diameter, with a 5 mm-thick, 80 mm-diameter tubular
steel frame, injected with a cement mortar. The face was advanced in 1.25 m
increments in the damp, loose ground, with less than 4 m cover to surface.
Railway Yard
In order to execute the railway yard that is located at tunnel exit, some 300,000
cu m of earth was shifted. This terrain was substituted with selected material
forming a drainage network. After this shaping layer, sub-ballast was spread,
and the track was laid on the ballast.
The railway yard is made up of a group of 33 tracks of UIC54 rails with monobloc
concrete sleepers. The fastenings are of Vossloh HM type, and there are 40 side-tracks
of TG 0.125 set on akoga sleepers to facilitate a full variety of train movements.
The tracks give access to both the main bay and the blowing, washing, go-devil
and dock bays.
Altogether there are approximately 5.4 km of tracks in the yard.
The railway in the tunnels is made up of concreted track set on elastic blocks
with Pandrol-type fastenings. This has two complete rerailers in the line tunnel,
as well as a sidetrack of TG 0.125, also on elastic block.
Main depot
bay.
The main depot bay consists of five subdivisions: Parking 1, 2, 3, maintenance,
and pits. It has a surface area of 19,152 sq m.
The structure of the bay is of prefabricated concrete in posts, beams and belts.
It has a deep foundation made of 50 mm piles. The cover is of ribbed panellised
50 mm plate, pre-lacquered with translucent panels as skylights. The outer closing
is also prefabricated concrete with a white arid finish.
In the maintenance bay there are six tracks, each 120 m-long set on a metallic
structure, with "Iberacero" type fastenings and elastic supports.
In the parking bays there are 24 tracks, each 120 m-long and set on rigid blocks.
In the front of the depot, the group of tracks changes onto a monobloc sleeper
to allow vehicles to pass.
Auxiliary building
and substation.
The auxiliary building is adjacent to the main bay and has an area of 2,570
sq m. It has two storeys with pre-stressed honeycomb plates. Here are found
the offices, locker rooms, bathroom facilities and other rooms (simulation room,
professional training, etc.).
Attached to another part of the main bay building is the electric substation
that provides energy to the entire depot.
Blowing, washing,
go-devil and dock bays.
From the group of tracks, a sidetrack is set up that leads to the building where
the bays are located for the blowing and washing of the trains, for parking
and maintenance of go-devils, and loading dock.
Facilities and sundry features.
This project also includes the complete facilities of gas, heating, fire protection,
water supply, electrical energy, interior and exterior illumination, grease
and oils, compressed air, as well as an anti-intrusion protection system. The
entire area is urbanised, with its drainage and sanitation networks.
A drainage channel has been excavated and lined to takes surface run-off water
from the adjacent M-40 motorway. Access ways will be left, as will footpaths.
The perimeter of the entire facility will be fenced to Metro standard, following
which the surrounding area will be returned to its previous environmental state.