Norway

Norway, Vestfold - no/62

Ring Road

Open call for bids, deadline 16th February, 2004 for construction of a 4-lane ring road including a dual-lane rock tunnel in Vestfold county. Length: 2 x 1,650 m, width: 9.5 m. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=215633-2003, OJ S 242, or contact Statens vegvesen Region south, Arendal, fax +47 33355601. E-mail oddvar.bakken@vegvesen.no 02/04.



Permalink

Norway, Sogn og Fjordane - no/61

Highway

Open invitation to tender, deadline 9th December, 2003 for construction of highway E134 between Grostí¸l and Rullestadvatn west (6,048 m), including a 2,969 m-long tunnel. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=182442-2003, OJ S 202, or contact Statens vegvesen Region vest, Leikanger, fax +47 91749162. E-mail oddsav@vegvesen.no 44/03.



Permalink

Norway, Bergen - no/60

Water Treatment

Prequalification notice, deadline 15th October, 2003 for the expansion and upgrading of the Svartediket water treatment plant, 2 km southwest of Bergen city centre. Includes a new treatment plant cavern in rock (length 83 m x width 21 m x height 16 m), a new deep water intake (length 120 m x width 4 m x height 4 m), a new clean water basin in rock (length 138 m x width 18 m x height 7 m), and approximately 2.5 km of tunnel. The main tunnel will be 1.3 km-long, cross section 4.3 x 5.5 m. Other cross section will be 21 x 16 m. Planning and engineering by Asplan Viak and GeoBergen. Tunnel design by Smidt & Ingebrigtsen. Construction to start in April 2004 for completion in October 2006. Financing by the City of Bergen. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=152591-2003, OJ S 166, or contact Bergen kommune, Bergen, fax +47 55566433. E-mail rune.torsvik@bergen.kommune.no and arne.halvorsen@bergen.kommune.no 38/03.NCC has secured the construction contract for the expansion of the Svartediket water treatment plant which includes a cavern in rock (length 83 m x width 21 m x height 16 m), a water intake (length 120 m x width 4 m x height 4 m), a clean water basin in rock (length 138 m x width 18 m x height 7 m), and approximately 2.5 km of tunnel. Click no/60. Visit www.ncc.no 24/04.



Permalink

Norway, Nordland - no/59

Road

Open call for bids, deadline 30th June, 2003 for construction of 14.4 km road section Gullersfjordbotn-Austerstraumen, including the 6.4 km Sí¸rdals tunnel. It is a 8.5 m-wide single-tube tunnel to be blasted in gneiss. Rockbolts and shotcrete will be implemented for the support and dumper trucks will be used for muck removal. Cost: NOK320 million approximately, financed by the national public roads administration. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=096200-2003, OJ S 107, or contact Statens Vegvesen Region nord, Bodí¸, fax +47 75552951. E-mail firmapost-nord@vegvesen.no and einar.karlsen@vegvesen.no 24/03.The three bidders for the construction of the Gullersfjordbotn-Austerstraumen road section including the 6.4 km Sí¸rdals tunnel through the Brynjulfslí¥ttheia mountain are Scandinavian Rock Group (lowest bidder with NOK212.7 million), Leonhard Nilsen & Sí¸nner (NOK224.7 million) and Mesta AS (NOK 233.4 million). 29/03.Scandinavian Rock Group (SRG) will build road section Gullersfjordbotn-Austerstraumen, including the 6.4 km-long 8.5 m-wide Sí¸rdals tunnel, a single bore to be blasted in gneiss. Contract value NOK212.7 million. Visit www.srg.no 36/03.Open invitation to tender, deadline 7th November, 2005 for the delivery of directional control fans for four tunnels: Soerdals (6,370 m), Ingelsfjord tunnel (1,240 m), Raftsund (1,530 m) and Fjoesdal (1,600 m). Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=177580-2005, OJ S 179, or contact Statens vegvesen, Bodoe, fax +47 75586501. E-mail robjak@vegvesen.no 38/05.



Permalink

Norway, Rogaland - no/58

Road

Open call for bids, deadline 7th July, 2003 for construction of the Iversflaten tunnel, approximately 1 km, plus electro works on county road Rv 13. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=086656-2003, OJ S 96, or contact Statens Vegvesen region west, Leikanger, fax +47 57655986 or 51911791. E-mail reg-3@vegvesen.no and knut.utaaker@vegvesen.no 22/03.Open call for bids, deadline 16th May, 2006 for construction of a new 6.8 km road (Rv 519) from Hanasand to Ladstein. The project will supply a mainland connection to Finní¸y and Talgje islands from Hanasand. The project comprises an approx. 5.8 km subsea tunnel, T-crossings with access ramps in the main tunnel, an approx. 1.5 km tunnel to Talgje island and approx. 1.3 km of road in open air. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=056702-2006, OJ S 54, or contact Statens vegvesen Region west, Leikanger, fax +47 57655986. E-mail rolf.harkestad@vegvesen.no 12/06.



Permalink

Norway, More & Romsdal - no/57

Roadway

Open call for bids, deadline 26th May, 2003 for collection, interpretation and reporting of refraction and reflection seismic measurements at sea and on land for three subsea tunnel projects named Langfjord connection, Sande mainland connection and Mí¸re connection. Length is still not decided but Langfjorden will be approximately 6.7 km, Sande approximately 6.2 km and Mí¸re around 7.5 km. Tunnel profile T8.5 (width 8.5 m for two lanes). Expected geology for the Mí¸re and Langfjorden connections will be mainly gneisses and for the Sande connection, some gneisses and some limestone/marble. Drill/blast tunnelling. Support with shotcrete, rock bolts and armed shotcrete arches. Projects in early design. Estimated costs: NOK400-800 million (Langfjorden), NOK350-800 million (Sande) and NOK450-1,000 million (Mí¸re). Financing probably by toll. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=060728-2003, OJ S 69, or contact Statens Vegvesen Region Midt, Molde, fax +47 71274101. E-mail torkild.andal@vegvesen.no 19/03.



Permalink

Norway, Oslo - no/56

Highway

Open call for bids, deadline 2nd June, 2003 for construction plans, tender documents and follow-up during construction for a new 700 m immersed tunnel under the Oslo harbour at Bjí¸rvika between the Festnings tunnel and the Ekeberg tunnel on road E18, including connections with the existing road/street network. The works consist of engineering design services for big concrete constructions, complicated foundation works and rock tunnels. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=063650-2003, OJ S 72, or contact Norwegian national road administration, Oslo, fax +47 23054158 or 4001. E-mail svein.roed@vegvesen.no. Visit www.vegvesen.no/oslo/bjorvika/bjorvika.stm 16/03.Open procedure, deadline 20th May, 2005 for construction of the Bjoervika immersed tunnel under Oslo Harbour. It is a 675 m tunnel connecting the existing Festning and Ekeberg tunnels. The tunnel has 2 x 3 lanes. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=031938-2005, OJ S 33, or contact Statens vegvesen Region east, Lillehammer, fax +47 61257480 or 24058774. E-mail firmapost@vegvesen.no or sveroe@vegvesen.no. Subscribe to E-News Weekly 4/2005. 08/05.The Norwegian public roads administration announced its intention to award the Sjoedel contract to Skanska, Bam Civiel and Volker Stevin, who submit an offer of NOK968 million for the immersed tunnel piece in the Bjoervika project at Oslo harbour. The project consists of a 670 m-long 35 to 40 m-wide 6-element immersed tube at 112 m under the sea level. The contract is expected to be signed at the beginning of August with work on site starting at the beginning of September when the necessary detailed plans/documentation have been approved. Completion is expected in 2010. Another contract for this project has also been signed. Subscribe to E-News Weekly 28/2005 & 23/2005 and read E-News Weekly 4/2005. Visit www.skanska.no 28/05.Open call for tenders, deadline 5th November, 2007 for delivery of booster fans for the Bjí¸rvika tunnels in Oslo including a 675 m-long immersed tunnel under the harbour and its ramps, 503 m of cut-and-cover tunnels and ramps totalling 1.2 km with a rectangular shape for one, two or three lanes at Sí¸renga, a new 420 m-long 9.5 m-wide rock tunnel in Mosseveien/Grí¸nlia and 620 m of enlarged existing tunnels and the ramps. Read E-News Weekly 39/2007, 40/2005, 28/2005, 26/2005, 23/2005, 4/2005, 18/2002 & 10/2002. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=223948-2007, OJ S 183, or contact Statens vegvesen Region east, Lillehammer, tel. +47 81522000 or 24058759. E-mail mari.barstad@vegvesen.no. Also visit www.vegvesen.no/bjorvika 40/07.Open call for tenders, deadline 22nd May, 2008 for fire protection of the Bjí¸rvika tunnel in Oslo. The contract includes delivery and installation of fire protection on the roof and walls (approx. 39,400 sq m and approx. 10,850 sq m, respectively), delivery and installation of fireproof seals in structure joints (approx. 350 m of element joints in the immersed tunnel section, approx. 1,300 m of segment joints in the immersed tunnel section and approx. 3,300 m, of section joints in the cast-on-site section of the tunnel), engineering design/detailed planning of fire protection/fireproof seals as described above. Read E-News Weekly 39/2007, 40/2005, 28/2005, 26/2005, 23/2005, 4/2005, 18/2002 & 10/2002. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=279483-2007, OJ S 229, or contact Statens vegvesen region east, Lillehammer, tel. +47 81 522000 or fax +47 24058774. E-mail kjell.furre@vegvesen.no 49/07.Vifter & Miljí¸ received a NOK5 million contract for delivery of booster fans for the Bjí¸rvika tunnels in Oslo including a 675 m-long immersed tunnel under the harbour and its ramps, 503 m of cut-and-cover tunnels and ramps totalling 1.2 km with a rectangular shape for one, two or three lanes at Sí¸renga, a new 420 m-long 9.5 m-wide rock tunnel in Mosseveien/Grí¸nlia and 620 m of enlarged existing tunnels and the ramps. Visit www.vifter.no 12/08.Invitation to tender for delivery and installation of shaft fans and associated equipment at four ventilation towers at Bjorvika tunnels on highway E18 in Oslo. http://ted.europa.eu/udl?request=Seek-Deliver&language=es&docid=268483-2008 OJ S202 Tender deadline 27.11.2008 for commencement of works on 19.01.2009 and completion by 01.11.2009. Contact e-mail kjetil.flotre@vegvesen.no tel +47 81 52 20 00. 43/08.



Permalink

Open invitation to tender, deadline 11.05.2009, for delivery of 23 controllable barriers with foundations for newly established closing points in Festning, Bjorvika and Ekeberg tunnels and other associated places on E18 highway. Contract to start 08.06.2009 for completion 01.03.2011. http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=091065-2009Open invitation to tender, deadline 12.05.2009, for 12 LED variable information boards and road signs for Bjorvika tunnel on E18 highway. Contract to start 09.06.2009 for completion 15.02.2010. http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=091066-2009More information, including specs and docs for both bids, from Kjetil Flotre at Statens vegvesen in Lillehammer, tel +47 8152 2000, e-mail kjetil.flotre@vegvesen.no. 14/09.



Permalink

Contract for concrete elements for fireproofing walls of concrete tunnels in the Havnelageret, Sjodelen and Sorenga areas of Bjorvika project awarded to BetongPartner AS, Teglversveien 18, Andalsnes, Norway, value EUR3,467,613 excluding VAT. Typical dimensions of the concrete elements, which are to be tiled on the side facing traffic, are 12-15 cm thickness, 3.5 m height, and 3.3 m length, and a total area of 21,200 sq m is required. See tunnelbuilder archive no/56 for project history. More from BetongPartner, tel +47 712277-40, fax -41, e-mail kontor@betong-partner.no. Further project details from Kjell Furre at Statens vegvesen in Lillehammer, tel +47 81522000, e-mail kjell.furre@vegvesen.no. http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=098031-2009 15/09.



Permalink

Open invitation to tender, deadline 10.06.2009, for delivery and installation of pumps with associated equipment at the pumping station in the Gronlia tunnel of the E18 Bjorvika project. Contract to commence 10.07.2009 for completion 20.11.2009. Specs and docs from Kjetil Flotre at Statens vegvesen in Oslo, tel +47 81522000, e-mail kjetil.flotre@vegvesen.no to whom tenders or requests to participate should be sent. 19/09. Site inspection scheduled for 11.05.2009 at 12.00. http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=124622-2009. 19/09.



Permalink

Open invitation to tender, deadline 24.02.2017, for the renovation of Ekeberg (1580 m, 1580 m) and Svartdals (1460 m, 1700 m) tunnels on the E6/E18 in Oslo, the eastern part of the Opera tunnel. The VALUE Range of the contract is EUR44 - 60.49 million, excluding VAT.

For electronic access to information https://kgv.doffin.no/ctm/Supplier/Documents/Folder/150443. Tenders must be sent to the Norwegian Public Roads Administration, Eastern Region, attn Kjetil Flotre, Oslo, tel  +47 91139522, e-mail kjetil.flotre@vegvesen.no. Contact The Norwegian Public Roads Administration, Eastern Region, attn Pernille| Reistadbakken, Lillehammer,  tel +47 91502030, e-mail firmapost-ost@vegvesen.no. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=456612-2016. Ref.n. 16/73369. 52/16.



Permalink

Skanska has signed the EUR54.56 million contract for the renovation of the Ekeberg (1580 m, 1580 m) and Svartdals (1460 m, 1700 m) tunnels on the E6/E18 in Oslo, Norway. The project consists mainly of electrical work, fire protection and improved cleaning solutions for the tunnels. In addition, new technical buildings will be built, evacuation routes will be upgraded, a new layer of asphalt will be added and all signs will be replaced. The work will begin in the summer of 2017 and will be completed before summer 2019. Contact The Norwegian Public Roads Administration, Eastern Region, attn Pernille| Reistadbakken, Lillehammer,  tel +47 91502030, e-mail firmapost-ost@vegvesen.no. Visit http://group.skanska.com/media/203108/Skanska-renovates-tunnels-in-Oslo%2c-Norway%2c-for-NOK-516M%2c-about-SEK-550M. Ref.n. 16/73369. 19/17.



Permalink

Skanska Norge AS from Oslo secured the contract for the renovation of the Ekeberg (1580 m, 1580 m) and Svartdals (1460 m, 1700 m) tunnels on the E6/E18 in Oslo, which is the eastern part of the Opera tunnel. Contact The Norwegian Public Roads Administration, Eastern Region, attn Pernille| Reistadbakken, Lillehammer,  tel +47 91502030, e-mail firmapost-ost@vegvesen.no. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=318393-2017. Ref.n. 16/73369. 32/17.



Permalink

Competitive procedure with negotiation, deadline 04.02.2019, for the renovation of the Festning tunnel on the E18 highway in Oslo, also the western part of the Opera tunnel and the pump station at Bygdoylokket. The value of the contract is EUR19.42 million, excluding VAT, and the duration of the contract is 17 months. For bid documents and further information  http://eu.eu-supply.com/app/rfq/rwlentrance_s.asp?PID=225727&B=VEGVESEN where offers must be sent. Contact Norwegian Public Roads Administration in Oslo, attn Bjorn Oystein Kroken, tel +47 47272268, email bjorn.kroken@vegvesen.no.Visit

http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=004419-2019.

Ref.n. 18/222374. 02/19.



Permalink

Skanska Norge AS from Oslo secured the EUR27.59 million (NOK267.19 million) contract, excluding VAT, for the renovation of the Festning tunnel on the E18 highway in Oslo, also the western part of the Opera tunnel and the pump station at Bygdoylokket. Contact Norwegian Public Roads Administration in Oslo, attn Bjorn Oystein Kroken, tel +47 47272268, email bjorn.kroken@vegvesen.no.Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=285725-2019.

Ref.n. 18/222374. 26/19.



Permalink

Norway, Hordaland - no/55

Hydropower

Periodic information notice, deadline 17th March, 2003 for construction of the Blí¥fjell power station including a 6.2 km tunnel and a new underground power house. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=038359-2003, OJ S 44, or contact Sunnhordland Kraftlag, Stord, fax +47 53414170. E-mail dagfinn.vatne@sunnhordland-kraftlag.no 11/03.NCC is building the Sima hydro power project in Eidfjord for Statkraft Energi at a cost of NOK31.5 million. The project includes a 1.6 km water tunnel, excavated section 11 sq m, and a 160 m access tunnel, excavated section 14 sq m. Other underground structures include a short shaft (3-5 m) to the inlet concrete construction in Onevatn and another short shaft (2 m) to the existing water tunnel with connection to the Sima power plant. Concrete plug with steel pressure gate in the access tunnel. The excavation method is drill and blast with three drives for the water tunnel. First, 2 x 450 m is bored in alternate excavation from the access tunnel's end. Then, approx. 700 m will be excavated in one-way excavation. One Atlas Copco AC 282 jumbo (model approx. 1995) is used. The geology is massive bedrock (gneiss, granite and megmatite). Support with Orsta bolts, in average 0.2 per metre of tunnel. Loading and haulage with one Toro 301 underground loader equipped with 3 cu m bucket (2 tractors with strengthened trailers). The site is without road access, located approx. 1,000 m above sea level. All equipment transportation is done by helicopter and snow vehicles. The tunnel started on 15th May, 2005 and is expected to finish on 15th October, 2005. All works (except final clearing of the tunnel and inlet sites) to be finished on 1st December, 2005. Visit www.ncc.no, www.atlascopco.com, www.toro.sandvik.com and www.orstastaal.no 35/05.



Permalink

Norway, Vestfold - no/54

Highway

Statkraft Grí¸ner has been awarded a NOK3.5 million engineering design of the Kopstad-Gulli section of highway E18 in Vestfold county, including three bored tunnels: Flí¥r (west tube, 870 m / east tube 850 m), Dí¸vik (west tube, 570 m / east tube, 600 m) and Hem (west tube, 910 m / east tube, 940 m). All T9.5 profile (9.5 m in width). Also two cut-and-cover tunnels: Steinbjí¸rnrí¸d (2 x 110 m, 11 m-wide) and Gulli (2 x 175 m, 13 m-wide). Visit www.vegvesen.no/vestfold and www.statkraftgroner.no 08/03.Open invitation to tender, deadline 26th March, 2004 for construction of a new four-lane section of motorway E 18 from Kopstad to Gulli. Lot 1 Kopstad-Solerí¸d is 5.5 km in length and includes two dual-lane rock tunnels: Flí¥r (west tube, 870 m / east tube 850 m) and Dí¸vik (west tube, 570 m / east tube, 600 m) and one dual-lane cut-and-cover tunnel: Steinbjí¸rnrí¸d (2 x 110 m, 11 m-wide). Lot 2 Solerí¸d-Gulli is 7 km in length and includes one dual-lane rock tunnel: Hem (west tube, 910 m / east tube, 940 m) and two dual-lane cut-and-cover tunnels: Gulli (2 x 175 m, 13 m-wide) and Svartedal (2 x 60 m, 11.5 m-wide). Planned method for rock tunnels is drill/blast with rockbolts and sprayed concrete as support. Work periods: August 2004-October 2007 (lot 1) and October 2004-October 2007 (lot 2). Cost for all tunnels: NOK424 million. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=174131-2003 and http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=174131-2003, OJ S 193, or contact Statens vegvesen Region sí¸r, Arendal, fax +47 33371640. E-mail karl.hoiland@vegvesen.no 43/03.Open call for tenders, deadline 5th October, 2005 for the delivery of booster fans for 3 two-lane tunnels on the E18, section Kopstad-Gulli. Total length: 2 x 2,300 m. Click no/54. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=132093-2005, OJ S 133, or contact Statens vegvesen Region south, Arendal, fax +47 33049995. E-mail oyvinp@vegvesen.no 29/05.



Permalink

Open invitation to tender, deadline 20.05.2011, for construction contract 1, Gulli-Holmene, comprising major upgrade of 6.7 km of 24 km-long E18 Gulli-Langaker highway. Completion deadline 30.10.2014. Further information, specs and docs from Oyvind Pettersen-Dahl at Statens vegvesen Region south in Arendal, tel +47 81548000/33371652/91780274, to whom tenders or requests to participate must be sent. Tender conference at 12.00 on 08.04.2011 at SV project office at Sem in Tonsberg. Register interest at www.doffin.no/Search/Search_Switch.aspx?ID=226163. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=093074-2011. 12/11.



Permalink

Open invitation to tender, deadline 12.08.2011, for construction contract 3, Tassebekk-Langaker, comprising major upgrade of 10.2 km of 24 km-long E18 Gulli-Langaker highway. Further information, specs and docs from Arvid Veseth at Statens vegvesen Region south in Sem, tel +47 33355612/91823741, to whom tenders or requests to participate must be sent. Tender conference at 12.00 on 24.05.2011 at SV project office at Sem in Tonsberg. Register interest at www.doffin.no/Search/Search_Switch.aspx?ID=230635. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=156396-2011. 20/11.



Permalink

Award of contract, value EUR97.12 million excluding VAT, to Skanska Norge of Oslo for construction contract 3, Tassebekk-Langaker, comprising major upgrade of 10.2 km of 24 km-long E18 Gulli-Langaker highway. Further information from Arvid Veseth at Statens vegvesen Region south in Arendal, tel +47 81548000/33355612, e-mail arvid.veseth@vegvesen.no. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=309814-2011. 40/11.



Permalink

Open invitation to tender, deadline 02.04.2013, for electro and SRO works on 24 km-long E18 Gulli-Langaker highway. Completion deadline 30.10.2014. Register interest at www.doffin.no/Search/Search_Switch.aspx?ID=279335. Further information, specs and docs from Oyvind Pettersen-Dahl at Statens vegvesen Region south in Arendal, tel +47 91780274, e-mail oyvinp@vegvesen.no, to whom tenders or requests to participate must be sent. Tender number 2013002973. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=019758-2013. 04/13.



Permalink

Award of contract 2013002973 to Scanmatic Elektro AS of Staubo, Norway for electro and SRO works on 24 km-long E18 Gulli-Langaker highway. Contract completion deadline 30.10.2014. Further information from Oyvind Pettersen-Dahl at Statens vegvesen Region south in Arendal, tel +47 02030, e-mail firmapost-sor@vegvesen.no. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=280152-2013. 34/13.



Permalink

Norway, Vest-Agder - no/53

Highway

Negotiated procedure, deadline 15th January, 2003 for a DBFO contract for the 18 km-long Handeland-Feda section of the 38 km-long Lyngdal-Flekkefjord highway. Eight kilometres will run in tunnel. Tender value NOK1-1.2 billion. Visit http://ted.eur-op.eu.int/udl?request=Seek-Deliver&language=en&docid=155614-2002, OJ S 197 or contact Norwegian public roads administration, Oslo, fax +47 22073673. E-mail firmapost@vegvesen.no 42/02.



Permalink

Open invitation to tender, deadline 15.08.2014, for the renovation of three tunnels on the E39 at Flekkefjord in Vest-Agder county. The three tunnels are Austad (1,040 m), Drangeid (765 m) and Loga (840 m). Contact Statens vegvesen Region South, att.n Oystein Lien, Arendal, tel +47 02030, e-mail oystein.lien@vegvesen.no.  Visit http://ted.eur-op.eu.int/udl?request=Seek-Deliver&language=en&docid=208442-2014. Ref. n. 2014040867. 26/14.



Permalink

Risa A/S of Naerbo secured the EUR17.67 million contract, excluding VAT, for the renovation of three tunnels on the E39 at Flekkefjord in Vest-Agder county. The three tunnels are Austad (1,040 m), Drangeid (765 m) and Loga (840 m). Contact Statens vegvesen Region South, att.n Oystein Lien, Arendal, tel +47 02030, e-mail oystein.lien@vegvesen.no.  Visit http://ted.eur-op.eu.int/udl?request=Seek-Deliver&language=en&docid=372879-2014. Ref. n. 2014040867. 45/14.



Permalink


Negotiated invitation to tender, deadline 05/10/2020, for engineering design, construction of and warranty responsibility for a new four-lane motorway E39 Lyngdal East - Lyngdal West. The stretch between the Herdalen junction and Royskar junction in Lyngdal municipality, includes approx. 2.5 km open air road,  the 3.4km Rossas and the 2.7 km Kalas tunnels, the two bridges Kvelland (over Lygna river) and Harikstad (170 m), two motorway junctions with connections to the existing road network. The value of the contract is EUR288.83 million (NOK2.9 bn), excluding VAT. Duration of the contract is from 28/05/2021 to 31/12/2024. Contact Nye Veier, attn Ruben Ramsland, Kristiansand, email anskaffelser@nyeveier.no. For further on the tender, please click here and here. 37/20.   




Permalink


Nye Veier, planner and operator of Norwegian motorways selected the Joint Venture of Implenia (69%) and Stangeland (31%) as preferred suppliers for the motorway E39 Lyngdal east - Lyngdal west. The route is part of the development E39 Sorvest between Kristiansand and Stavanger, and runs between Herdal and Roysgard in Lyngdal municipality. The legally binding decision and contract award is expected in the middle of July, 2021. It is a EUR 288.83 million (NOK2.9 bn) turnkey contract. Approximately 10 km of four-lane motorway will be built, of which 6.2 km will be tunnels, bridges and level crossings. Construction is scheduled to start in autumn 2021 and will continue until summer 2025.  

Implenia will plan and construct the tunnels as well as the concrete structures while Stangeland will be in charge of building the roads. Sweco Norway has been chosen as the design consultant and will be responsible for the detailed design of bridges, structures, tunnels and roads. Visit https://implenia.com/en and https://www.tsmaskin.no/. 19/21 

 




Permalink


The JV Implenia Stangeland E39 Lyngdal ANS from Lysaker  secured the EUR 279.47 million (NOK4.9 bn) contract, excluding VAT, for engineering design, construction of and warranty responsibility for a new four-lane motorway E39 Lyngdal East - Lyngdal West. The stretch between the Herdalen junction and Royskar junction in Lyngdal municipality, includes approx. 2.5 km open air road,  the 3.4km Rossas and the 2.7 km Kalas tunnels, the two bridges Kvelland (over Lygna river) and Harikstad (170 m), two motorway junctions with connections to the existing road network. Contact Nye Veier, attn Ruben Ramsland, Kristiansand, email anskaffelser@nyeveier.no. For further on the tender, please click here. 28/21.   

 




Permalink