Turkey, Bolu - tr/16

Highway

Consultant: Geoconsult E-mail: office@gcs.co.at contact F L Jansky.  3 km-long x 150 sq m finished section twin-tube Bolu tunnel on North Anatolian motorway linking Ankara to Istanbul again under construction in weathered, faulted amphibolite by Astaldi following devastating earthquake in November, 1999 which caused 350 m collapse at each face. Articulated seismic lining design through active fault area, with 5 m-deep reinforced concrete invert and three-layer support comprising bolts, mesh, shotcrete, ribs and mass concrete. Second faces will be opened on Ankara side once 150 m-long cut-and-cover access completed. Visit www.astaldi.com and www.lombardi.ch 17/03.



Permalink

Turkey, Izmir - tr/15

Metro

  Wayss & Freytag using Herrenknecht 6.5 m shield completed first 550 m in very unstable soil consisting of sand, silt, clay and gravel using bentonite and foam. Another 550 m tunnel and two at 800 m to be driven. Best advance 25 m/day. June 1998.   Second section in two parts: 3.2 km line through stations at University and Bornova involves 836 m tunnel, 1,480 m cut-and-cover and 715 m at surface; alignment through stations at Bahceliever, Haimevieri, the Islamic Institute, Poligone and F Altay involves 2.19 km of double-track tunnel with internal diameter of 11.8 m to be driven through andesite using NATM techniques. March 1999.   Prequalification for phase two cancelled and sent back to the drawing board. Plans now involve constructing just the section from Bahceliever to F Altay which now will comprise a 1.35 km bored tunnel and 2.85 km cut and cover, subject to detailed design. New prequalification planned for May, 2000. October 1999.   General contractor Yapi Merkezi reports completion of 11.5 km first stage with ten stations from Ucyol to Halkapynar including the workshop and depot area in less than four years. $600 million contract was handled on a turnkey basis by Adtranz-Yapi Merkezi for Municipality of Greater City of Izmir. Five of the stations and 5.8 km of the line are underground. The stations at Konak, Cankaya and Basmane were constructed by cut-and-cover 10-13 m below sea level using 25-33 m-deep diaphragm walls. The Ummuhan Ana twin tunnels of driven length 2.75 km were in waterlogged ground comprising sands, silts and clays. They were constructed by the Herrenknecht 6.54 m EPB using a VMT guidance system and lined with 1.2 m-wide, 5.7 m elastomeric-gasketted precast concrete 7 + 1 rings. Average advance was 19.2 m/day on the fourth drive with a maximum of 28.8 m or 24 rings in 2 x 12 h shifts. Measured settlements were less than the 10 mm allowable. Foam and bentonite injection was available on the machine. More from www.yapi-merkezi.com November 1999.Consortium of STFA Muhendislik and Semaly on design and engineering for 5.2 km second stage from Ucyol to Fahrettin Altay for end-2000. Invitations to tender for construction are expected early-2001. Visit www.semaly.fr Sept 2000.



Permalink

Prior information notice without call for competition for the EUR754.50 million project for the Izmir Light Rail System,  section Ucyol - Buca (Izmir Metro project III).

The proposed project will require the procurement process for the following components:

1) Civil works for metro line extension by 13,5 km from Ucyol to Buca districts with construction of 11 underground stations, a depot area and workshop building and 6 km long  connection tunnel between main line and depot area, including E&M installations;

2) Consulting services for corporate development programme (CDP);

3) Consulting services for implementation support.

The procurement processes are planned to be initiated during 1st Qtr of 2020 for component n. 1,  by 3rd Qtr of 2020 for component n.3 and by 1st Qtr of 2021 for component n.2. Contact Izmir Metropolitan Municipality, attn Ms Arzu Yavuz, Izmir, tel +90 232 293 15 18, fax +90 232 293 90 38, email arzucr@hotmail.com.

For tender information please click here and here. Ref.n. 9567-GPN-51599. 04/20.



Permalink

Turkey, Istanbul - tr/14

Railway

  Marmaray crossing mooted at $650 million for 13.3 km including 1.8 km immersed tube joining Yenikapi with Sogutlucesme. Four year construction period. August 1998.   First US$117 million tranche of Japanese funding for the cross-Bosphorus rail link has been released to finance consultants to oversee design and tendering of the project and preliminary construction work. Japan's Overseas Economic Cooperation Fund (OECF) has already agreed to provide US$866 million for the US$1.6 billion project. The 13.3 km-long Bosphorus crossing will be combined with upgrading of the existing TCDD suburban lines to create a 76.3 km-long high-capacity railway across the Istanbul conurbation from Gebze to Halkali. The 1.8 km-long earthquake-proof immersed tube crossing will be assembled from 18 sections. It will be accessed by bored approaches from Yenikapi on the European side and Sogutlucesme on the Anatolian side. There will be intermediate stations at Sirkeci and Uskudar where the tunnel passes under the old city. Construction is expected to take around four years. December 1999.   Turkey's General Directorate of Railway, Port & Airport Construction has shortlisted three consortia for consultancy and engineering services. They are Pacific Consultancy of Japan with Parsons Brinckerhoff and Yuksel Project; Nippon Koei, Mott MacDonald, Louis Berger, Su Yapi Muhendislik, Nippon Civic and Sverdrup; and Prokon Muhendislik, Chiyoda, Akun, DE-Consult, Bung, TEC and Setec. The consultancy contract will be awarded with the aim of starting work early in 2001. Construction is expected to take around four years. The three consortia are to be vetted by Japan's Overseas Economic Cooperation Fund (OECF) before the final tenders are issued. Contact through www.mottmac.com April 2000.   Design contract for upgrade of 63 km of line with new 13.3 km-long marine link across Bosphorus from Gebze to Haliki and three underground stations awarded to PCI, Parsons Brinckerhoff and Yuksel. Tunnel will be bored from both sides, with 1.8 km-long immersed tube in central section at 58 m below sea level. Project value $1.2 billion, duration four years. Visit www.pbworld.com 44/01.   $2.5 billion engineering and consultancy agreement signed for the Marmaray project between the ministry of transport and the Avrasya consortium. The project involves the construction of a 13.3 km crossing over the Bosphorus and the upgrade of 63 km of suburban railway. $800 million to be spent for a 1.8 km earthquake-proof immersed tube, taking four years to build. 02/02.   Invitation to prequalify issued by the General Directorate of Railways, Harbours and Airports (DLH) for design and construction of the Istanbul Strait rail tube tunnel called 'Marmaray' and the Gebze-Halkali surface metro system after approval by the Japan Bank for International Cooperation (JBIC). The project includes a 2 km-long two-track immersed tunnel beneath the Bosphorus between the districts of Eminönü on the European side and íœsküdar on the Asian side of Istanbul, two-track approach tunnels on both sides of the immersed tunnel totalling 12 kilometres of combined bored tunnels, cut-and-cover tunnels and open cuts, and four deep underground stations. DLH is expected to collect bids for the tender in April 2003. Contact Mrs F. Simin Pehlivan, Ministry of Transportation, General Directorate of Railways, Harbours and Airports Construction (DLH), fax +90 312 2122874, E-mail simin@ubak.gov.tr. Visit www.ubak.gov.tr/tr/dlh/home/engmarmaray.htm 33/02.   The Japan Bank for International Cooperation (JBIC) has agreed to finance the Bosphorus strait tunnel crossing and 76.3 km-long Gebze-Haydarpasa and Sirkeci-Halkali suburb line paving the way to the tendering phase to be launched by DLH, the general directorate of railways, harbours and airports construction under the ministry of transportation. A 1.8 km immersed tunnel under the Bosphorus strait will be built to link the European and Asian sides and 12 km of connecting tunnels on both sides. The four prequalifiers are: Hazama / Penta Ocean / Yuksel Construction / Guris Construction; Kajima / Nishimatsu / Mitsubishi Heavy Industries / Enka / Dogus; Kumagai Gumi / Taisei / Gama / Nurol Construction; and Obayashi / Construction Center / Kiska / Metis. Estimated cost: €2.5 billion. Visit www.ubak.gov.tr/tr/dlh/index.html 05/03.  The four prequalifiers for the 1.8 km Marmaray tunnel across the Bosphorus strait and associated works, including 12 km of approach tunnels on both sides of the strait, are Kajima / Nishimatsu / Mitsubishi / Enka / Dogus; Hazama / Penta Ocean / Yuksel Guris; Taisei / Kumagai Gumi / Gauma / Nurol; and Obayashi / Construction Center / Kiska / Metis. Construction of the $2.5 billion Marmaray tunnel and the upgrading of existing rail links on both sides will begin in 2004 for completion in 2008. The tunnel will start in Yedikule, continue to Yenikapi and Sirkeci underground stations, cross the strait and be connected to another underground station at íœsküdar. After that point, the line will run above ground in Sogutlucesme. In total, the railway, including the tunnel, will be 13.5 km. Tenders for the project will open in October with work expected to begin in mid-2004. 27/03.The Kajima / Nishimatsu / Mitsubishi / Enka / Dogus consortium has withdrawn from the bid for the subsea metro tunnel project to connect the Asian and European sides of Istanbul, also known as Marmaray. The consortium said that the contract conditions were difficult to fulfill. The expiry date for submitting an offer is 3rd October, 2003. Three consortia remain in the race. 38/03.The transport ministry received two preliminary bids from Turkish-Japanese consortiums in a tender to build a rail tunnel under the Bosphorus straits between the European and Asian sides of Istanbul. The first consortium is formed by Taisei, Kumagai Gumi and Turkey's Gama and Nurol. The second group includes Obayashi and Turkey's Yapi Merkezi, Metis and Kiska. The $2.5 billion Marmaray project covers a distance of 13.1 km. The bids will be evaluated within two months. The first tunnel phase of the project, to be financed by the Japan Bank for International Cooperation (JBIC), is expected to cost around $800 million. The second phase, linking the tunnel to an existing rail line between the stations of Halkali and Gebze, is forecast to cost $700 million, while the trains and signalling in the third phase will cost around $1 billion. Officials plan to lay the foundation stone in the first quarter of 2004. 02/04.A USD2 billion contract for the third crossing of the Bosphorus Strait was signed on 6th May by a consortium between Taisei, Kumagai Gumi, Gama and Nurol. Construction was officially launched on 9th May. The project, also known as Marmaray, includes a 13.3 km tunnel crossing and the upgrade of 63 km of suburban line to create a 76.3 km high capacity line between Gebze and Halkali. The Bosphorus Strait will be crossed by a 1.8 km immersed tube tunnel, composed of 18 elements sunk at a depth of approximately 60 m. This tube will be accessed by bored tunnels from Yenikapi on the European side and Sogutlucesme on the Asian side of Istanbul. Stations will be built at Sirkeci and Uskudar. The project is due to finish in 2008. Visit www.taisei.co.jp/english 21/04.CPG Consultants of Singapore has been engaged by Taisei and its JV partners Kumagai, Gama and Nurol to lead the design of the 1,387 m immersed tunnel crossing under the Bosphorus Strait, which is part of the 13,558 m Marmara railway tunnel project to link the Asian and European continents. The USD1 billion project also involves the design and construction of three TBM-driven twin-tube sections (2 x 4,620 m, 2 x 3,343 m and 2 x 2,170 m from east to west), cut-and-cover portions and three underground stations, one on the Asian side (the Usukudar cut-and-cover station) and two on the European side (Yenikapi and Sirkuci, to be built respectively in cut-and-cover and NATM). Deepest station at about 50 m underground. Also Kazlicesme station at grade on the European side. The earthquake-proof immersed tunnel will be one of the deepest of its kind in the world, at 55 m below sea level at its lowest point. It is scheduled to be completed in 2009. The Bosphorus Strait joins the Marmara Sea with the Black Sea and separates Europe and Asia. Visit www.cpgcorp.com.sg and www.marmaray.com 05/05.



Permalink

Open invitation to tender for design, execution and completion of 77 km-long Gebze-Halkali commuter rail upgrading as Contract CR3 of Marmaray project including equipping new Bosphorus tunnel. Contract starts April, 2011 for phased completion end-2013 to end-2014. Pre-bid meeting 15.09.2010. More from Ministry of Transportation, DLH in Ankara, tel +90 312203-1638, fax -1470, e-mail hamzasen@ubak.gov.tr. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=220958-2010. 30/10.



Permalink

Open invitation to tender, revised deadline 28.02.2011, for design, execution and completion of 77 km-long Gebze-Halkali commuter rail upgrading as Contract CR3 of Marmaray project including equipping new Bosphorus tunnel. Contract starts April, 2011 for phased completion end-2013 to end-2014. Pre-bid meeting 15.09.2010. More from Ministry of Transportation, DLH in Ankara, tel +90 312203-1638, fax -1470, e-mail hamzasen@ubak.gov.tr. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=368672-2010. 50/10.



Permalink

Open invitation to tender, revised deadline 28.02.2011, for design, execution and completion of 77 km-long Gebze-Halkali commuter rail upgrading as Contract CR3 of Marmaray project including equipping new Bosphorus tunnel. Contract starts April, 2011 for phased completion end-2013 to end-2014. More from Ministry of Transportation, DLH in Ankara, tel +90 312203-1638, fax -1470, e-mail hamzasen@ubak.gov.tr. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=368672-2010. 01/11.



Permalink

Flakt Woods will supply EUR7 million ventilation fans for the Marmaray rail tunnel in Turkey. For more click here an visit www.flaktwoods.com/it. 20/11.



Permalink

The JV of Spanish OHL (70%) and Invensys Rail (30%), a division of global technology group Invensys plc, has been awarded the EUR932.8 million CR3 contract for design, execution and completion of 77 km-long Gebze-Halkali commuter rail upgrading of Marmaray project including equipping the new Bosphorus tunnel. The contract also includes maintenance for two years, with an option for a further five years. Work starts in early 2012. Visit www.ohl.es and www.invensysrail.com. 45/11.



Permalink

OHL/Dimetronic JV has been awarded the EUR1.042 billion contract, excluding VAT, for upgrading civil, electrical and mechanical systems of the Marmaray project comprising dismantling of existing 63 km two-line railway and 37 stations and constructing new three-line railway, stations, depot and stabling yards and renewal of all electromechanical systems between Gebze and Halkali. More from OHL in Ankara, tel +90 31243653-50, fax –52, e-mail mnt@ohl.com.tr or from alvaro.lopez@dimetronic.com. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=370617-2011. 48/11.



Permalink

Turkey, Istanbul - tr/13

Metro

Bids under consideration by Istanbul Metropolitan Municipality for 2.5 km extension from Taksim to Yenikapi which will include bridge over the Golden Horn. Nov 1998.Tender notice, deadline 25th December, 2007 for supply, installation and commissioning of electro-mechanical systems for the Kadiköy-Kartal metro (power supply and traction force, signalling, control and communication, ventilation, lighting, escalators and lifts, plumbing, drainage, installation of a traffic control centre, etc.). The Kadiköy-Kartal metro is a 21.7 km double-track underground line with 16 stations. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=247239-2007, OJ S 204, or contact Istanbul metropolitan Municipality, Istanbul, fax +90 2124494180. E-mail raylisistem@ibb.gov.tr 44/07.A consortium of Italian construction company Astaldi and its Turkish partners Makyol and Gülermak is in the lead to get a EUR751.2 million contract from the Istanbul Metropolitan Municipality's transportation department to build a 21.7 km subway line between the Kadiköy and Kartal districts of Istanbul's Asian side. Astaldi, which is leading the group in the bidding for the contract, could get 42%, or EUR315.4 million, of the total value of the contract which also includes the E&M and signalling technology. Makyol has 41.33% and Gülermak has 16.77%. The Italian-Turkish consortium submitted the low bid against two rival consortia, namely Alarko-OHL (EUR753 million) and Dogu?-Yapi Merkezi-Yüksel-Siemens (EUR779.9 million). A previous tender for the project had been held two-and-a-half years ago but was cancelled, as the construction project was not feasible at the time. The line will be constructed underground but will go above ground wherever possible. The line will have 16 stops. Work is to begin in the second half of the year and last three years, once the contract signing process is concluded. The project will employ 2,000 people. Visit www.astaldi.com, www.makyol.com.tr and www.gulermak.com.tr 04/08.Astaldi, as general contractor and leader of a joint venture with Makyol and Gülermak, and the municipality of Istanbul signed a EUR751 million contract for the construction of the new Kadiköy-Kartal line in Istanbul. The contract has been signed after the joint venture was named preferred bidder in January. Astaldi's share amounts to EUR315 million. The contract is for the construction of a new 20 km-long double-track underground line, with 16 underground stations, and includes also the supply of electromechanical equipment and the signalling system. The works are planned to start in the second half of 2008 and will be completed in three years. Visit www.astaldi.com, www.makyol.com.tr and www.gulermak.com.tr 11/08.



Permalink

Open invitation to tender, deadline 03.05.2011, for construction of second phase of Uskudar-Umraniye-Cekmekoy metro line between Ihlamurkuyu-Cekmekoy and the storage area EIB. Contract period 730 days commencing 15 days from signing and handover. Contact Istanbul Metropolitan Municipality, Department of Transportation, Directorate of Rail Systems, tel 0212 449 41-75/80/84, e-mail raylisistem@ibb.gov.tr for tender documents. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=065870-2011. 09/11.



Permalink

Open invitation to tender, deadline 09.08.2011, for construction of Uskudar-Umraniye-Cekmekoy metro line (20 km-long with 17 stations). Contract period 1,140 days. Contact Istanbul Metropolitan Municipality, Department of Transportation, Directorate of Rail Systems, tel +90 (0)212 449 41-75/80/84, e-mail raylisistem@ibb.gov.tr for tender documents. Tender n. 2011/76140. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=183588-2011. 24/11.



Permalink

Dogus Construction and Trade Inc of Kavacik-Beykoz/Istanbul secured the EUR563,900,000 contract, VAT not included, for construction and E&M works for 20 km-long Uskudar-Umraniye-Cekmekoy metro line with 17 stations. Contact Istanbul Metropolitan Municipality, Department of Transportation, Directorate of Rail Systems, tel +90 (0)212 449 41-75/80/84, e-mail raylisistem@ibb.gov.tr. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=112589-2012 and www.dogusinsaat.com.tr. 15/12.



Permalink

Open invitation to tender, deadline 18.09.2013, for construction of Mecidiyekoy-Mahmutbey metro line, depot and depot connection lines. Contract period 1,095 days. Contact Istanbul Metropolitan Municipality, Department of Transportation, Directorate of Rail Systems, tel +90 212 449 4175-84, fax +90 212 449 4175-80, e-mail avruparaylisistem@ibb.gov.tr for tender documents. View tender documents at https://ekap.kik.gov.tr/EKAP/, tender n. 2013/87848. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=261894-2013. 32/13.



Permalink

Pre-qualification tender, deadline 30.06.2014, for the final design works of 6.65 km-long Metrokent–Kayasehir underground line and 12.64 km-long Basaksehir-Kayasehir-Olympic Park Tramcar line. Duration of work 15 months. Companies interested can obtain tender documents from Istanbul Metropolitan Municipality (IBB), Projects Department, Infrastructure Projects Directorate, Merter-Ä°stanbul. Visit http://www.ibb.gov.tr/tr-TR/Pages/IhaleIlani.aspx?IhaleID=12842 and http://www.ambankara.esteri.it/NR/rdonlyres/91A7B652-3458-48CE-A951-D9D2C1CD394D/33218/CronacheEconomiche201412.pdf. Ref. n. 2014/48722. 24/14.



Permalink

Turkey, Ankara - tr/12

Metro

  EGO calling for tenders for 18.3 km metro Line No 2 between Kizilay and Cayyolu. September 1998.Line 2 now to be 18.2 km long and to have 16 stations. The State planning office has been approached by Ankara Metropolitan Municipality for authority to start work. Tenders to be called for complete works. Proposed further extensions to Ankara metro are 7.9 km from Ulus to Keeioren and 4.8 km from TBMM to Dikmen. Sept 1999.



Permalink

Turkey, Adana Province - tr/11

Kavsak River Hydropower

Requirement for 9.2 km x 10 m outside diameter tunnel lined at 8.5 m diameter through shales, limestones and sandstones with initial support by rockbolts and shotcrete. Consultant Temel’su. April 1999.Negotiated invitation to tender, deadline 19th October, 2008 for construction of civil and hydromechanical works for the Kavsakbendi RCC dam, including a 2,263 m 9 m ID tunnel and two divertion tunnels, 531 m and 330 m long and 7.9 m ID. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=246508-2008, OJ S 186, or contact Enerjisa Enerji íœretim, Istanbul, fax +90 2122810574 or 3124738546. E-mail msenturk@enerjisa.com.tr or lkasap@enerjisa.com.tr 40/08.



Permalink

Turkmenistan

Turkmenistan, Ashgabat - tm/12

Wastewater

3.7 m-diameter Herrenknecht EPB, machine No. M-715 with VMT semi-automatic guidance system, screw conveyor, and articulated shield supplied for 2 x 3.5 km-long project. M-715 is already in Ashgabat since early July 2002. On-site assembly in August-September 2002 for tunnelling start in October 2002. Lining rings consisting of five segments plus key. Geology is mainly stiff to hard loam (clay, silt, sand) with ballast in the south part of the city. Groundwater table varies from 1 m below the surface (northern part) to 5 m below the surface. Maximum coverage of 13 m, maximum pressure of 1 bar. First bore expected to break through in about one year. Planning and design of second drive not ready yet. Construction company is Construction Association Interbudmontazh (CAI) of Ukraine. Client is the municipality of Ashgabat. Visit www.herrenknecht.com and www.vmt-gmbh.de 32/02.



Permalink

Turkmenistan, Ashgabat - tm/11

Combined Utility

Two 6.25 m-diameter Herrenknecht EPB TBMs, machines No. S-218 and S-219, with VMT semi-automatic guidance systems, screw conveyor, and articulated shield being supplied for 8 km drive with radius of 300 m and 5 km drive. Segment design by Herrenknecht, Ceresola and PSP. Universal rings, OD 6,000 and ID 5,400 with six segments plus key. Segments to be installed using bolts, with central socket for mortar injection. Geology consisting of clay and silt. Ashgabat's geology is made of loam, sand and sections of crushed gravel. Soils are mostly cohesive with groundwater table ranging from below to above the tunnel alignment. Some sand lenses have to be expected imbedded within a stiff silt-matrix. S-218 being shipped from Antwerpen to Turkmenbaschi. Arrival in Ashgabat end of August 2002. On-site assembly in September 2002 for tunnelling start in October-November 2002. S-219 is still in Schwanau, Germany and will be transported in about two weeks. Contractor is Ukrainian company Construction Association Interbudmontazh (CAI). Client is the municipality of Ashgabat. Visit www.herrenknecht.com and www.vmt-gmbh.de 32/02.



Permalink

Uganda

Uganda, Hoima District - ug/11

Hydropower

Closing Date: 30.03.2015 (Tender Closed)

Open invitation to tender, deadline 30.03.2015 for notification of interest for tunnelling works. The project is for hard rock drill/blast, minimum cross section 880 m-long hydro tunnel at the Nkusi water falls. Principal is Norwegian company. Possible extension to Civil works. Free issue operating equipment. Experience with African operations required. Need lean, but complete crews for 24/7 operations. Contacts are rune.freyer @freyerconsulting.com and asakatama @yahoo.com.



Permalink

Ukraine

Ukraine, Kharkiv - ua/16

Metro

Prior information notice without call for competition for a project to extend a metro (subway) line in the city of Kharkiv. The proposed project, which has a total estimated cost of approximately EUR 382 million will be implemented by Kharkiv Metro Company and will require the procurement of the following contracts: extension of the existing metro line by 3.5km and construction of 2 metro stations; construction of new metro wagon depot and connecting rail; acquisition of new rolling stock; FIDIC Engineer and procurement and implementation support consultant. Interested suppliers, contractors and consultants have to contact Kharkiv Metro Company, attn Igor Pashnev, Kharkiv, tel +380 57 731 62 64, fax +380 57 731 50 73, email kharkivmetro@gmail.com. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=392558-2017. Ref. n. 8838-GPN-46411. 41/17.



Permalink

Invitation for expression of interest, deadline 16.03.2018, for a FIDIC Engineer,  procurement and implementation support consultant for the extension of the existing Green Metro Line in Kharkiv. the project is to extend the metro (subway) line in the city of Kharkiv. Contact Kharkiv Metro Company, attn Igor Pashnev, Kharkiv, tel +380 57 731 59 83, fax +380

57 731 21 41, email kharkiv.metro2017@gmail.com. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=069090-2018.

Ref. n. 8979-EOI-46411(NM). 09/18.



Permalink

Prior information notice without call for competition for the project to extend the Green metro line in the city of Kharkiv. This is an update of the original notice published on 9.2.2018. The Government of Ukraine has signed loan financing agreements with the European Bank for Reconstruction and Development (EBRD) and European Investment Bank (EIB) for the project.

The EUR382 million project, implemented by Kharkiv Metro Company, will require the procurement of the following 3 contracts:-

  • Extension of the existing metro line by 3.47 km and construction of 2 metro stations;
  • Construction of a new metro wagon depot and connecting rail;
  • Acquisition of new rolling stock.

 Tendering for the above contracts is expected to begin in the Q2 of 2019.The selection of the FIDIC Engineer and procurement and implementation support consultant is ongoing  (click ua/16 for tunnelbuilder archive).

Interested suppliers and contractors have to contact Kharkiv Metro Company, attn Igor Pashnev, Kharkiv, tel +380 57 731 59 83, fax +380 57

731 21 41, email kharkiv.metro2017@gmail.com  with cc to kharkivmetro@gmail.com. Visit

http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=075799-2019

and https://www.ebrd.com/work-with-us/procurement/p-pn-190211b.html. Ref.

n. 9339-GPN-46411. 12/19.




Permalink

Invitation for expression of interest, deadline 16.03.2018, for a firm or group of firms (the "Consultant") (the "Assignment") supporting the client in all aspects of the Kharkiv Metro Line project’s implementation, including preparation of tender documents, assisting with tendering, tender evaluation, contract finalisation and administration and works supervision. Contact Kharkiv Metro Company, attn Igor Pashnev, Kharkiv, tel +380 57 731 59 83, fax +380 57 731 21 41, email kharkiv.metro2017@gmail.com. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=077723-2018.

Ref. n. 46411. 09/18.




Permalink

Open invitation to tender, deadline  20/04/2020, for the extension of the existing metro line and construction of two metro stations. The contract will include 3.47 km twin-tube tunnels,  2 underground stations (platform lengths approx. 104 m), track works, supply and installation of E&M equipment and integration of this equipment into existing metro systems.

Contact Kharkiv Metro Company, attn  Mr Igor Pashnev,  Kharkiv, tel +380 577303406, fax +380 577315983, email kharkiv.metro2017@gmail.com  with CC: to kharkivmetro@gmail.com. For further tender information please click here Ref.n. 9593-IFP-46411. 11/20.