Tunnelbuilder Promoting the world's tunnelling industry to a huge qualified audience

View the Spanish Tunnelbuilder website View the Italian Tunnelbuilder website

Archive Search

Spain

Spain, Catalonia - es/57

Highway

Second 5.23 km-long x 95 sq m parallel tube in design for Central Pyrenees N230 highway from Toulouse to Lerida. 13.75 m-wide x 8.2 m-high, for three-lane traffic, with pedestrian connections to existing tunnel every 400 m. Drill/blast in Paleozoic rocks, granite, slate, quartzite and sandstone, with rockbolts, mesh and shotcrete support. Value $130 million. Tenders expected 2001 for completion 2005. Visit www.idom.es 04/01. Open invitation to tender, deadline 14th September, 2001, for construction of 5 km-long road tunnel for Ministerio de Fomento, Madrid. Visit www.boe.es 36/01. Invitations to tender expected for three-year construction of $120 million, 9.5 km-long motorway section including four twin-tube tunnels of lengths 163 m, 394 m, 258 m, and 1.2 km. Visit www.boe.es 38/01. Tenders invited for consulting and assistance for the dualling of the 5.2 km Viella tunnel in Lérida. Value of €4 million. Deadline 1st February, 2002. Visit http://ted.eur-op.eu.int, document S 246-169590. 01/02. Award to a jv of OHL, Comsa, and Copcisa of the dualling of the Vielha tunnel in Lleida for €128 million. Bored length totals 5,059 metres, 106.25 sq m cross section. Also a 165 cut-and-cover portion, 5 m-high x 13.41 m-wide. Drill/blast method. Support with shotcrete, mesh, rockbolts and steel arches. The project also includes 120 m-long cross passages to the existing tube every 400 metres, a service tunnel, refuges, safety niches, restructuring the accesses, installing equipment within the tunnel, ventilation facilities at each portal, as well as a management and operation building at the north portal. Time frame of 39 months with start in September, 2002 and completion in March, 2005. Doubling the tunnel is urgent since safety in the existing tube, also known as Alfonso XIII, scored 'very bad' in a survey published in April, 2000 by the international tourism alliance and the international motoring federation. Visit www.ohl.es 05/02.Sener have been awarded a €3.6 million contract for work supervision of the 5 km Vielha tunnel. Visit www.sener.es. 31/02.Open call for tenders, deadline 14th September, 2007 for draft design for conversion to motorway of the Vielha tunnel-French border section of road N-230 in Aran Valley. The west alternative includes seven tunnels totalling nine kilometres, the longest of which would be five kilometres in length. More details in E-News Weekly 51/2003 & 5/2002. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=142852-2007, OJ S 116, or contact Ministry of Development, Madrid, fax +34 915978536 or 915978470. E-mail randujar@fomento.es or cpublic@fomento.es 29/07.Indra pocketed a EUR4.6 million contract to supply and install safety and control systems in the Juan Carlos I tunnel in Viella in Lerida province. The new tunnel, located on the Vilaller-Viella section of trunk road N-230, will be equipped with the most modern safety and control systems, including signage, video monitoring, video detection, telephone and videoconference, IP communication network, fire detection, radio communication, SOS stations and ventilation and lighting control. Indra will also supply the systems for the control centre, both for the new and old tunnels. With three lanes, one of which will be reversible, the new tunnel will solve safety problems in the existing tunnel, which is bidirectional and carries two very narrow lanes. The two parallel tunnels will be cross-connected by 12 escape galleries. Click here and here. Visit www.indra.es 36/07.Open invitation to tender, deadline 03.03.2009, for 16 month contract to equip new 5,230 m-long Vielha Juan Carlos I tunnel on N-230 highway in Lleida province, value EUR16,352,192. Specs and docs from Ministerio de Fomento, Madrid, e-mail cpublic@fomento.es, fax +34 915978470. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=000803-2009. 02/09.



Permalink

Spain, Madrid-Valladolid - es/56

High Speed Railway

  Open invitation to tender, deadline 10th September, 2001, for design of Fuencarral-Canto Blanco section of Madrid-Miraflores route including 1.5 km cut and cover tunnel. First of five similar contracts. Visit www.gif.es 34/01. Open invitation to tender, deadline 12th September, 2001, for geotechnical evaluation of Madrid-Valladolid line tunnels, including one 9 km-long, three totalling 1 km, and a 1.5 km-long cut and cover. Contact www.gif.es 37/01. Open invitation to tender, deadline 24th October, 2001, for consultancy services for Madrid-Avila high speed railway, including tunnels. Contact Ministry of Construction, fax +34 91 5631574 or visit www.gif.es 42/01. Design and work supervision contract of the Fuencarral-Canto Blanco section including a 1.5 km cut-and-cover tunnel to a jv of Paymacotas, Esteyco and Icyf for €2.9 million. Visit www.gif.es 47/01. Consulting and assistance for geotechnical studies on the Colmenar Viejo-Soto del Real section awarded to a jv of Ingeotec and Mayasa for €501,000. Includes the San Pedro tunnel, a 9 km twin tube. Visit www.gif.es 48/01. Open call for bids, deadline 16th January, 2003 for construction of the 7 km Canto Blanco-Tres Cantos section, including 3 cut-and-cover tunnels totalling 1 km. Tender value €45.4 million. Visit http://ted.eur-op.eu.int/udl?request=Seek-Deliver&language=en&docid=190325-2002, OJ S 239, or contact GIF, Madrid, fax +34 913198535. 51/02. Invitation to tender imminent further to government approval of the construction of the Colmenar Viejo-Soto del Real section, north of Madrid. This requires the San Pedro twin tunnel, approximately 9,5 km in length. Tender value: €310.3 million, of which €150.7 million for the east tunnel and €159.6 million for the west tunnel. Time frame for construction: 42 months. 18/03.Open call for bids, deadline 20th June, 2003 for construction of the west tunnel, 9.5 km in length, on section Colmenar Viejo-Soto del Real. The project includes civil works and equipment for the west tunnel and civil works for the south portal common to the two tracks. Tender value: €159.6 million. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=077509-2003, OJ S 87, or contact GIF, Madrid, fax +34 913198535. 20/03.Open call for bids, deadline 20th June, 2003 for construction of the east tunnel, 9.5 km in length, on section Colmenar Viejo-Soto del Real. The project includes civil works and equipment for the east tunnel, the connecting galleries to the west tunnel and civil works for the north portal common to the two tracks. Tender value: €150.8 million. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=078412-2003, OJ S 88, or contact GIF, Madrid, fax +34 913198535. 20/03.OHL has secured a €137.6 million contract to build the west tube of the San Pedro tunnels between Colmenar Viejo and Soto del Real, north of Madrid. A TBM will be used to drive this 9.5 km 8.75 m-diameter tunnel. The contract also includes tunnel equipment (safety, lighting, communication and control) and building of the south portal. Completion at fall 2006. Visit www.ohl.es 39/03.Construction of the east tube, of the same length, has been commissioned to a JV of midsize contractors including Construcciones Sí¡nchez Domí­nguez, Construcciones Paraí±o SA (Copasa), Aldesa Construcciones and Tableros y Puentes SA (Tapusa) for €130 million. The contract also includes tunnel equipment (safety, lighting, communication and control), building of the cross passages to the west tube and the north portal. 39/03.Open call for bids, deadline 8th January, 2004 for technical and environmental management during construction of several sections of the Madrid-Valladolid high speed line, among which Fuencarral-Canto Blanco, Canto Blanco-Tres Cantos and Colmenar Viejo-Soto del Real. Fuencarral-Canto Blanco includes a 1.5 km cut-and-cover tunnel, Canto Blanco-Tres Cantos requires 1 km of cut-and-cover tunnels and Colmenar Viejo-Soto del Real includes the San Pedro tunnel (2 x 9.5 km). Tender value: €9 million. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=208815-2003, OJ S 234, or contact GIF, Madrid, fax +34 913198535. 50/03.Open call for bids, deadline 12th March, 2004 for design and assistance to work control for the urban integration of the high speed line in Valladolid. The line will run underground, requiring a south-north tunnel starting near a viaduct at Daniel del Olmo Street to link up with the Renedo Road, north of the city, and a new underground station in Campo Grande. Tender budget: EUR2.3 million. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=024945-2004, OJ S 28, or contact GIF, Madrid, fax +34 913198535. 09/04.Ineco won a EUR5.4 million contract for technical and environmental management during construction of several sections of the Madrid-Valladolid high speed line, among which the Fuencarral-Canto Blanco, Canto Blanco-Tres Cantos and Colmenar Viejo-Soto del Real sections. Fuencarral-Canto Blanco includes a 1.5 km cut-and-cover tunnel, Canto Blanco-Tres Cantos requires 1 km of cut-and-cover tunnels and Colmenar Viejo-Soto del Real includes the 2 x 9.5 km San Pedro tunnel. Visit www.ineco.es 10/04.Ineco has secured a EUR1.6 million contract for the design and assistance to work control for the urban integration of the high speed line in Valladolid. The line will run underground, requiring a south-north tunnel starting near a viaduct at Daniel del Olmo Street to link up with the Renedo Road, north of the city, and a new underground station in Campo Grande. Visit www.ineco.es 31-32/04.Open call for tenders, deadline 28th August, 2007 for work to equip the 9.4 km-long Colmejar Viejo-Soto del Real section, including all outfit (ventilation, fire extinguishing, civil protection and safety, and electrical equipment) in the 2 x 8,759 m-long San Pedro tunnels. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=161959-2007, OJ S 132, or contact ADIF, Madrid, fax +34 917005751. 29/07.Open call for tenders, deadline 3rd September, 2007 for construction of the 5.44 km section Duero River-Pinar de Antequera tunnel, including a 2 x 1,057 m-long cut-and-cover tunnel, one for IUC gauge trains and one for Spanish gauge trains. Read E-News Weekly 12/2007, 16/2006 & 5/2006. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=182519-2007, OJ S 147, or contact ADIF, Madrid, fax +34 917005751. 32/07.Open call for tenders, deadline 25th October, 2007 for construction of the east bypass railway for freight trains in Valladolid on the Madrid-Valladolid high speed line. This is a 17.5 km Spanish gauge line, starting at chainage 242.9 on the Madrid-Hendaya line and finishing at chainage 258.4 on the same line. It is mainly a surface line, except two kilometres between chainages 3.9 and 5.9 in Pinar del Jalí³n, San Cristí³bal industrial park and Cerro de San Cristí³bal. The cut-and-cover method will be used. Read E-News Weekly 5/2006. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=221177-2007, OJ S 181, or contact Ministry of Development, Madrid, fax +34 915979342 or 915978470. E-mail vrpascual@fomento.es or cpublic@fomento.es 40/07.Open call for tenders, deadline 5th November, 2007 for site supervision and work inspection during construction of the east bypass railway for freight trains in Valladolid on the Madrid-Valladolid high speed line. The 17.5 km line includes a 2 km cut-and-cover tunnel. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=228141-2007, OJ S 187, or contact Ministry of Development, Madrid, fax +34 915979342 or 915978470. E-mail vrpascual@fomento.es or cpublic@fomento.es 41/07.ADIF awarded the construction and equipment of the 5.44 km section between the Duero River and the Pinar de Antequera tunnel, including a 2 x 1,057 m-long cut-and-cover tunnel, one for IUC gauge trains and one for Spanish gauge trains, to Corsí¡n-Corviam, Begar and Zarzuela. The contract is worth EUR76.2 million. Visit www.corsan-corviam.es, www.begar.es and www.zarzuelasa.com 41/07.OHL (50%), Aldesa Construcciones (14%), Construcciones Sando (14%), Copasa (14%) and Tapusa (8%) landed a EUR60 million contract to equip the 9.4 km-long Colmejar Viejo-Soto del Real section, including all outfit (ventilation, fire extinguishing, civil protection and safety, and electrical equipment) in the 2 x 8,759 m-long San Pedro tunnels. Visit www.ohl.es, www.aldesaconstrucciones.es, www.sando.net, www.copasa.es and www.tapusa.es 45/07.Idom Internacional bagged a EUR2.4 million contract for site supervision and work inspection during construction of the east bypass railway for freight trains in Valladolid on the Madrid-Valladolid high speed line. The 17.5 km line includes a 2 km cut-and-cover tunnel. Visit www.idom.es 52/07-01/08.The Ministry of development has awarded the construction of the east bypass railway for freight trains in Valladolid to FCC and its affiliate Convensa. The contract is worth EUR108.2 million. The project forms part of the Madrid-Segovia-Valladolid high speed line, which opened on 22nd December, 2007. Construction will take 27 months until early 2011. Basically, the bypass is 17.5 km long and its path runs in majority parallel to Valladolid's outer ring road. It travels at grade for most of the length, except two kilometres in Pinar del Jalon, San Cristobal industrial park and Cerro de San Cristobal, running mainly in a cut-and-cover tunnel. Visit www.fcc.es 03/08.Open call for tenders, deadline 23rd April, 2008 for design of the 4,680 m cross city high speed tunnel and the new Campo Grande underground station in Valladolid. The Madrid-Valladolid high speed line entered in service in December 2007 but the bullet trains enter Valladolid at grade using the conventional tracks. Click here. Read E-News Weekly 5/2006, 49/2005, 38/2003 & 49/2002. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=79012-2008, OJ S 58, or contact ADIF, Madrid, fax +34 917005751. 14/08.Intecsa-Inarsa scooped a EUR4.2 million contract to design the 4,680 m cross-city high speed tunnel and the new Campo Grande underground station in Valladolid. Visit www.intecsa-inarsa.es 24/08.Intecsa-Inarsa has been awarded a EUR4.2 million design contract for the 4,680 m cross city high speed tunnel and the new Campo Grande underground station in Valladolid. The Madrid-Valladolid high speed line entered in service in December 2007 but trains still use the conventional surface tracks within the city. Visit www.intecsa-inarsa.es 27/08.



Permalink

Open invitation to tender, deadline 25.04.2012, for the maintenance and repair of the civil protection and safety equipment in tunnels of the Madrid-Valladolid high-speed line.

Time limit for accessing documents 24.04.2012. Contract value EUR3,214,992 excluding VAT, duration one year. Contact Luis Mariano Ortiz at Adif in Madrid, tel +34 913007487, fax +34 913006104, e-mail lmortiz@adif.es. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=079331-2012. 15/12.



Permalink

The JV Indra-Alstom of Alcobendas secured the EUR3,785,882 contract, excluding VAT, for the maintenance and repair of the civil protection and safety equipment in tunnels of the Madrid-Valladolid high-speed line. Contact Mercedes Lopez de la Fuente at Adif in Madrid, tel +34 913007260, fax +34 913006623, e-mail mlfuente@adif.es. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=378316-2013. 46/13.



Permalink


The JV Tuneles Guadarrama from Alcobendas (Madrid) secured the EUR 4.23 million contract, excluding VAT, for the maintenance and repair of the civil protection and safety equipment in tunnels of  the Madrid-Valladolid-Venta de Banos-Burgos-Leon High Speed Railway. For further information contact Mercedes Lopez de la Fuente at Adif in Madrid, tel +34 913007260, fax +34 913006623, e-mail mlfuente@adif.es. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=396732-20135. Ref.n. 4.15/20506.0022. 47/15.




Permalink

Open invitation to tender, deadline 01.03.2019, for the maintenance and repair of the civil protection and safety equipment in tunnels of the Madrid-Valladolid-Leon and Venta de Banos-Burgos high-speed line. Contract value EUR12.3 million, excluding VAT, duration 48 months from award.

Contact Angel Una Ruciero at Adif in Madrid, tel +34 913007588, fax +34 913006623, email AURUCIERO@ADIF.ES. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=034001-2019.

Ref.n. 4.18/21506.0032. 04/19.




Permalink


Asociacion de Accion Ferroviaria (Cetren) from Madrid have secured the contracts for 9 lots for CE validation  of interoperability of the infrastructure and/or energy subsystems on the new high speed railway sections: 

  • Lot1: Olmedo-Zamora-Pedralba, value of the contract EUR355,000, excluding VAT; 
  • Lot 2: Valladolid-Leon/Venta de Banos-Burgos, value of the contract EUR495,000, excluding VAT; 
  • Lot 3: Antequera-Granada, value of the contract EUR188,000, excluding VAT; 
  • Lot 4: La Robla-Pola de Lena, value of the contract EUR249,000, excluding VAT;
  • Lot 5: Castellbisbal-Tarragona (Vilaseca)-Vandellos-Castellon-Valencia, value of the contract EUR664,000, excluding VAT;
  • Lot 6: Monforte del Cid-Murcia-Alicante (Cambiador Encina)-Jativa-Valencia, value of the contract EUR305,000, excluding VAT;
  • Lot 7: Plasencia-Badajoz, , value of the contract EUR170,000, excluding VAT; 
  • Lot 8: Vigo-Santiago-la Coruna-Orense-Santiago, value of the contract EUR567, 000, excluding VAT; 
  • Lot 9: Tunnel AV Atocha-Chamartin, , value of the contract EUR43,459, excluding VAT. 

Contact  Adif Alta Velocidad, attn Francisco Macias Bonilla, Madrid, tel +34 661347788,  email fmacias@adif.es. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=120827-2022. Ref.n. 3600000039. 11/22.




Permalink

Spain, Asturias-Castilla & Léon - es/55

High Speed Railway

  Open invitation to tender, deadline 3rd August, 2001, for engineering design of railway line including tunnels for Asturias Government, Ministry of Infrastructure, fax +34 985 105884. Visit www.boe.es 29/01. Open tendering, deadline 16th January, 2002, for consultancy and design of the Variante de Pajares option between La Robla and Pola de Lena on the Valladolid-Gijí³n rail link. Budget of €6.1 million. A 980 m-deep core drill was due to be completed in December, 2001 by a jv of Geoconsult and Compaí±i­a General de Sondeos under Mounts Valgrande and El Huerna for a long twin tunnel, possibly up to 2 x 25 km, required to cross the Cantabrian mountain chain. Visit http://ted.eur-op.eu.int, documents S 230-158539 or fax +34 917004755, Madrid, Gestor de Infraestructuras Ferroviarias. Also visit www.gif.es 02/02. Award to a jv of Ineco and Geoconsult of the design of the Variante de Pajares with a possible 25 km twin tunnel. Contract value of €5.2 million. Visit www.gif.es 13/02. Call for tenders imminent in OJEC for project and construction of the Pajares tunnels for €1.08 billion with time frame of five years. The Spanish OJ has already invited tenders twelve days only after approval by the government. The Pajares bypass consists of two twin tunnels of 24.6 km each to connect Asturias with the centre of Spain through Leí³n. Construction of the tunnel will be divided into four contracts. Number one from Pola de Gordí³n to Folledo will cost €403 million; number 2 (Folledo-Viadangos) will cost €306 million; number 3 (Viadangos-Telledo-Tunnel east) €192.5 million and number 4 (Viadangos-Telledo-Tunnel west) €183.5 million. Visit www.boe.es and www.gif.es/lineav1.html 11/03. Open call for bids, deadline 30th April, 2003 for the design, construction and execution of requirements for the Pajares twin tunnels (2 x 24.6 km) on the high speed link between Léon and Asturias. Maximum budget for design: €500,000. Reference budget for construction: €1,085 million. Lot 1 is section Pola de Gordí³n-Folledo consisting of an access tunnel, joint cavern, two single-track tunnels, cross connections between both tubes and associated installations. This section is 11 km-long. Maximum budget for design: €110,000. Reference budget for construction: €403 million. Lot 2 is section Folledo-Viadangos, which includes two twin tunnels excavated by conventional means, start shafts, a joint cavern, cross connections between both tunnels and associated installations. The length is approximately 4 km. Maximum budget for design: €140,000. Reference budget for construction: €306 million. Lot 3 has an approximate length of 10 km and encompasses the tunnel on section Viadangos-Telledo, east tube and its associated installations. Maximum budget for design: €140,000. Reference budget for construction: €192.5 million. Lot 4 is the west tube parallel to the previous one and the cross connections between both. Maximum budget for design: €110,000. Reference budget for construction: €183.5 million. Time frame of 4 months for design, 5 years for construction and 18 months for the assembly of TBMs as of the contract awarding date. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=042344-2003, OJ S 49, or contact GIF, Madrid, fax +34 913198535. Visit www.gif.es/lineav1.html 12/03. The Ministry of development has approved the project for the Léon Asturias high speed line, section La Robla-south portal of the Pajares tunnels near Pola de Gordí³n. This 9.44 km section includes six tunnels totalling 4,089 m and three viaducts. Construction budget: €118.6 million. It has been proposed to divide the section into three subsections with an aproximate time frame for completion of two years. Design studies by Ineco and Geoconsult. Visit www.gif.es, www.geoconsult.es and www.ineco.es 18/03. Seven candidates have bidded for Lot 1 of the Pajares tunnels, section Pola de Gordí³n-Folledo. Lot 1 is for the construction of two single-track tunnels of 10.5 km each and associated underground structures, with an estimated cost of €403 million. The bidders are OHL and, in JV, Corsí¡n-Corviam, Coprosa and Comsa; Ploder and Vinci; Dragados, ACS and Obras Subterrí¡neas; Aldesa, Tableros y Puentes, Construcciones Paraí±o and Construcciones Sando; FCC and Necso; and Ferrovial with Sacyr. Tenders lapsed on 30th April, 2003 and it is planned to open the financial bids on 16th May. Tenders lapsed on 7th May, 2003 for the submission of bids for Lot 2, section Folledo-Viadangos (4 km). This section is valued at €306 million and includes two twin tunnels and other underground works. The bidders are the same as for Lot 1.Bids for the two remaining contracts are due in May 2003. Bids for Lot 3, section Viadangos-Telledo, east tunnel, are due 14th May while for Lot 4, section Viadangos-Telledo, west tunnel, they must be submitted 21st May. Visit www.gif.es 20/03. Contract 1 of the Pajares tunnels, section Pola de Gordí³n-Folledo, has been awarded to a JV of FCC and Necso for €531.7 million. Contract 1 includes the construction of two 10.5 km tunnels. The JV will build the Folledo access adit (1,950 m), to be mined by conventional means and a 60 m cut-and-cover tunnel at the portal, both to be completed during the first 14 months of the project, concurrently with a 230 m open cut to access to the portals on the Leí³n side. Once this is completed, four months will be needed to mine the Folledo cavern using conventional means. This cavern is necessary for geological reasons at the junction between the access adit and the future tunnels. The TBMs will be assembled in the cavern to drive 8 km of tunnels uphill until the portals located on the Leí³n side. Time frame: 32 months. At the same time, from the cavern, 2 x 2.5 km of tunnel will be excavated by conventional means heading downhill. Finally, 40 m-long cut-and-cover tunnels will be built at the Leí³n portals. The project also encompasses the building of the cross passages between the twin tunnels. Contract 1 also has a 18-month time frame for the assembly of the TBMs. Visit www.fcc.es and www.necso.es 22/03.Contract 2, section Folledo-Viadangos, has been awarded to a JV of Dragados, ACS and Obras Subterrí¡neas for €417.8 million. The JV will build the inmediate access to the Viadangos shafts and the cavern necessary for the junction with the tunnels, using conventional means. This will take the first two years of the project. Afterwards, 4 km of the Pajares tunnels will be bored using conventional means (San Emiliano geological formation), some 1,600 m downwhill and 2,400 m uphill. The cross passages between the two bores are also included. Time frame: 5 years. Visit www.dragados.es, www.grupoacs.com and www.obrassubterraneas.es 22/03.Both for contracts 1 and 2, the time frame for design is 4 months and 60 months for construction. 22/03.For contract 3, section Viadangos-Telledo (tunnel east), the eight bidders are Aldesa Construcciones / Tableros y Puentes / Construcciones Paraí±o / Construcciones Sí¡nchez Domí­­nguez Sando; Corsí¡n-Corviam / Coprosa / Comsa; FCC / Necso; Copcisa / Ferní¡ndez Constructor / Azvi / Constructora Hispí¡nica; OHL; Ploder / Vinci; Ferrovial-Agromí¡n / Sacyr / Cavosa; and Dragados / ACS / Obras Subterrí¡neas. 22/03.The seven candidates who have bidded for contract 4, section Viadangos-Telledo (tunnel west) are: Aldesa Construcciones / Tableros y Puentes / Construcciones Paraí±o / Construcciones Sí¡nchez Domí­­nguez Sando; Corsí¡n-Corviam / Coprosa / Comsa; FCC / Necso; Copcisa / Ferní¡ndez Constructor / Azvi / Constructora Hispí¡nica; OHL; Ferrovial-Agromí¡n / Sacyr / Cavosa; and Dragados / ACS / Obras Subterraneas. 22/03.Contract 3 for the design and construction of the Pajares tunnels has been awarded to a JV of Ferrovial-Agromí¡n, Sacyr and Cavosa for €239.19 million. Time frames are four months for design, 18 months for assembly of the TBM and 60 months for construction. Contract 3 runs from Viadangos to Telledo and includes the east tunnel and its equipment. The section starts and most of its alignment runs in Leí³n province to end in Asturias. The first stretch of this tunnel will be driven by conventional means and then with the TBM driving upwards to connect with Contract 2.Contract 4 has been commissioned to Copcisa, Ferní¡ndez Constructor, AZVI and Constructora Hispí¡nica for €220.42 million. Times frames are four months for design, 18 months for assembly of the TBM and 58 months for construction. Contract 4 also starts in Viadangos and ends in Telledo. It comprises of the west tunnel starting on the Asturian side. It also includes the construction of cross galleries between the two bores.The two single-track Pajares tunnels, 25 km in length, will feature a minimum cross section of 52 square metres. Cross passages will be drilled every 400 metres and a place for connection between the two main tunnels, located about half-way, will be excavated to allow trains to swap tracks if needed and for maintenance and emergency.According to planning, work will be completed in 2009. Then, track laying, electrification, signalling, safety and communication equipment work will commence. This will take one year to complete so that the tunnels will be commissioned in 2010. Visit www.gif.es 26/03.Open call for bids, deadline 4th February, 2004 for work supervision during construction of the Pajares tunnels. Tender budget: 7.1 million euros. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=004362-2004, OJ S 5, or contact GIF, Madrid, fax +34 913198535. 03/04.Invitation to tender to be published imminently, further to government approval, for the remaining sections of the Pajares bypass on the Leon-Asturias high speed line. Budget: EUR478.7 million. They are sections La Robla-Pajares tunnels, in Leon province, and Pajares tunnels-Pola de Lena, in Asturias. The latter has been divided in two subsections, Pajares tunnels-Sotiello and Sotiello-Pola de Lena. The total length is 24.7 km.Section La Robla-Pajares tunnels, 9.4 km in length, runs through the municipalities of Cuadros, La Robla and Pola de Gordon, all situated in Leon province. Budget for construction estimated at EUR118.7 million, time frame of 24 months. Budget for design: EUR750,000 with time frame of six months from award date. Includes six tunnels totalling 4,089 m.Subsection Pajares tunnels-Sotiello, 6 km in length, runs through the municipality of Lena in Asturias. Budget for construction estimated at EUR174 million, time frame of 32 months. Budget for design: EUR450,000 with time frame of six months from award date. Includes two double single-track tunnels, lengths 3,825 m approximately and 2,100 m.Subsection Sotiello-Pola de Lena, length 9.3 km, runs also in the municipaly of Lena. Budget for construction: EUR186 million, time frame of 36 months. Budget for design: EUR750,000 with time frame of six months from award date. Includes one double single-track tunnel, length 3,500 m, and two dual-track tunnels, lengths 2,418 m and 1,674 m respectively. 08/04.Open call for bids, deadline 12th April, 2004 for design and construction of the 6 km subsection running from the Pajares tunnels to Sotiello. Budget for design: EUR450,000. Time frame: six months. Budget for construction: EUR174 million. Time frame: 32 months. Includes two double single-track tunnels, lengths 3,825 m approximately and 2,100 m. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=034011-2004, OJ S 39, or contact GIF, Madrid, fax +34 913198535. 10/04.Open call for bids, deadline 12th April, 2004 for design and construction of the 9.3 km subsection running from Sotiello to Pola de Lena. Budget for design: EUR750,000. Time frame: six months. Budget for construction: EUR186 million. Time frame: 36 months. Includes one double single-track tunnel, length 3,500 m, and two dual-track tunnels, lengths 2,418 m and 1,674 m respectively. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=034070-2004, OJ S 39, or contact GIF, Madrid, fax +34 913198535. 10/04.Open call for bids, deadline 12th April, 2004 for design and construction of the 9.4 km subsection running from La Robla to the Pajares tunnels. Budget for design: EUR750,000. Time frame: six months. Budget for construction: EUR118.7 million. Time frame: 24 months. Includes six tunnels totalling 4,089 m. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=034079-2004, OJ S 39, or contact GIF, Madrid, fax +34 913198535. 10/04.Open call for bids, deadline 26th March, 2004 for project construction management and work control of subsection La Robla-Pajares tunnels. Tender budget: EUR3.7 million. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=034342-2004, OJ S 39, or contact GIF, Madrid, fax +34 913198535. 10/04.Open call for bids, deadline 26th March, 2004 for project construction management and work control of section Pajares tunnels-Pola de Lena. Subsection Pajares tunnels-Sotiello includes two double single-track tunnels, lengths 3,825 m and 2,100 m. Subsection Sotiello-Pola de Lena includes one double single-track tunnel, length 3,500 m, and two dual-track tunnels, lengths 2,418 m and 1,674 m respectively. Tender budget: EUR8.1 million. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=034344-2004, OJ S 39, or contact GIF, Madrid, fax +34 913198535. 11/04.Ineco and Geoconsult secured a EUR4.5 million contract for construction management and work conrol of the Pajares tunnels. Visit www.ineco.es and www.geoconsult.es 15/04.Open call for bids, deadline 19th August, 2004 for design of two subsections, 4.32 km and 4.85 km, running from Sotiello to Campomanes and from Campomanes to Pola de Lena. Budgets: EUR980,000 and EUR850,000. Time frames: ten months and nine months respectively. The Sotiello-Pola de Lena section includes one double single-track tunnel, length 3,500 m, and two dual-track tunnels, lengths 2,418 m and 1,674 m respectively. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=107736-2004 and http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=107737-2004, OJ S 127, or contact GIF, Madrid, fax +34 913198535. This is a rebid further to the decision of the Ministry of public works to cancel a previous design and build tender and to invite tenders separately for design and construction. 29/04.Open call for bids, deadline 18th August, 2004 for construction management and work control of sections La Robla-Pajares tunnels and Pajares tunnels-Pola de Lena. Tender budget: EUR600,000 and time frame: 12 months. Subsection Pajares tunnels-Sotiello includes two double single-track tunnels, lengths 3,825 m and 2,100 m. Subsection Sotiello-Pola de Lena includes one double single-track tunnel, length 3,500 m, and two dual-track tunnels, lengths 2,418 m and 1,674 m respectively. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=107752-2004, OJ S 127, or contact GIF, Madrid, fax +34 913198535. This is a rebid. 29/04.Open call for bids, deadline 19th August, 2004 for design of the subsection running from La Robla to the Pajares tunnels. Budget: EUR1.25 million and time frame: nine months. This section includes six tunnels totalling 4,089 m. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=107730-2004, OJ S 127, or contact GIF, Madrid, fax +34 913198535. This is a rebid further to the decision of the Ministry of public works to cancel a previous design and build tender and to invite tenders separately for design and construction. 29/04.Open call for bids, deadline 19th August, 2004 for design of the 6.1 km Pajares tunnels-Sotiello section. Tender budget: EUR950,000 and time frame: nine months. Section Pajares tunnels-Sotiello includes two double single-track tunnels, lengths 3,825 m and 2,100 m. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=107731-2004, OJ S 127, or contact GIF, Madrid, fax +34 913198535. This is a rebid further to the decision of the Ministry of public works to cancel a previous design and build tender and to invite tenders separately for design and construction. 29/04.The design of section La Robla-south portals of the Pajares tunnels, 9.4 km in length, has been awarded to Geoconsult Espaí±a and Idom for EUR900,000. This section includes six tunnels for a total length of 4,089 m. Visit www.geoconsult.es and www.idom.es 45/04.Ayesa will design for EUR684,000 the section from the north portals of the Pajares tunnels to Sotiello (6.1 km), which includes two tunnels (3,825 and 2,094 m). Visit www.ayesa.es 45/04.Getinsa and Geocontrol will design the Sotiello-Campomanes section (4.3 km), which includes two tunnels (1,004 and 753 m), for EUR715,700. Visit www.getinsa.es and www.geocontrol.es 45/04.TRN Ingenierí­­a y Planificacií³n de Infraestructuras and GTT Ingenierí­­a y Tratamientos del Agua secured a EUR603,500 contract to design the Campomanes-Pola de Lena section (4.9 km), which includes two tunnels (2,418 and 1,674 m). 45/04.Ineco secured a EUR380,200 contract for the construction management and work control of sections La Robla-Pajares tunnels and Pajares tunnels-Pola de Lena. Section from La Robla to the south portals includes six tunnels for a total length of 4,089 m. Section from the north portals to Pola de Lena includes six tunnels (3,825 m / 2,094 m / 1,004 m / 753 m / 2,418 m and 1,674 m). Visit www.ineco.es 48/04.Open call for tenders, deadline 14th February, 2006 for construction of section La Robla-Pajares tunnel (9.4 km), in Leon province, on the Leon-Asturias high speed link. The EUR120.6 million scheme includes six twin-track 85-90 sq m tunnels: Castro (493 m), Alba (1,132 m), Peredilla (711 m), Buen Suceso I (736 m), Buen Suceso II (251 m) and Nocedo de Gordon (701 m), to be built by conventional methods. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=03564-2006, OJ S 3, or contact ADIF, Madrid, fax +34 917005771. 03/06.Open call for tenders, deadline 17th March, 2006 for work supervision of section La Robla-Pajares tunnel in Leon province. The 9,440 m section includes six tunnels (4,024 m). Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=033396-2006, OJ S 30, or contact ADIF, Madrid, fax +34 917005771. 08/06.ADIF, the authority responsible for managing the construction of high speed lines, has awarded to a JV between OHL and Obras Subterraneas a EUR89.5 million 24-month contract. This 9.4 km-long section has been designed for double tracks. Along its route, the following 85-90 sq m twin-track tunnels will be built using conventional methods: Castro (493 m), Alba (1,132 m), Peredilla (711 m), Buen Suceso I (736 m), Buen Suceso II (251 m) and Nocedo de Gordon (701 m). Read E-News Weekly 5/2006. Visit www.adif.es, www.ohl.es and www.obrassubterraneas.es 15/06.Open call for bids, deadline 17th May, 2006 for construction of section Sotiello-Campomanes (4.3 km) on the Pajares railway bypass, including the Sotiello and Teso twin-tube tunnels. Their length is 2 x 990 m and 2 x 786 m for a cross section of 62 sq m. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=079306-2006, OJ S 75, or contact ADIF, Madrid, fax +34 917005751. 19/06.Open call for bids, deadline 26th June, 2006 for construction of section Pajares tunnels-Sotiello in Asturias. It is a 6.1 km-long dual-track section starting from the north entrance of the Pajares tunnels. The section includes the Los Pontones and Jomezana tunnels, of 3,780 m and 2,050 m respectively. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=099907-2006, OJ S 93, or contact ADIF, Madrid, fax +33 917005751. 21/06.Open call for tenders, deadline 26th June, 2006 for construction of section Campomanes-Pola de Lena on the Pajares railway bypass. This 4.9 km dual-track section includes two tunnels: Vega de Ciego (2,465 m) and Pico de Siero (1,646 m). Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=099910-2005, OJ S 93, or contact ADIF, Madrid, fax +34 917005751. 22/06.Prointec secured a EUR2.4 million contract to supervise the construction of section La Robla-Pajares tunnel in Leon province. The 9,440 m section includes six tunnels, totalling 4,024 metres. Click es/55. Visit www.prointec.es 24/06.ADIF, the high speed rail administration, has awarded to Acciona Infraestructuras the construction contract for section Sotiello-Campomanes (4.32 km) on the Pajares railway bypass, which is part of the high speed link from Leon to Asturias. The contract, worth EUR79.8 million with a time frame of 28 months, has been designed for UIC gauge for a twin-track high speed line. The first 2.6 kilometres run along two single tracks while the remaining 1.72 kilometres travel on a double track. Noticeable structures include the Sotiello and Teso twin-tube tunnels, respectively 2 x 990 m and 2 x 786 m in length for a cross section of 62 sq m, to be bored using conventional methods. Visit www.acciona-infraestructuras.es 27/06.A JV of Acciona Infraestructuras (50%) and FCC (50%) will construct section Pajares tunnels-Sotiello in Asturias. This 6.1 km dual-track section starts from the north entrance of the Pajares tunnels and includes the Los Pontones and Jomezana tunnels, of 3,780 m and 2,050 m respectively. The contract is worth EUR160.3 million. Visit www.acciona.es and www.fcc.es 36/06.A JV of Comsa (50%) and Corsan-Corviam (50%) has been awarded a EUR70.8 million contract to build the twin-track section Campomanes-Pola de Lena (4.9 km) on the Pajares railway bypass, which includes two tunnels: Vega de Ciego (2,465 m) and Pico de Siero (1,646 m). Visit www.comsa.com and www.isoluxcorsan.com 36/06.Open call for tenders, deadline 13th November, 2006 for construction supervision for the Sotiello-Campomanes and Campomanes-Pola de Lena sections, 4.3 km and 4.9 km respectively, on the Pajares railway bypass. The first section includes the Sotiello and Teso twin-tube tunnels, 2 x 990 m and 2 x 786 m respectively. The second section includes the Vega de Ciego and Pico de Siero tunnels, 2,465 m and 1,646 m long respectively. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=199100-2006, OJ S 187, or contact ADIF, Madrid, fax +34 917005751. 41/06.Open cal lfor tenders, deadline 24th November, 2006 for work supervision of section Pajares tunnels-Sotiello on the new Leon-Asturias high speed line. This 6.1 km dual-track section starts from the north entrance of the Pajares tunnels and includes the Los Pontones and Jomezana tunnels, of 3,780 m and 2,050 m respectively. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=209608-2006, OJ S 197, or contact ADIF, Madrid, fax +34 917005751. 43/06.SGS Tecnos and Inocsa secured a EUR2.8 million contract for work supervision of section Pajares tunnels-Sotiello on the new Leon-Asturias high speed line. This 6.1 km dual-track section starts from the north entrance of the Pajares tunnels and includes the Los Pontones and Jomezana tunnels, of 3,780 m and 2,050 m respectively. Visit www.es.sgs.com and www.inocsa.esPayma Cotas and Apia XXI bagged a EUR4 million contract for site supervision for the Sotiello-Campomanes and Campomanes-Pola de Lena sections, 4.3 km and 4.9 km respectively, on the Pajares railway bypass. The first section includes the Sotiello and Teso twin-tube tunnels, 2 x 990 m and 2 x 786 m respectively. The second section includes the Vega de Ciego and Pico de Siero tunnels, 2,465 m and 1,646 m long respectively. Visit www.paymatocas.com and www.apiaxxi.es 07/07.Periodic notice, deadline unspecified, being a call for bids aiming at reducing time limits for the receipt of tenders, for design of the overhead installations (switches, tunnel lighting, energy supply) for the Pajares railway bypass between La Robla and Pola de Lena. This includes the 2 x 24.6 Pajares tunnel and 12 tunnels on the north and south accesses to this base tunnel. Read E-News Weekly 10/2007 & 5/2006. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=30386-2008, OJ S 23, or contact ADIF, Madrid, tel. +34 915067281. E-mail gvillegas@adif.es 07/08.Open invitation to tender, deadline 18th November, 2008 for designs of the necessary civil works in addition to those already built at the Pajares railway bypass: ultimate waterproofing of the Pajares tunnels, complementary civil works in the Pajares twin-tube tunnel (platforms, ducting, hazardous liquid drainage system, water inflow drainage system, fit-out of cross-passages, safe areas and emergency exits), outside works (water treatment system for the drainage waters from the tunnel, technical and management facilities and all civil works needed to complement the final equipment of the tunnel). The contract also includes a safety study of the tunnels to analyse the works already completed and propose measures to be adopted in these complementary civil works. Click here, here, here and here. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=259042-2008, OJ S 195, or contact ADIF, Madrid, fax +34 917005751. 42/08.



Permalink

JV Obrascon Huarte Lain SA and Obras Subterraneas SA secured the EUR6.82 million contract for complementary works on La Robla-Pola de Lena (Pajares bypass) section La Robla-Pajares tunnels, lot 2 on the new Leon-Asturias high speed line. Contact Adif, c/Titan, Madrid, tel +34 917744837, fax +34 917745814, e-mail irodriguezdepablos@adif.es, pmardaiz@adif.es. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=056455-2010. 11/10.



Permalink

JV Pajares 3, composed by Ferrovial Agroman SA (50%), Sacyr, S.A.U. (35%) and Cavosa obras y proyectos SA (15%), secured the EUR34.99 million contract for complementary works at Lot 3 Pajares tunnels on the new Leon-Asturias high speed line. Contact Adif, c/ Tití¡n, Madrid, tel +34 917744837, fax +34 917745814, e-mail irpablos@adif.es, pmardaiz@adif.es. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=064223-2010. 12/10.JV Tunel Pajares IV (Constructora Hispanica SA (25%), Copcisa SA (25%), Azvi SA (25%) and Fernandez Constructor SA (25%)) secured the EUR33.6 million contract for complementary works at Lot 4 Pajares tunnels on the new Leon-Asturias high speed line. Contact Adif, c/ Tití¡n, Madrid, tel +34 917744837, fax +34 917745814, e-mail irpablos@adif.es, pmardaiz@adif.es. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=067269-2010. 12/10.



Permalink

Open invitation to tender, deadline 25.11.2010, for additional internal civil construction in Pajares tunnels Lot South, Madrid-Asturias La Robla-Pola de Lena (Pajares variant). Contract value EUR78,412,822 excluding VAT, duration 14 months. Time limit for accessing documents 18.11.2010. More information from ADIF in Madrid, tel +34 91774-4837, fax -5814, e-mail mjmoro@adif.es or pmardaiz@adif.es to whom tenders or requests to participate must be sent. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=303532-2010. 41/10.



Permalink

Open invitation to tender, deadline 25.11.2010, for additional internal civil construction in Pajares tunnels Lot North, Madrid-Asturias La Robla-Pola de Lena (Pajares variant). Contract value EUR140,145,741 excluding VAT, duration 15 months. Time limit for accessing documents 18.11.2010. More information from ADIF in Madrid, tel +34 91774-4837, fax -5814, e-mail mjmoro@adif.es or pmardaiz@adif.es to whom tenders or requests to participate must be sent. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=303533-2010. 41/10.



Permalink

Contract for additional internal civil construction in Pajares tunnels Lot South, Madrid-Asturias La Robla-Pola de Lena (Pajares variant), value EUR70,759,730 excluding VAT, awarded to UTE Constructora San Jose (60 percent) and Peninsular de Contratas (40 percent). Contract duration 14 months. More information from ADIF in Madrid, tel +34 91774-4837, fax -5814, e-mail mjmoro@adif.es. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=082794-2011. 11/11.



Permalink

Contract for additional internal civil construction in Pajares tunnels Lot North, Madrid-Asturias La Robla-Pola de Lena (Pajares variant), value EUR126,131,167 excluding VAT, awarded to UTE FCC Construccion SA (50 percent) and Acciona Infraestructuras (50 percent). Contract duration 14 months. More information from ADIF in Madrid, tel +34 91774-4837, fax -5814, e-mail mjmoro@adif.es. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=122242-2011. 16/11.



Permalink

JV Pajares 3 comprising Ferrovial Agroman SA, Sacyr, S.A.U. and Cavosa obras y proyectos SA, secured the EUR9.17 million contract, VAT not included, for complementary works n.2 and construction of the platform at Lot 3 Pajares tunnels on the new Leon-Asturias high speed line. Contact Adif, c/ Titan, Madrid, tel +34 917744837, fax +34 917745814, e-mail mjmoro@adif.es. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=171223-2011. 23/11.



Permalink

Open invitation to tender, deadline 17.02.2014, for track construction works on the section Tuneles de Pajares-Pola de Lena (Pajares bypass), new Madrid-Asturias high speed line. Duration of contract 15 months from award, value EUR28,266,207, excluding VAT. Time limit for receipt of requests for documents or for accessing documents: 10.02.2014. Contact Adif, Madrid, tel +34 917744804, fax +34 917674490, e-mail mjmoro@adif.es. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=80-2014. Ref.n. 3.13/20505.0031 (ON 013/13). 02/14.



Permalink

Open invitation to tender, deadline 17.02.2014, for track construction works on the section La Robla- Tuneles de Pajares (Pajares bypass), new Madrid-Asturias high-speed line. Duration of contract 12 months from award, value EUR27,157,771, excluding VAT. Time limit for receipt of requests for documents or for accessing documents: 10.02.2014. Contact Adif, Madrid, tel +34 917744804, fax +34 917674490, e-mail mjmoro@adif.es. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=81-2014. Ref.n. 3.13/20505.0029 (ON 012/13). 02/14.



Permalink

Open invitation to tender, deadline 03.02.2014, for lining of Folledo tunnel (Pajares tunnels) on the new Madrid-Asturias high-speed line, section La Robla-Pola de Lena. Duration of contract nine months from award, value EUR9,736,307, excluding VAT. Time limit for receipt of requests for documents or for accessing documents: 27.01.2014. Contact Adif, Madrid, tel +34 917744804, fax +34 917674490, e-mail mjmoro@adif.es. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=418437-2013. Ref.n. 3.13/06402.0091 (ON 009/13). 02/14.



Permalink

The JV Electrificacion Pajares (Astom Transporte, SA and Isolux Ingenieria, SA) at Madrid secured the EUR10,496,595 contract, excluding VAT, for the catenary construction and maintenance works.of the section La Robla-Pola de Lena (Pajares bypass) on the new Madrid-Asturias high speed line. Contact Mrs Rosa Samper Membrillo, Adif, Madrid, tel +34 913007589, fax +34 913006623, e-mail rsamper@adif.es. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=439492-2013. Ref.n. 4.13/20505.0030. 02/14.



Permalink

Open invitation to tender, deadline 30.06.2014, for construction and maintenance of civil protection and safety equipment of the tunnels on the section La Robla -Pola de Lena (Pajares bypass), new Madrid-Asturias high-speed line.  Duration of contract 38 months from award, value EUR83,396,252.92, excluding VAT. Time limit for receipt of requests for documents or for accessing documents: 23.06.2014. Contact Adif, Madrid, tel +34 917744804, fax +34 917674490, e-mail pmardaiz@adif.es. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=165617-2014. Ref.n. 4.14/06800.0123 (OM 002/14). 21/14.



Permalink

Dragados SA secured the EUR7.67 million contract, excluding VAT, for track construction works on the section Tuneles de Pajares-Pola de Lena (Pajares bypass), new Madrid-Asturias high-speed line. Contact Adif, Madrid, tel +34 917744804, fax +34 917745814, e-mail pmardaiz@adif.es. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=318518-2014. Ref.n. 3.13/20505.0031. 39/14.



Permalink

The JV FCC Construccion (50 percent)/Acciona Infraestructuras (50 percent) secured the EUR7.81 million contract, excluding VAT, for track construction works on the section La Robla-Tuneles de Pajares (Pajares bypass), new Madrid-Asturias high-speed line. Contact Adif, Madrid, tel +34 917744804, fax +34 917745814, e-mail pmardaiz@adif.es. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=289834-2014. Ref.n. 3.13/20505.0029. 39/14.



Permalink

The JV Alstom Transporte (42.75 percent)/Instalaciones Carlos Busto (5 percent)/Indra Sistemas (35.15 percent)/Indra Sistemas de Seguridad (17.10 percent) secured the EUR29.8 million contract, excluding VAT, for construction and maintenance of civil protection and safety equipment of the tunnels on the section La Robla-Pola de Lena (Pajares bypass), new Madrid-Asturias high-speed line. Contact Adif, Madrid, tel +34 917744804, fax +34 917674490, e-mail pmardaiz@adif.es. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=396652-2014. Ref.n. 4.14/06800.0123 (OM 002/14). 01/15.



Permalink

The JV Alstom Transporte (42.75 percent)/Instalaciones Carlos Busto (5 percent)/Indra Sistemas (35.15 percent)/Indra Sistemas de Seguridad (17.10 percent) secured the EUR29.8 million contract, excluding VAT, for construction and maintenance of civil protection and safety equipment of the tunnels on the section La Robla-Pola de Lena (Pajares bypass), new Madrid-Asturias high-speed line. Contact Adif, Madrid, tel +34 917744804, fax +34 917674490, e-mail pmardaiz@adif.es. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=396652-2014. Ref.n. 4.14/06800.0123 (OM 002/14). 01/15.



Permalink


The joint venture of Impermeabilizacion Tunel and Pajares Norte from Alcobendas secured the contract n.246.561, the value of EUR2.25 million, excluding VAT, for the procedure for  the acquisition of existing temporary power supply, ventilation, lighting and communications installations of the Pajares Tunnel (Lot North).  For more information contact: Tragsa SA from Madrid, tel +34 913963667, fax +34 913969172, email contratacion@tragsa.es. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=066759-2017. Ref.n. TSA000062328. 09/17.




Permalink

Open invitation to tender, deadline 16.11.2017, for consultancy and technical assistance during lining work for the Folledo tunnel (2 km long) on the La Robla-Pola de Lena (Pajares bypass), section. This tunnel is on the new Madrid-Asturias high speed line. Duration of the contract will be 14 months from the award, renewable for 7 months maximum. Value contract  EUR1.04 million, excluding VAT. Contact Adif, Madrid, tel +34 917744804, fax +34 917674490, email mjmoro@adif.es. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=396903-2017. Ref.n. 3.17/20830.0234 (CON 015/17). 41/17.



Permalink

The JV Constructora San Jose SA (60 %)/Ferpi Transportes y Obras SA at Pontevedra secured the EUR6.55 million contract, excluding VAT, for lining work for the Folledo tunnel (2 km long) on the La Robla-Pola de Lena (Pajares bypass) section. This tunnel is on the new Madrid-Asturias high speed line. Value of thr contract is EUR6.55 million, excluding VAT. Contact Adif, Madrid, tel +34 917744804, fax +34 917674490, email pmardaiz@adif.es. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=089039-2018.

Ref.n. 3.17/20830.0042 (ON 003/17). 11/18.



Permalink

Prior information notice without call for competition for the provision of protection and safety equipment in the Pajares tunnels. The contract value is EUR1.86 million, excluding VAT. Duration of the contract is 14 months from award. Contact Adif-Alta Velocidad, Madrid, tel +34 915066671, email subirecciongestionadministrativa@adif.es. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=188941-2018.

25/18.



Permalink


Prior information notice without call for competition for the ACO (Asistencia para el Control de las Obras) for the installation of protection and safety equipment in the Pajares tunnels. The contract value is EUR1.86 million, excluding VAT. Duration of the contract is 14 months from award.

Contact Adif-Alta Velocidad, Madrid, tel +34 915066671, email subirecciongestionadministrativa@adif.es. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=188941-2018.

25/18.




Permalink


Prior information notice without call for competition for installation of protection and safety equipment in tunnels of the Pajares bypass. Value of the contract is EUR 74.28 million, excluding VAT. Duration of the contract 14 months from award. Contact Adif-Alta Velocidad, Madrid, tel  +34 915066671, email subirecciongestionadministrativa@adif.es.

Visit

http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=185753-2018.

27/18.




Permalink

Prior information notice without call for competition for the technical assistance for the supervision of acoustic protection works on Pajares bypass. Scheduled date of publication of the call for tenders: 01/03/2019. Contract value 55.000 Euro, VAT excludedContact Adif, Madrid, email gestionadministrativaAV@adif.es. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=078749-2019.

08/19.



Permalink

Periodic indicative notice without call for competition for installation of protection and safety equipment in tunnels of the Pajares bypass. Value of the contract is EUR57 million, excluding VAT. Duration of the contract will be 18 months from the award. Contact Adif-Alta Velocidad, Madrid, email gestionadministrativaAV@adif.es.. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=106402-2019.

11/19.




Permalink

Periodic indicative notice without call for competition for assistance for the control of works  during installation of protection and safety equipment in tunnels as part of the Pajares bypass. Value of the contract is EUR2.85 million, excluding VAT. Duration of the contract will be 12 months.

Contact Adif-Alta Velocidad, Madrid, email gestionadministrativaAV@adif.es. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=096544-2019.

Ref.n. 19FEI37396.  11/19.



Permalink

Open invitation to tender, deadline 10/09/2019, for technical assistance for control and monitoring of electric traction substation works and associated auto - transformation centres, power remote control and double 20kv line on the La Robla - Pola de Lena section (Pajares bypass). Value of the contract is EUR447,869.65, excluding VAT. Duration of the contract will be 10 months. Contact Adif-Alta Velocidad, attn Rosa Samper, Madrid, tel +34 913007589, fax +34 917674490, email RSAMPER@ADIF.ES. Visit

http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=358453-2019.

Ref.n. 3.19/20830.0192.  32/19.



Permalink

The JV Comsa Instalaciones y Sistemas Industriales / Sacyr Neopul secured the EUR12.81 million contract, including VAT, for the overhead contact line and associated systems on the La Robla-Campomanes section (Pajares bypass). The estimated execution time is 15 months. Contact ADIF Alta Velocidad, attn Rosa  Samper, Madrid, tel +34 913007589, email rsamper@adif.es.  Visit http://www.adifaltavelocidad.es and http://prensa.adifaltavelocidad.es. Ref.n. 3.19/20830.0237. 28/20.




Permalink

The JV Alstom Transporte, Indra Sistemas and Constructora San Jose secured the EUR64.38 million contract, including VAT, for protection and security equipment in the tunnels of the La Robla-Pola de Lena section, Pajares Bypass. The estimated execution time is 18 months. Contact ADIF Alta Velocidad, attn Tomas Rodriguez, Madrid, tel +34 917744838, email contrataciondcc@adif.es. Visit http://www.adifaltavelocidad.es and http://prensa.adifaltavelocidad.es. Ref.n. 3.19/20830.0324. 28/20.





Permalink


The JV Saite SA and Geocontrol SA from Leioa secured the EUR948,550.07 contract, excluding VAT, for consulting and technical assistance to the construction management of Adif - High Speed for protection and safety equipment in the tunnels of the La Robla-Pola de Lena section, Pajares Bypass. Contact Adif - Alta Velocidad, Madrid, tel +34 917744804, fax +34 917674490, email contrataciondcc@adif.es. For further on the tender click here. Ref.n. 3.19/20830.0192. Ref.n. 3.20/20830.0049 – CON 004/20. 02/21.

 




Permalink


The Joint Venture Alstom Transporte SA (35 %) – Indra Sistemas SA (35 %) – Constructora San Jose SA (30 %) from Madrid secured the EUR 53.20 million contract, excluding VAT, for protection and safety equipment in the tunnels of the La Robla-Pola de Lena section, Pajares Bypass. Contact Adif - Alta Velocidad, Madrid, tel +34 917744804, fax +34 917674490, email contrataciondcc@adif.es. For further on the tender click here. Ref.n. 3.19/20830.0324 – ON 034/19. 02/21. 

 




Permalink


Periodic indicative notice for adaptation of access, evacuation and protection and security installations in the tunnels of the Pajares bypass on the León-Asturias high-speed line. Click here for tender documents and here where tenders or requests to participate must be submitted electronically. Estimated date of publication of contract notice: 30/06/2021. Value of the contract is EUR14 million, excluding VAT. Duration of the contract will be 13 months. Contact ADIF Alta Velocidad,  Madrid, tel +34 917744804, fax +34 917674490, email contrataciondcc@adif.es.  For further on TED tender, please click here. 14/21. 

 




Permalink


Periodic indicative notice for technical assistance to works management for adapting access, evacuation, protection and security facilities in the tunnels of the Pajares bypass. Click here for procurement and here for tenders or requests to participate. Estimated date of publication of contract notice: 30/06/21. Value of the contract is EUR 700,000, excluding VAT. Duration of the contract 17 months. Contact Adif-Alta Velocidad, Madrid, tel +34 917744804, fax  +34 917674490, email contrataciondcc@adif.es. For further information on TED tender, please click here. 17/21.  




Permalink


Periodic indicative notice for the adaption works of access, evacuation, protection and security facilities in the tunnels of the Pajares bypass. Click here for procurement and here for tenders or requests to participate. Estimated date of publication of contract notice: 30/06/21. Value of the contract is EUR14 million, excluding VAT. Duration of the contract 14 months. Contact Adif-Alta Velocidad, Madrid, tel +34 917744804, fax  +34 917674490, email contrataciondcc@adif.es. For further information on TED tender, please click here. 17/21.  




Permalink


The Consortium composed of Indra (35%), Alstom (35%) and Constructora San Jose (30%) has awarded Zitron  with the supply and commissioning of the tunnel ventilation system for the 25 km High-Speed Rail twin-tube tunnels of Pajares.  

The project includes a longitudinal system, comprising the installation of 212 jet fans, distributed throughout the tunnels. These units are designed and certified to work at 400ºC during at least two hours and are completely made of 316L quality stainless steel to withstand the harsh environmental conditions of the tunnel. In addition, special attention has been paid to their reinforced design, as they must be able to withstand pressures of up to 10,000 Pa produced by the piston effect of high-speed trains. Visit https://zitron.com. 20/21. 

 




Permalink


Open invitation to tender, deadline 07/06/2021, for the adaptation of access, evacuation, protection and security installations in the tunnels of the Pajares bypass on the León-Asturias high-speed line. Click here for tender documents and here where tenders or requests to participate must be submitted electronically. Value of the contract is EUR13.5 million, excluding VAT. Duration of the contract will be 14 months. Contact ADIF Alta Velocidad,  Madrid, email contrataciondcc@adif.es.  For further on TED tender, please click here. Ref.n. 3.21/20830.0035 – ON 007/21. 21/21.  

 




Permalink


Cavosa Obras y Proyectos SA from Madrid secured the EUR 11.24 million contract, excluding VAT, for the adaptation of access, evacuation, protection and security installations in the tunnels of the Pajares bypass on the León-Asturias high-speed line. Contact ADIF Alta Velocidad,  Madrid, email contrataciondcc@adif.es.  Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=545595-2021. Ref.n. 3.21/20830.0035 – ON 007/21. 43/21. 



Permalink


Segura Control SA from Madrid secured the EUR 605,841.60 contract, excluding VAT, for the surveillance and access control service in the Pajares tunnels and their annexed facilities (Madrid-Asturias high-speed line). Contact Empresa de Transformación Agraria S.A.,S.M.E., M.P., (TRAGSA), Madrid, tel +34 913963667, fax +34 913969172, email contratacion@tragsa.es.  Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=041948-2022. Ref.n. TSA000071457. 04/22. 



Permalink


Typsa (Tecnica Y Proyectos, SA) from San Sebastian de los Reyes secured the EUR563,508.79 contract, excluding VAT, for technical assistance to works management for adapting access, evacuation, protection and security facilities in the tunnels of the Pajares bypass. Contact Adif-Alta Velocidad, Madrid, tel +34 917744804, fax  +34 917674490, email contrataciondcc@adif.es. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=091378-2022. Ref.n. 3.21/20830.0052 - CON 002/21. 07/22.   



Permalink


Asociacion de Accion Ferroviaria (Cetren) from Madrid have secured the contracts for 9 lots for CE validation  of interoperability of the infrastructure and/or energy subsystems on the new high speed railway sections: 

  • Lot1: Olmedo-Zamora-Pedralba, value of the contract EUR355,000, excluding VAT; 
  • Lot 2: Valladolid-Leon/Venta de Banos-Burgos, value of the contract EUR495,000, excluding VAT; 
  • Lot 3: Antequera-Granada, value of the contract EUR188,000, excluding VAT; 
  • Lot 4: La Robla-Pola de Lena, value of the contract EUR249,000, excluding VAT;
  • Lot 5: Castellbisbal-Tarragona (Vilaseca)-Vandellos-Castellon-Valencia, value of the contract EUR664,000, excluding VAT;
  • Lot 6: Monforte del Cid-Murcia-Alicante (Cambiador Encina)-Jativa-Valencia, value of the contract EUR305,000, excluding VAT;
  • Lot 7: Plasencia-Badajoz, , value of the contract EUR170,000, excluding VAT; 
  • Lot 8: Vigo-Santiago-la Coruna-Orense-Santiago, value of the contract EUR567, 000, excluding VAT; 
  • Lot 9: Tunnel AV Atocha-Chamartin, , value of the contract EUR43,459, excluding VAT. 

Contact  Adif Alta Velocidad, attn Francisco Macias Bonilla, Madrid, tel +34 661347788,  email fmacias@adif.es. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=120827-2022. Ref.n. 3600000039. 11/22.




Permalink


Modification of the contract secured to the Joint Venture Alstom Transporte SA (35 %) – Indra Sistemas SA (35 %) - Constructora San Jose SA (30 %) from Madrid for protection and security installations in the tunnels of the La Robla-Pola de Lena section, Pajares Bypass. Contact Adif - Alta Velocidad, attn Jose Vicente Rodriguez, Madrid, tel +34 917744891, fax +34 917674490, email jvrodriguez@adif.es. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=360496-2022. Ref.n. 3.19/20830.0324 – ON 034/19. 28/22.  



Permalink


Open invitation to tender, deadline 11/12/2023, for the maintenance  of civil protection and security facilities in the tunnels of the La Robla - Pola de Lena high-speed line (Pajares Bypass). Click here for tender documents and here where tenders must be sent. Value of the contract is EUR 4,490,551.32, excluding VAT. Duration of contract 24 months. Contact Adif, Madrid, tel +34 91 300 6638, email compras.contratacion@adif.es. Visit  http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=660530-2023. Ref.n. 2.23/21520.0128.  45/23. 

 




Permalink

Spain, Malaga - es/54

Water Distribution

Open invitation to tender, deadline 10th September, 2001, for engineering design and EIS of Aliviadero water tunnel as part of Limonero dam project for ACS, Malaga, fax +34 95 2206817. Visit www.boe.es 35/01. Two design supervision tenders, deadline 11th December, 2001. First for 5.5 km tunnel to link Guadalmedina to La Vií±uela Dam for which seventeen bids have been submitted for the design and nineteen for the EIS. Visit http://ted.eur-op.int, document S 206-141359. Second for 11 km discharge tunnel between Limonero Dam and Rock of El Cuervo, for which eleven bids have been received for the design and sixteen for the EIS. Visit http://ted.eur-op.int, document S 206-141360. Contact Acusur, Malaga, fax +34 952206817. Visit www.acusur.es 45/01. Ayesa-Narval jv appointed for the design of the 5.5 km tunnel between Guadalmedina and La Vií±uela Dam for Euro1 million. EIS contract awarded to Interlab. Iberinsa commissioned for the design of the 11 km discharge tunnel to link Limonero Dam to El Cuervo for Euro1.8 million. EIS contract awarded to Eptisa. Design time frame to last 8 months for both projects. Visit www.acusur.es 46/01.Cancellation of the two design supervision tenderings for the 5.5 km tunnel to link Guadalmedina to La Vií±uela Dam, and the 11 km discharge tunnel between Limonero Dam and Rock of El Cuervo. Visit http://ted.eur-op.eu.int, documents S 206-141359 and 141360. 48/01.



Permalink

Spain, Puertollano - es/53

Motorway

Preannouncement of invitation to tender for consultancy contract to establish route of A42 motorway from Levante to Extremadura with 1.4 km-long tunnel. Visit www.boe.es 24/01. Open invitation to tender, deadline 19th October, 2001, for engineering design of the N-420 Variante de Poblacion, Puertollano section with 1 km-long x 90 sq m tunnel. Contact Ministry of Works, fax +34 91 597 8537, or visit www.boe.es 42/01.Award to Ofiteco of a €790,800 engineering contract for the Puertollano variant on N-420 in Ciudad Real province. There is a 1 km tunnel. Visit www.ofiteco.es 25/02.



Permalink

Spain, International - es/51

High Speed Railway

Work groups to carry out technical, economic and financial studies for Porto-Vigo and Madrid-Lisbon-Porto high speed railway lines. Visit www.gif.es and www.rave.pt 18/01. Invitations to tender expected for 18.5 km of tunnels on 43 km-long section from Guadalcazar to Fuente Palmero including 7 km-long Abdalajis tunnel. Visit www.gif.es 21/01.Open tendering for technical, economical and environmental feasibility of the Madrid-Lisbon-Porto and the Vigo-Porto high speed connections. Deadline 18th February, 2002. Visit http://ted.eur-op.eu.int/ojs/en/frame.htm, OJ S 248, documents 171254- and 171255-2001 or contact AVEP, Alta Velocidad Espaí±a-Portugal, c/ Miguel Angel, 21 28010 Madrid, tel. +34 917004700. 03/02.



Permalink

Spain, Madrid-Segovia - es/50

High Speed Railway

Open invitation to tender, deadline 7th May, 2001, for construction of 6.7 km-long railway section between Santa Marí­a la Real de Nieva and Ortigosa del Pestaí±o including 3.5 km-long Tabladillo tunnel. Visit www.gif.es 16/01. Award of a 6.7 km section with 4.3 km-long 14 m-diameter (100 sq m) Tabladillo tunnel to a jv of Ploder and Obras Subterrí¡neas. Preparatory works underway. Drill/blast method for 2,725 metres plus cut-and-cover method for 790 metres on the south side and 835 metres on the north side. Contract value of €49 million. Time frame of 21 months. Visit www.gif.es 17/02.



Permalink

Spain, San Sebastian - es/49

Railway

Invitation to negotiate contract, deadline 7th May, 2001, for construction of 1.75 km-long railway tunnel for Ferrocarriles Vascos, fax +34 94 401 9901. Visit www.boe.es 17/01. Open tendering, deadline 20th December, 2001, for the south variant between Aí±orga and Amara stations on the Bilbao-San Sebastian railway. Includes a 900 m tunnel and a 100 m underground station. Visit http://ted.eur-op.int, document S 214-147100 or contact the Basque Railways, Bilbao, fax +34 94 4330602. Budget is €18.5 million. Also visit www.euskotren.es 47/01.Dualling of the EuskoTren line between the Easo and Aí±orga stations awarded to a jv of Construcciones Altuna y Urí­a, and Construcciones Mariezkurrena for €18 million. Time frame for construction of 23 months. The 3,366 m section includes two tunnels in Aiete and Amara totalling 1,606 m as well as a 101 m-long subterranean station in Gerií¡trico. Visit www.euskotren.es 09/02.Open call for tenders, deadline 5th September, 2005 for design of section Anorga-Rekalde on the Bilbao-San Sebastian line. This 2.5 km section includes a 1.3 to 1.4 km single-tube dual-track tunnel, finished section 60 sq m, to be built in marly limestone in urban area, using a roadheader. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=135276-2005, OJ S 136, or contact Red Ferroviaria Vasca, Bilbao, fax +34 944329189. E-mail jortega@ets-rfv.es 33-34/05.Open call for tenders, deadline 20th February, 2006 for design of the dualling of the Loiola-Herrera section on the Lasarte-Hendaya rail line operated by Euskotren, in San Sebastian province. The new route of the Loiola-Herrera section will enable the existing 2.5 km single-track tunnel to carry freight traffic only, thereby separating freight and passenger traffic. The planned section is 2,701 m long, whereof 1,628 m in tunnel, a 480 m semi-underground station in Herrera, a 452 m stretch of open air and a 141 m concrete box. Work will commence at the end of 2006 or in early 2007 to end in early 2010. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=249375-2005, OJ S 252, or contact Red Ferroviaria Vasca, Bilbao, fax +34 944329189. E-mail jortega@ets-rfv.es 03/06.Typsa bagged a EUR781,500 contract to design the dualling of the Loiola-Herrera section on the Lasarte-Hendaya rail line operated by the Basque railway operator Eusko Tren. The 2,701 m-long section, whereof 1,628 m in tunnel, includes a 480 m semi-underground station in Herrera, a 452 m stretch of open air and a 141 m concrete box. Visit www.typsa.es 26/06.Periodic notice, deadline unspecified, being a call for bids aiming at reducing time limits for the receipt of tenders, for 2.7 kilometres of double tracking between Loiola and Herrera stations, including a 1.6 km tunnel, redevelopment of Herrera station, a new station in Intxaurrondo and refurbishment of the existing tunnel to be used by freight trains only. Read E-News Weekly 37/2007. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=36593-2008, OJ S 27, or contact ETS-RFV, Bilbao, fax +34 946572601. E-mail ets@ets-rfv.es 07/08.Open invitation to tender, deadline 3rd July, 2008 for construction of a 2.7 km double tracking between Loiola and Herrera stations, including a 1,628 m tunnel, a 141 m in situ concrete box, the Herrera partially underground station and the Intxaurrondo underground station. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=127126-2008, OJ S 93, and http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=151991-2008, OJ S 114, or contact ETS-RFV, Bilbao, fax +34 946572601. E-mail ets@ets-rfv.es 21/08.Open invitation to tender, deadline 4th August, 2008 for construction management for the 2.7 km Loiola-Herrera track dualling, including a 1,628 m tunnel, a 141 m in situ concrete box, the Herrera partially underground station and the Intxaurrondo underground station. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=151901-2008, OJ S 113, or contact ETS-RFV, Bilbao, fax +34 946572601. E-mail ets@ets-rfv.es 25/08.Ví­as y Construcciones will partner with Altuna y Uria to construct a 2.7 km double tracking between Loiola and Herrera stations, including a 1,628 m tunnel, a 141 m in situ concrete box, the Herrera partially underground station and the Intxaurrondo underground station. Their contract is worth EUR51.8 million. Visit www.vias.es 42/08.



Permalink


Open invitation to tender, deadline 01/03/2024, for the Amara freight bypass in Donostia-San Sebastián. The project involves the construction of a new railway branch line to connect the Lugaritz and Anoeta freight stations once the Lugaritz-Easo bypass is in service, seeking to make the best use of the Aiete tunnel, which will remain unused except for freight. The 450 m projected new line will be developed entirely in tunnel and cut-and-cover tunnel and it will connect the Aiete tunnel with the Morlans tunnel, thus allowing goods trains to run in the Pasaia direction. Click here for bid/tender documents and here where tenders must be sent. Contact Euskal Trenbide Sarea - ETS - Euskal Trenbide Sarea, Bilbao, tel +34 946572600. E-mail kontratazioa@ets-rfv.eus.  Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=038062-2024. 04/24. 

 




Permalink

Spain, Barcelona - es/48

Metro

    Preannouncement of invitation to tender for design and construction of metro line 9 from Sagrera to Can Peixauet, Can Zam and Gorg. Contact GISA, fax +34 9 34 300124. Monitor http://ted.eur-op.eu.int 14/01. Three open invitations to tender, deadline 17th July, 2001, for 10 km-long x 11.9 m-diameter section of line 9 with thirteen 35-65 m-deep stations. Y-shaped line will run from Gorg and Can Zam to Bon Pastor and on to Sagrera Meridiana in mixed ground requiring hardrock TBM and EPB. Commencement early-2002 for completion end-2004. Further 30 km with 30 stations in design to be tendered as three sections. Contact fax +34 934 300124 or visit www.gisa.es 27/01. Two contracts awarded by the Catalan government for Line 9 to connect Gorg in Badalona and Can Zam in Santa Coloma, both forming the upper branches of a Y, with Parc Logí­stic. First section is open cut. Pta48.6 billion second section including subsections from Bon Pastor to Gorg and from Parc Logí­stic up to Zona Universitaria secured by Dragados, Necso, Comsa, ACS, and Sorigué. EPB shield to be used with launch shafts in Zona Universitaria and Gorg. Time frame of 54 months. Pta64.4 billion third section including subsections from Can Zam to Bon Pastor and from Zona Universitaria to Sagrera scooped by FCC, OHL, Ferrovial-Agromí¡n and Copisa. EPB TBM. Time frame of 64 months. All tunnels 10.9 m-diameter with two levels for both directions. Excavation to start in 2002 at a depth of 35-60 m. Three machines needed altogether. Section between Can Zam, Gorg and Sagrera to open in 2004. Sagrera-Parc Logí­stic stretch to open in 2006. Visit www.gencat.es and www.gisa.es 44/01. A jv of Riazu, Tec-Cuatro, and GPO Ingenierí­a has secured the work supervision for a 3 km section of Line 9 for €1.8 million. Visit www.gencat.es and www.gisa.es 51/01. Work supervision for the bulk of Line 9, including the bored tunnels, awarded to Paymacotas and Nicola Della Valle for €16.4 million. Visit www.paymacotas.com and www.nicdv.it 03/02. Open call for bids, deadline 25th February, 2003 for construction of the infrastructure and stations for Line 9, section 1 Airport-Parc Logí­stic, subsection Llobregat-Parc Logí­stic, and section 2 Parc Logí­stic-Zona Universitaria, subsection Parc Logí­stic-Fira. Includes the construction of stations Mercabarna, Parc Logí­stic and Fira de Barcelona, and one tunnel between river Llobregat and the Fira station. Tender value: €149.2 million. Visit http://ted.eur-op.eu.int/udl?request=Seek-Deliver&language=es&docid=001119-2003, OJ S 2, or contact GISA, Barcelona, fax +34 934300124. E-mail dlh@gisa.es. 02/03. The 44 km-long line 9 will be the longest in Europe connecting Badalona and Santa Coloma de Gramanet with the port and the airport, running through the exhibition and fair area. It is also the first metro line in the world for trainsets in each direction in a single two-level tunnel. The project requires to invest approximately €2 billion. Construction will not be finished before mid-2007. 02/03. Open call for bids, deadline 25th February, 2003 for structural work inside the section 2 tunnel, track laying and catenary installation. Tender value: €71.9 million. Visit http://ted.eur-op.eu.int/udl?request=Seek-Deliver&language=es&docid=001115-2003, OJ S 2, or contact GISA, Barcelona, fax +34 934300124. E-mail dlh@gisa.es. 02/03.Open call for bids, deadline 25th February, 2003 for construction of the tunnel on section 2 Parc Logí­stic-Zona Universitaria, subsection Bifurcacií³, section Bifurcacií³-Fira. Tender value: €93.7 million. Visit http://ted.eur-op.eu.int/udl?request=Seek-Deliver&language=es&docid=001107-2003, OJ S 2, or contact GISA, Barcelona, fax +34 934300124. E-mail dlh@gisa.es. 02/03.Open call for bids, deadline 25th February, 2003 for construction of the stations on section 2 Parc Logí­stic-Zona Universitaria, subsection Zona Universitaria-Bifurcacií³, and subsection Bifurcacií³-Start shaft in Motors street. Tender values: €63.4 million and €57.8 million. Visit http://ted.eur-op.eu.int/udl?request=Seek-Deliver&language=es&docid=001117-2003 and http://ted.eur-op.eu.int/udl?request=Seek-Deliver&language=es&docid=001118-2003, OJ S 2, or contact GISA, Barcelona, fax +34 934300124. E-mail dlh@gisa.es. 02/03.Open call for bids, deadline 25th February, 2003 for construction of infrastructure, stations, workshops and depots on section 2 Parc Logí­stic-Zona Universitaria, subsection Start shaft in Motors street-Zona Franca Zal. Tender value: €154.9 million. Visit http://ted.eur-op.eu.int/udl?request=Seek-Deliver&language=es&docid=001108-2003, OJ S 2, or contact GISA, Barcelona, fax +34 934300124. E-mail dlh@gisa.es. 02/03.Open call for bids, deadline 25th February, 2003 for structural works inside section 3 tunnel, track laying and catenary installation. Tender value: €59.1 million. Visit http://ted.eur-op.eu.int/udl?request=Seek-Deliver&language=es&docid=001109-2003, OJ S 2, or contact GISA, Barcelona, fax +34 934300124. E-mail dlh@gisa.es. 02/03.Open call for bids, deadline 25th February, 2003 for construction of stations Zona Universitaria, Campus nord, Manuel Girona and ventilation shafts, section 3 Zona Universitaria-Sagrera Meridiana. Tender value: €41.7 million. Visit http://ted.eur-op.eu.int/udl?request=Seek-Deliver&language=es&docid=001111-2003, OJ S 2, or contact GISA, Barcelona, fax +34 934300124. E-mail dlh@gisa.es. 02/03.Open call for bids, deadline 25th February, 2003 for construction of stations Prat de la Riba, Sarrií , Mandri and ventilation shafts, section 3 Zona Universitaria-Sagrera Meridiana. Tender value: €49.7 million. Visit http://ted.eur-op.eu.int/udl?request=Seek-Deliver&language=es&docid=001112-2003, OJ S 2, or contact GISA, Barcelona, fax +34 934300124. E-mail dlh@gisa.es. 02/03.Open call for bids, deadline 25th February, 2003 for construction of stations Putxet, Lesseps, Muntanya and ventilation shafts, section 3 Zona Universitaria-Sagrera Meridiana. Tender value: €39.3 million. Visit http://ted.eur-op.eu.int/udl?request=Seek-Deliver&language=es&docid=001116-2003, OJ S 2, or contact GISA, Barcelona, fax +34 934300124. E-mail dlh@gisa.es. 02/03.Open call for bids, deadline 25th February, 2003 for construction of stations Sanllehy, Guinardí³, Maragall and ventilation shafts, section 3 Zona Universitaria-Sagrera Meridiana. Tender value: €42.3 million. Visit http://ted.eur-op.eu.int/udl?request=Seek-Deliver&language=es&docid=001120-2003, OJ S 2, or contact GISA, Barcelona, fax +34 934300124. E-mail dlh@gisa.es. 02/03.Open call for bids, deadline 25th February, 2003 for installation of escalators and lifts in the 40 stations. Tender value: €52.9 million and €58.8 million. Visit http://ted.eur-op.eu.int/udl?request=Seek-Deliver&language=es&docid=001110-2003 and http://ted.eur-op.eu.int/udl?request=Seek-Deliver&language=es&docid=001121-2003, OJ S 2, or contact GISA, Barcelona, fax +34 934300124. E-mail dlh@gisa.es. 02/03.Open call for bids, deadline 25th February, 2003 for installation of ticketing equipment. Tender value: €28.3 million. Visit http://ted.eur-op.eu.int/udl?request=Seek-Deliver&language=es&docid=001113-2003, OJ S 2, or contact GISA, Barcelona, fax +34 934300124. E-mail dlh@gisa.es. 02/03.The total budget of these tenders amounts to €963 million. The administration will pay for the works, interests included, as the construction companies complete and commission the sections.To date, section 4 has been fully awarded (Can Zam and Gorg branches to Sagrera-Meridiana) and work is underway as well as the tunnels on almost all section 2 and all section 3. It is foreseen that section 4 will be operational in 2004. Open call for bids, deadline 25th February, 2003, for construction of the infrastructure and stations of line 9, section 1 Airport-Parc Logí­stic, subsection km 4+500 to Llobregat. Budget: €197.6 million. Visit http://ted.eur-op.eu.int/udl?request=Seek-Deliver&language=en&docid=002625-2003, OJ S 4, or contact GISA, Barcelona, fax +34 934300124. 03/03.Open call for bids, deadline 25th March, 2003, for design and construction of the telecom systems for line 9. Traction substations, power substations and energy distribution system. Budget: €161.2 million. Visit http://ted.eur-op.eu.int/udl?request=Seek-Deliver&language=en&docid=002632-2003, OJ S 4, or contact GISA, Barcelona, fax +34 934300124. 03/03. Open invitation to tender, deadline 11th April, 2003 for work supervision of Line 9, section 2 Parc Logí­stic-Zona Universití ria, subsection Bifurcacií³, stretch Bifurcacií³-Fira, and subsection Start shaft in Motors street-Zona Franca Zal. Tender value: €6 million. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=031751-2003, OJ S 37, or contact GISA, Barcelona, fax +34 934300124. E-mail dlh@gisa.es 10/03.Open invitation to tender, deadline 15th April, 2003 for work supervision of Line 9 for the ATC, signalling and Centralized Control Room as well as the platform edge doors (PEDs) system. Tender value: €3.2 million. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=035370-2003, OJ S 41, or contact GISA, Barcelona, fax +34 934300124. E-mail dlh@gisa.es 10/03.Open invitation to tender, deadline 15th April, 2003 for work supervision of Line 9, section 1 Airport-Parc Logí­stic, subsections Airport Terminal to km 4+500, km 4+500 to Llobregat and Llobregat to Parc Logí­stic, and section 2 Parc Logí­stic-Zona Universitaria, subsection Parc Logí­stic-Fira. Tender value: €10.5 million. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=035364-2003, OJ S 41, or contact GISA, Barcelona, fax +34 934300124. E-mail dlh@gisa.es 10/03.Open invitation to tender, deadline 15th April, 2003 for work supervision for the stations of Line 9, section 2 Parc Logí­stic-Zona Universitaria, subsections Zona Universitaria-Bifurcacií³ and Bifurcacií³-Start shaft in Motors street. Tender value: €4 million. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=035381-2003, OJ S 41, or contact GISA, Barcelona, fax +34 934300124. E-mail dlh@gisa.es 10/03.Open invitation to tender, deadline 15th April, 2003 for work supervision of Line 9 for telecom systems, traction substations, power substations and energy distribution system. Tender value: €3.5 million. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=035374-2003, OJ S 41, or contact GISA, Barcelona, fax +34 934300124. E-mail dlh@gisa.es 10/03.Open invitation to tender, deadline 15th April, 2003 for work supervision of Line 9 for the ticketing system, and installation of elevators and escalators. Tender value: €2.3 million. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=035371-2003, OJ S 41, or contact GISA, Barcelona, fax +34 934300124. E-mail dlh@gisa.es 10/03. Open invitation to tender, deadline 11th April, 2003 for work supervision of Line 9, section 2 Parc Logí­stic-Zona Universití ria, subsection Bifurcacií³, stretch Bifurcacií³-Fira, and subsection Start shaft in Motors street-Zona Franca Zal. Tender value: €6 million. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=031751-2003, OJ S 37, or contact GISA, Barcelona, fax +34 934300124. E-mail dlh@gisa.es 10/03.Open invitation to tender, deadline 15th April, 2003 for work supervision of Line 9 for the ATC, signalling and Centralized Control Room as well as the platform edge doors (PEDs) system. Tender value: €3.2 million. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=035370-2003, OJ S 41, or contact GISA, Barcelona, fax +34 934300124. E-mail dlh@gisa.es 10/03.Open invitation to tender, deadline 15th April, 2003 for work supervision of Line 9, section 1 Airport-Parc Logí­stic, subsections Airport Terminal to km 4+500, km 4+500 to Llobregat and Llobregat to Parc Logí­stic, and section 2 Parc Logí­stic-Zona Universitaria, subsection Parc Logí­stic-Fira. Tender value: €10.5 million. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=035364-2003, OJ S 41, or contact GISA, Barcelona, fax +34 934300124. E-mail dlh@gisa.es 10/03.Open invitation to tender, deadline 15th April, 2003 for work supervision for the stations of Line 9, section 2 Parc Logí­stic-Zona Universitaria, subsections Zona Universitaria-Bifurcacií³ and Bifurcacií³-Start shaft in Motors street. Tender value: €4 million. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=035381-2003, OJ S 41, or contact GISA, Barcelona, fax +34 934300124. E-mail dlh@gisa.es 10/03.Open invitation to tender, deadline 15th April, 2003 for work supervision of Line 9 for telecom systems, traction substations, power substations and energy distribution system. Tender value: €3.5 million. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=035374-2003, OJ S 41, or contact GISA, Barcelona, fax +34 934300124. E-mail dlh@gisa.es 10/03.Open invitation to tender, deadline 15th April, 2003 for work supervision of Line 9 for the ticketing system, and installation of elevators and escalators. Tender value: €2.3 million. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=035371-2003, OJ S 41, or contact GISA, Barcelona, fax +34 934300124. E-mail dlh@gisa.es 10/03. The construction of the tunnel on section 2 Parc Logí­stic-Zona Universitaria, subsection Bifurcacií³, section Bifurcacií³-Fira on Line 9 has been commissioned to FCC, Copisa and Comapa for €74.2 million. Visit www.gisa.es, www.fcc.es and www.copisa.com 22/03.Dragados, Copcisa, Construcciones Rubau and Comapa have been appointed to build the infrastructure, stations, workshops and depots on section 2 Parc Logí­stic-Zona Universitaria, subsection Start shaft in Motors street-Zona Franca Zal. Contract value: €128.9 million. Visit www.gisa.es, www.dragados.es and www.copcisa.com 22/03.Dragados, Necso, Comsa, ACS and Sorigué have scooped a €59 million contract for structural works inside the section 2 tunnel, track laying and catenary installation, section Start shaft in Motor street-Zona Universitaria. Visit www.gisa.es, www.dragados.es and www.necso.es 22/03.Copisa, FCC, Copcisa, OHL and Ferrovial-Agromí¡n have been awarded a €51 million contract for structural works inside section 3 tunnel, track laying and catenary installation on section Zona Universitaria-Sagrera Meridiana. Visit www.gisa.es, www.copisa.com and www.fcc.es 22/03.A JV of Dragados, Necso, Comsa and Sorigué has won for €124 million the construction of the infrastructure and stations, section 1 Airport-Parc Logí­stic, subsection Llobregat-Parc Logí­stic, and section 2 Parc Logí­stic-Zona Universitaria, subsection Parc Logí­stic-Fira. Includes the construction of stations Mercabarna, Parc Logí­stic and Fira de Barcelona, and one tunnel between river Llobregat and Fira station. Visit www.gisa.es, www.dragados.es and www.necso.es 22/03.The stations on section 2 Parc Logí­stic-Zona Universitaria, subsection Zona Universitaria-Bifurcacií³ will be built by Dragados, Necso and ACS at a cost of €54.7 million. Visit www.gisa.es, www.dragados.es and www.necso.es 22/03.The stations on section 2 Parc Logí­stic-Zona Universitaria, subsection Bifurcacií³-Start shaft in Motors street will be built by Scrinser, Comsa and Sorigué for €49.8 million. Visit www.gisa.es and www.comsa.es 22/03.Corsí¡n-Corviam will construct stations Zona Universitaria, Campus nord, Manuel Girona and the ventilation shafts on section 3 Zona Universitaria-Sagrera Meridiana. Contract value: €35.6 million. Visit www.gisa.es and www.corsan-corviam.es 22/03.Copcisa, FCC, Ferrovial-Agromí¡n, OHL and Copisa will build stations Prat de la Riba, Sarrií , Mandri and the ventilation shafts on section 3 Zona Universitaria-Sagrera Meridiana. Contract value: €42.3 million. Visit www.gisa.es, www.copcisa.com and www.fcc.es 22/03.Copcisa, FCC, Ferrovial-Agromí¡n, OHL and Copisa will also build stations Putxet, Lesseps, Muntanya and the ventilation shafts on section 3 Zona Universitaria-Sagrera Meridiana. Contract value: €33.6 million. Visit www.gisa.es, www.copcisa.com and www.fcc.es 22/03.Copcisa, FCC, Ferrovial-Agromí¡n, OHL and Copisa will finally build stations Sanllehy, Guinardí³, Maragall and the ventilation shafts on section 3 Zona Universitaria-Sagrera Meridiana. Contract value: €36 million. Visit www.gisa.es, www.copcisa.com and www.fcc.es 22/03.FCC, Ferrovial-Agromí¡n, OHL, Scrinser and Copisa will construct the infrastructure and stations on section 1 Airport-Parc Logí­stic, subsection km 4+500 to Llobregat. Contact value: €169 million. Visit www.gisa.es, www.fcc.es and www.ferrovial.es 22/03.Indra Sistemas and Sainco Trí¡fico have won a €22.9 million contract for the supply and installation of the ticketing equipment. Visit www.gisa.es, www.indra.es and www.saincotrafico.com 22/03.ThyssenKrupp Elevadores has won a €28.4 million contract for the supply and installation of escalators and another contract worth €32.3 million for the supply and installation of lifts in the 40 stations. Visit www.gisa.es and www.thyssenkrupp.com 22/03.A JV between Agelèctric, Elecnor, Emte, Instalaciones Inabensa and Isolux Wat has secured a €130.7 million design and equipment contract for line 9 including the telecom systems, the traction substations, the power substations and the energy distribution system. Visit www.elecnor.es, www.grupemte.com, www.inabensa.com and www.isolux.es. Work supervision goes to Auditorí­as e Ingenierí­as and Sener for €2.9 million. Visit www.sener.es 29/03.Typsa, Europrincipia and Idom have won a €3.26 million contract for work supervision for the stations on section 2 Parc Logí­stic-Zona Universitaria, subsections Zona Universitaria-Bifurcacií³ and Bifurcacií³-Start shaft in Motors street. Visit www.typsa.es and www.idom.es 29/03.GPO Ingenierí­a, Catalana d'Ingenyeria and Payma Cotas have won a €4.3 million contract for work supervision of stations Campus nord, Manuel Girona, Prat de la Riba, Sarrií , Mandri, Putxet, Lesseps, Muntanya and the associated ventilation shafts on section 3 Zona Universitaria-Sagrera Meridiana. Visit www.gpo.es and www.paymacotas.com 29/03.A JV between Payma Cotas, Riazu and Tec-Cuatro has pocketed a €8.5 million contract for work supervision of the infrastructure and stations on section 1 Airport-Parc Logí­stic, subsections Airport terminal to Km 4+500, Km 4+500 to Llobregat, Llobregat to Parc Logí­stic, and section 2 Parc Logí­stic-Zona Universitaria, subsection Parc Logí­stic-Fira. 29/03.A JV of AZM Ingenyers, SGS Tecnos, Ardanuy Ingenierí­a and Sener has gained a €1.8 million contract for work supervision of the ticketing system, elevators and escalators. Visit www.ardanuy.com and www.sgs.es 29/03.Sener has won a €2.6 million contract for work supervision for the ATC, signalling and Centralized Control Room as well as the platform edge doors (PEDs) system. 29/03.Open call for bids, deadline 9th February, 2004 for construction of section Airport-Parc Logí­stic, subsection Terminal station between runways-Km 4+500. Cut-and-cover method from Terminal station between runways to Km 1+250 and EPB TBM. The tunnel will accomodate two tracks and feature an outer diameter of 9.07 m and inner diameter of 8.43 m. Includes also three cut-and-cover stations. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=220683-2003, OJ S 248, or contact GISA, Barcelona, fax +34 934444488. Visit dlh@gisa.es 02/04.GISA has awarded the construction of subsection Terminal between runways-Km 4+500 of Line 9 between the airport and Parc Logistic which will connect the Mas Blau business park to the new airport terminal to a JV between FCC, Ferrovial-Agroman, Scrinser, OHL and Copisa. The contract is worth EUR139 million. Work will commence by two months and last 20 months. The section is 3,934 m in length, whereof 3,050 m in tunnel, with three stations temporarily known as Terminal entre pistas, Terminal actual and Mas Blau. The double-track tunnel features an outer diameter of 9.4 m and an inner diameter of 8.4 m. Visit www.fcc.es, www.ferrovial.com, www.ohl.es and www.copisa.com 14/04.Open call for bids, deadline 10th May, 2004 for construction of the Sagrera Meridiana interchange on Line 9. Tender value: EUR105.9 million. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=051109-2004, OJ S 60, or visit GISA, Barcelona, fax +34 934444488. E-mail dlh@gisa.es 16/04.It was initially planned to construct in open cut the subsection running from Sagrera-Meridiana to the exit shaft of the TBMs near the future high speed station in La Sagrera. Because of a planning clash between the construction of this subsection and the future high speed railway station, the project has been modified and will be TBM-driven. GISA has awarded the construction of this subsection, running from Onze de Setembre station to Sagrera-Meridiana to Dragados, Necso, Comsa, ACS and Sorigué for EUR89.8 million and a time frame to complete the job of 24 months. The contract also includes an extension to Line 4 from Santander to Sagrera TAV and Sagrera-Meridiana, with a 12 m-diameter tunnel and the new Line 4 station at Sagrera-Meridiana. The Sagrera TAV - Sagrera-Meridiana stretch of Line 4 will be used by Line 9 trains while the Onze de Setembre - Sagrera-Meridiana parallel section is used for spoil removal when work continues on Line 9 between Sagrera-Meridiana and Zona Universití ria. The new Line 4 section will be commissioned as Line 9 without being connected to La Pau, the current head of the line. Construction of both sections implies therefore that Lines 9 and 4 will run in parallel in separated tunnels between Sagrera TAV and Sagrera Meridiana. Sagrera-Meridiana will also be an interchange station between four metro lines (4, 9, 1 and 5) and the Renfe station. These companies are currently excavating the Gorg-Bon Pastor section by means of a 12.06 m-diameter Herrenknecht EPB shield. This machine has excavated over 1 km and recently passed Llefia station. The other EPB shield, 11.95 m in diameter, built by NFM Technologies launched from Can Zam on 20th June, 2003 is on schedule, having driven 1.7 km. The machine is between Singuerlin and Esglesia stations. Visit www.gisa.es, www.gencat.net, www.herrenknecht.com and www.nfm-technologies.com 16/04.Open call for bids, deadline 19th July, 2004 for work management of the Sagrera Meridiana interchange on Line 9 of the Barcelona metro. Tender budget: EUR3 million. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=086071-2004, OJ S 105, or contact GISA, Barcelona, fax +34 934444488. E-mail contractacio@gisa.es 25/04.Comsa, Scrinser and Isolux Wat will construct Sagrera Meridiana interchange on Line 9, for EUR75.1 million. Visit www.comsa.com 30/04.Idom, Europrincipia and Typsa have secured a EUR2.3 million contract for work management of the Sagrera Meridiana interchange on Line 9 of the Barcelona metro. Visit www.idom.es, www.europrincipia.es and www.typsa.com 45/04.Open call for tenders, deadline 2nd September, 2005 for quality control during construction of the infrastructure and stations on section 4t Bon Pastor-Can Zam and the tunnel on the Zona Universitaria-Sagrera Meridiana section and during the design of the infrastructure and station of the access to the railway triangle, as part of Line 9 of the Barcelona metro. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=133995-2005, OJ S 135, or contact GISA, Barcelona, fax +34 934444488. E-mail contractacio@gisa.es 29/05.Open call for bids, deadline 2nd September, 2005 for quality control during construction of the infrastructure, stations, workshops and depots on section 2 Parc Logistic-Zona Universitaria, subsection Start shaft in Motors street-Zona Franca Zal. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=134039-2005, OJ S 135, or contact GISA, Barcelona, fax +34 934444488. E-mail contractacio@gisa.es 35/05.Open call for bids, deadline 2nd September, 2005 for quality control during construction of section 2n Parc Logistic-Zona Universitaria, subsection Bifurcacion, section Bifurcacion-Fira. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=134038-2005, OJ S 135, or contact GISA, Barcelona, fax +34 934444488. E-mail contractacio@gisa.es 35/05.Open call for bids, deadline 2nd September, 2005 for quality control during construction of the infrastructure and stations on section 4t Bon Pastor-Gorg, of the tunnel on section Parc Logistic-Zona Universitaria and of the infrastructure and stations on subsection Sagrera-TBM shaft (end of section at Sagrera high speed rail-Bon Pastor). Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=134026-2005, OJ S 135, or contact GISA, Barcelona, fax +34 934444488. E-mail contractacio@gisa.es 35/05.Open call for tenders, deadline 12th December, 2005 for design of the modified project for Line 9, stations on the subsection Zona Universitaria-Bifurcacion (Gornal, Torrassa, Collblanc, Campus Sud and Zona Universitaria). Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=201911-2005, OJ S 204, or contact GISA, Barcelona, fax +34 934444488. E-mail contractacio@gisa.es 45/05.Open call for tenders, deadline 12th December, 2005 for design of the modified project for Line 9, subsection Llobregat-Fira. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=201909-2005, OJ S 204, or contact GISA, Barcelona, fax +34 934444488. E-mail contractacio@gisa.es 45/05.Open call for tenders, deadline 12th December, 2005 for design of the modified project for Line 9, subsection Parc Logistic-Zona Universitaria. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=202045-2005, OJ S 204, or contact GISA, Barcelona, fax +34 934444488. E-mail contractacio@gisa.es 45/05.Open call for tenders, deadline 12th December, 2005 for design of the modified project for Line 9, subsection TBM shaft-Sagrera Meridiana. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=201956-2005, OJ S 204, or contact GISA, Barcelona, fax +34 934444488. E-mail contractacio@gisa.es 45/05.Payma Cotas won a EUR530,000 contract to undertake the quality control during construction of the infrastructure and stations on section 4t Bon Pastor-Can Zam and the tunnel on the Zona Universitaria-Sagrera Meridiana section and during the design of the infrastructure and station of the access to the railway triangle, as part of Line 9 of the Barcelona metro. Visit www.paymacotas.comEptisa secured a EUR590,000 contract to undertake the quality control during construction of the infrastructure and stations on section 4t Bon Pastor-Gorg, of the tunnel on section Parc Logistic-Zona Universitaria and of the infrastructure and stations on subsection Sagrera-TBM shaft (end of section at Sagrera high speed rail-Bon Pastor). Visit www.eptisa.es 47/05.Eptisa also secured a EUR303,300 contract to undertake the quality control during construction of section 2n Parc Logistic-Zona Universitaria, subsection Bifurcacion, section Bifurcacion-Fira. Visit www.eptisa.es 47/05.LGAI Technological Center and Applus Construccií³n Técnica pocketed a EUR887,300 contract to undertake the quality control during construction of the infrastructure, stations, workshops and depots on section 2 Parc Logistic-Zona Universitaria, subsection Start shaft in Motors street-Zona Franca Zal. Visit www.lgai.es and www.appluscorp.com 47/05.Open call for bids, deadline 10th April, 2006 for design of the airport loop on section 1 Airport-Logistic Park, between Mas Blau station (not included in the contract) at Km 0.750 of the original project and the terminal station between the runways (Km 3.595 in the original project). The alignment change to the project originally designed in 2002 is motivated by the need to serve the new airport city under development northeast of the airport. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=040175-2006, OJ S 37, or contact GISA, Barcelona, fax +34 934444488. E-mail contractacio@gisa.es 09/06.Auding secured a EUR304,000 contact to design the modified project for Line 9, subsection TBM shaft-Sagrera Meridiana. Visit www.auding.com 12/06.Tec-Cuatro, Intraesa and Geocontrol received three contracts to design the modified project for Line 9. The first contract, worth EUR210,800, is to design subsection Parc Logistic-Zona Universitaria. The second contract is to design the stations on subsection Zona Universitaria-Bifurcacion (Gornal, Torrassa, Collblanc, Campus Sud and Zona Universitaria). It is worth EUR370,700. The third contract is to design subsection Llobregat-Fira. It is worth EUR210,340. Visit www.tec-cuatro.es, www.intraesa.com and www.geocontrol.es 12/06.Open call for tenders, deadline 2nd May, 2006 for conceptual design of section 3r Zona Universitaria-Sagrera meridiana on Line 9 of the Barcelona metro. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=054507-2006, OJ S 52, or contact GISA, Barcelona, fax +34 934444488. E-mail contractacio@gisa.es 13/06.The call for tenders for the conceptual design of section 3r Zona Universitaria-Sagrera meridiana on Line 9 of the Barcelona metro has been cancelled. Click es/48. 19/06.Open call for tenders, deadline 29th May, 2006 for general supervision of safety and health during construction of Line 9 of the Barcelona metro. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=088116-2006, OJ S 83, or contact GISA, Barcelona, fax +34 93 4444488. E-mail contractacio@gisa.es 20/06.Peyco and Inpasa secured a EUR563,500 contract to design the airport loop (tunnel, stations and ventilation shaft) on section 1 Airport-Logistic Park, between Mas Blau station (not included in the contract) at chainage 0.750 of the original project and the terminal station between the runways (chainage 3.595 in the original project). Visit www.peyco.es 23/06.Darzal Consultoria y Prevencion received a EUR327,600 contract for general supervision of safety and health during construction of Line 9 of the Barcelona metro. 29/06.Open call for tenders, deadline 15th September, 2006 for quality control on Line 9 on the Barcelona metro, section 1 Airport- Parque Logistico, subsection Terminal between runways-Ch 4,500 and Ch 4,500-Llobregat. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=158878-2006, OJ S 147, or contact GISA, Barcelona, fax +34 934444488. E-mail contractacio@gisa.es 33-34/06.Open call for tenders, deadline 15th September, 2006 for quality control on Line 9 on the Barcelona metro, section 2 Parque Logistico-Zona Universitaria, subsection Parque Logistico-Fira, and section 1 Airport-Parque Logistico, subsection Llobregat-Parque Logistico. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=158874-2006, OJ S 147, or contact GISA, Barcelona, fax +34 934444488. E-mail contractacio@gisa.es 33-34/06.Open call for tenders, deadline 15th September, 2006 for quality control on Line 9 on the Barcelona metro, section 2 Parque Logistico-Zona Universitaria, subsection Bifurcacion-Launch shaft in Motors Street. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=158866-2006, OJ S 147, or contact GISA, Barcelona, fax +34 934444488. E-mail contractacio@gisa.es 33-34/06.Open call for tenders, deadline 18th September, 2006 for quality control of studies and projects for Line 9 of the Barcelona metro. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=es&docid=161116-2006, OJ S 149, or contact GISA, Barcelona, fax +34 934444488. E-mail contractacio@gisa.es 33-34/06.Open call for tenders, deadline 26th September, 2006 for conceptual design of section 3, Zona Universitaria-Sagrera Meridiana (tunnel and stations) on Line 9 on the Barcelona metro. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=169694-2006, OJ S 157, or contact GISA, Barcelona, fax +34 934444488. E-mail contractacio@gisa.es 35/06.Intemac received a EUR540,300 contract for quality control on Line 9 on the Barcelona metro, section 2 Parque Logistico-Zona Universitaria, subsection Parque Logistico-Fira, and section 1 Airport-Parque Logistico, subsection Llobregat-Parque Logistico. Visit www.intemac.es 46/06.Payma Cotas won a EUR260,800 contract for quality control on Line 9 of the Barcelona metro, section 2 Parque Logistico-Zona Universitaria, subsection Bifurcacion-Launch shaft in Motors Street. Visit www.paymacotas.com 46/06.LGAI Technological Center secured a EUR835,300 contract for quality control on Line 9 on the Barcelona metro, section 1 Airport-Parque Logistico, subsections Terminal between runways-Ch. 4+500 and Ch. 4+500-Llobregat, and Fira station on section 2. Visit www.lgai.es 46/06.Typsa has bagged a EUR1.2 million contract for quality control of studies and projects for Line 9 of the Barcelona metro. Visit www.typsa.es 46/06.Open call for tenders, deadline 2nd January, 2007 for quality control during construction of the Zona Universitaria-Bifurcacion subsection on section 2 Parc Logistic-Zona Universitaria on Line 9. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=232019-2006, OJ S 216, or contact GISA, Barcelona, fax +34 934444488. E-mail cpublic@mfom.es 50/06.Payma Cotas received a EUR290,000 contract to control quality during construction of the Zona Universitaria-Bifurcacion subsection on section 2 Parc Logistic-Zona Universitaria on Line 9. Visit www.paymacotas.com 08/07.Open invitation to tender, deadline 20th May, 2008 for safety and health coordination for Line 9 of the Barcelona metro related to subsection Bifurcacií³n-Fira, in particular ground improvement; subsection Entry shaft in Motors Street-Zona Franca Zal (infrastructure, stations, workshops and rolling stock depot); subsection Zona Universitaria-Bifurcacií³n (stations); Torrassa interchange station; subsection Bifurcacií³n-Entry shaft in Motors Street and its stations; subsection Entry shaft in Motors Street-Zona Universitaria (complementary interior fit-out, tracks and catenaries as well as ground improvement measurements); and section Parc Logistic-Zona Universitaria (tunnel). Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=86772-2008, OJ S 64, or contact GISA, Barcelona, fax +34 934444488. E-mail correu@gisa.es 15/08.Open invitation to tender, deadline 2nd June, 2008 for safety and health coordination for Line 9 of the Barcelona metro related to the infrastructure, stations and installations of several sections. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=98894-2008, OJ S 73, or contact GISA, Barcelona, fax +34 934444488. E-mail correu@gisa.es 17/08.Open invitation to tender, deadline 9th June, 2008 for design for stations Zona Universitaria, Campus Norte, Manuel Girona and ventilation shafts, as part of the revised section 3 Zona Universitaria-Sagrera Meridiana of Line 9 of the Barcelona metro. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=104396-2008, OJ S 77, or contact GISA, Barcelona, fax +34 934444488. E-mail correu@gisa.es 18/08.Open invitation to tender, deadline 16th July, 2008 for work control and construction supervision of the New airport terminal-Parc Logistic section 1r. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=136952-2008, OJ S 102, or contact GISA, Barcelona, fax +34 934444488. E-mail esm@gisa.cat 23/08.Open invitation to tender, deadline 16th July, 2008 for work control and construction supervision of the Parc Logistic-Bifurcation shaft and Zona Franca entry shaft-Zona Universitaria section 2n. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=136951-2008, OJ S 102, or contact GISA, Barcelona, fax +34 934444488. E-mail esm@gisa.cat 23/08.Open invitation to tender, deadline 16th July, 2008 for work control and construction supervision of the Zona Universitaria-Sagrera Meridiana section 3r and section 4t. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=136950-2008, OJ S 102, or contact GISA, Barcelona, fax +34 934444488. E-mail esm@gisa.cat 23/08.Cygsa secured a EUR565,100 safety and health coordination contract for Line 9 of the Barcelona metro related to subsection Bifurcacií³n-Fira, in particular ground improvement; subsection Entry shaft in Motors Street-Zona Franca Zal (infrastructure, stations, workshops and rolling stock depot); subsection Zona Universitaria-Bifurcacií³n (stations); Torrassa interchange station; subsection Bifurcacií³n-Entry shaft in Motors Street and its stations; subsection Entry shaft in Motors Street-Zona Universitaria (complementary interior fit-out, tracks and catenaries as well as ground improvement measurements); and section Parc Logistic-Zona Universitaria (tunnel). Visit www.cygsa.com 30/08.Payma Cotas secured a EUR468,600 safety and health coordination contract for Line 9 of the Barcelona metro related to the infrastructure, stations and installations of several sections. Visit www.paymacotas.net 30/08.Auding received a EUR1.2 million contract to design the Zona Universitaria, Campus Norte and Manuel Girona stations and ventilation shafts, as part of the revised section 3 Zona Universitaria-Sagrera Meridiana of Line 9 of the Barcelona metro. Visit www.auding.com 36/08.Prior information notice for execution of construction work at Pozo Campus Norte on Barcelona metro line 9, value EUR6 million. Contract period 14 months commencing February, 2009. http://ted.europa.eu/udl?request=Seek-Deliver&language=es&docid=267741-2008 OJ S 202 Award procedures start 10.12.2008. Contact Gestio d'Infraestructures, tel +34 9 34 44 44 44, e-mail esm@gisa.cat 43/08.ATI, a consortium of OHL, FCC Construction and Copisa, has been awarded the EUR1 billion concession for construction, maintenance and management of section 1 of line 9 of Barcelona Metro involving 13 stations and 17 km of line serving Prat airport, Llobregat hospital and the terminus at Amadeu Torner station. Line 9 will be the longest metro line in Europe at 46.6 km. Visit www.ohl.es, www.fcc.es, and www.copisa.com. 48/08.



Permalink

Barcelona - es/48MetroLine 9JV Linia 9 secured the EUR12.5 million contract for complementary project no 3, section 2 Parc Logí­stic-Zona Universitaria, subsection Bifurcacií³-Fira on Line 9. Code TM-00509.5A-C3. Contact GISA, Barcelona, fax +34 934444488, e-mail dlh@gisa.cat. http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=127688-2009. 21/09.



Permalink

JV Cerdí  (Scrinser, Comsa, Sorigué) secured the EUR 9.4 million contract for construction of section 2n, subsection fork-access shaft calle Motors, for complementary project n. 2 of line 9 of Barcelona Metro. Contract duration 13 months, code TM-00509.5D-C2. Contact GISA, Barcelona, tel +34 9344444-44, fax -88, e-mail dllobet@gisa.cat. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=304564-2009. 47/09.



Permalink

JV Gorg secured the EUR10.3 million contract, VAT not included, for complementary project n.1, section 2 Parc Logí­stic-Zona Universitaria, subsection Bifurcacio-Fira on Line 9; internal structure complements and tunnel 2 catenaria, section Pozo C/Motors-Zona Universití ria; TBM and shaft adaptation. Contract duration 13.5 months. Bid code TM-00509.5E-C1. Contact GISA, Barcelona, tel +34 9344444-44, fax -88, e-mail dllobet@gisa.cat. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=129638-2010. 20/10.



Permalink

Open invitation to tender, deadline 31.05.2010, for consultative engineering and construction services for Metro Line 9 in Barcelona, section 3, Zona Universitaria-Sagrera Meridiana: Muntanya Station, shaft enclosure, hall and connection tunnels. Contract duration four months, value EUR344,827.59 excluding VAT. Contact GISA, attn Sigra Elena Sole Minguell, Barcelona, tel +34 9344444-44, fax -88, e-mail: esole@gisa.cat. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=103718-2010.Bid Code TM-00509.4C-BIS.2. 20/10.Open invitation to tender, deadline 31.05.2010, for consultative engineering and construction services for Metro Line 9 in Barcelona, section 3, Zona Universitaria-Sagrera Meridiana: Putxet, Lesseps and Muntanya stations, inner structures and urbanization. Contract value EUR271,551.72 excluding VAT, duration six months. Contact GISA, attn Sigra Elena Sole Minguell, Barcelona, tel +34 9344444-44, fax -88, e-mail: esole@gisa.cat. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=103719-2010. Bid code: TM-00509.4C-BIS.1. 20/10.Open invitation to tender, deadline 31.05.2010, for consultative engineering and construction services for Metro Line 9 in Barcelona, section 3, Zona Universitaria-Sagrera Meridiana: Prat de la Riba station, shaft enclosure, hall and connection tunnels.Contract value EUR362,068.96 excluding VAT, duration six months. Contact GISA, attn Sigra Elena Sole Minguell, Barcelona, tel +34 9344444-44, fax -88, e-mail: esole@gisa.cat. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=103720-2010. Bid code: TM-00509.4B-BIS.2. 20/10.Open invitation to tender, deadline 31.05.2010, for consultative engineering and construction services for Metro Line 9 in Barcelona, section 3, Zona Universitaria-Sagrera Meridiana: Prat de la Riba, Sarria and Mandri stations, inner structures and urbanization. Contract value EUR219,827.59 excluding VAT, duration six months. Contact GISA, attn Sigra Elena Sole Minguell, Barcelona, tel +34 9344444-44, fax -88, e-mail: esole@gisa.cat. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=103721-2010. Bid code Codice gara: TM-00509.4B-BIS.1. 20/10.



Permalink

Open invitation to tender, deadline 16.06.2010, for the supervision of works during construction of Metro Line 9 in Barcelona, section 3, Zona Universitaria-Sagrera Meridiana: inner structures complements and tunnel 3 catenary. Contract duration 30 months, value EUR1,988,888.89 excluding VAT. Contact GISA, attn Sigra Elena Sole Minguell, Barcelona, tel +34 9344444-44, fax -88, e-mail esole@gisa.cat. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=121505-2010. Bid code: TM-00509.4E. 20/10.Open invitation to tender, deadline 16.06.2010, for Baix Llobregat Intermodal Centre construction at Prat de Llobregat. Value contract: EUR68,854,707.65 excluding VAT, duration 34 months. Contact GISA, attn Sigra Elena Sole Minguell, Barcelona, tel +34 9344444-44, fax -88, e-mail esole@gisa.cat. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=136349-2010. Bid code: TM-00509.6A2-C1. 20/10.



Permalink

JV Gorg secured the EUR10.3 million contract, VAT not included, for complementary project n.1, section 2 Parc Logí­stic-Zona Universitaria, subsection Bifurcacio-Fira on Line 9; internal structure complements and tunnel 2 catenary, section Pozo C/Motors-Zona Universitaria; TBM and shaft adaptation. Contract duration 13.5 months. Bid code TM-00509.5E-C1. Contact GISA, Barcelona, tel +34 9344444-44, fax -88, e-mail dllobet@gisa.cat. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=129638-2010. 20/10.



Permalink

The JV Comsa, SA & Dragados, SA & FCC Construccion, SA secured the EUR59.08 million construction contract, VAT not included, for Baix Llobregat Intermodal Centre at Prat de Llobregat. Contact GISA, Barcelona, tel +34 9344444-44, fax -88, e-mail dllobet@gisa.cat.Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=388662-2010. Bid code: TM-00509.6A2-C1. 01/11.



Permalink

Open invitation to tender, deadline 03.06.2013, for high-voltage electricity supply on Line 9 of the Barcelona metro, value EUR3.99 million, excluding VAT. Duration contract 12 months after award. Contact Infraestructures Ferroviaries de Catalunya, att.n Asun Aspas Blasco, Barcelona, tel +34 934444444, fax +34 934444488, e-mail maaspas@infraestructures.cat. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=124234-2013. 16/13.



Permalink


Open invitation to tender, deadline 08/09/2021, to provide technical assistance for auscultation (sound tests) of the works of the construction project of metro Line 9 in Barcelona to enable tunnel and stations completion.

For tender documents, please click here. Value of the contract is EUR5.50 million, excluding VAT. Duration of the contract will be 90 months. Contact Infraestructures de la Generalitat de Catalunya, attn Xavier Fernandez Urban, Barcelona, tel +34 934444444, fax +34 934444488, email xfernandez@infraestructures.cat. For further on the TED tender, please click here and here. Ref.n. ATDO. TM-00509.AU. 31/21. 

 




Permalink


Open invitation to tender, deadline 10/01/2022, for environmental technical assistance for tunnel works and additional works in the Zona Universitària - Sagrera Meridiana section of Metro Line 9 in Barcelona. For tender documents please click here. The value of the contract is EUR 288,413.60, excluding VAT. Duration of the contract will be 40 months. Contact Infraestructures de la Generalitat de Catalunya SAU, att.ne Xavier Fernandez Urban, Barcelona, tel +34 934444444, fax +34 934444488, email xfernandez@infraestructures.cat. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=624581-2021. Ref.n. ATAM. TM-00509.4F. 49/21.

 



Spain-Barcelona: Environmental engineering consultancy services

2021/S 237-624581

Contract notice

Services

Legal Basis:

Directive 2014/24/EU

Section I: Contracting authority

I.1)Name and addresses

Official name: Infraestructures de la Generalitat de Catalunya, SAU
National registration number: A-59.377.135
Postal address: Calle dels Vergós, 36-42
Town: Barcelona
NUTS code: ES511 Barcelona
Postal code: 08017
Country: Spain
Contact person: Xavier Fernández Urbán
E-mail: xfernandez@infraestructures.cat
Telephone: +34 934444444
Fax: +34 934444488
Internet address(es):
Main address: http://infraestructures.gencat.cat/
Address of the buyer profile: https://contractaciopublica.gencat.cat/perfil/Infraestructures

I.3)Communication

The procurement documents are available for unrestricted and full direct access, free of charge, at: https://contractaciopublica.gencat.cat/ecofin_pscp/AppJava/perfil/Infraestructures

Additional information can be obtained from the abovementioned address

Tenders or requests to participate must be submitted to the abovementioned address

I.4)Type of the contracting authority

Regional or local agency/office

I.5)Main activity

General public services

Section II: Object

II.1)Scope of the procurement

II.1.1)Title:

Contrato de servicios asistencia técnica ambiental conjunta de las obras de túnel y de las obras adicionales Zona Universitària - Sagrera Meridiana de la línea 9 metro Barcelona. Clave: TM-00509. 4F

Reference number: ATAM. TM-00509.4F

II.1.2)Main CPV code

71313000 Environmental engineering consultancy services

II.1.3)Type of contract

Services

II.1.4)Short description:

Contrato de servicios para la asistencia técnica ambiental conjunta de las obras de Ejecución de las obras de túnel y de las obras adicionales del tramo Zona Universitària - Sagrera Meridiana de la línea 9 de Metro de Barcelona. Claves: TM-00509.4F1 y TM-00509.4F2 y modificados. Clave: TM-00509.4F

II.1.5)Estimated total value

Value excluding VAT: 288 413.60 EUR

II.1.6)Information about lots

This contract is divided into lots: no

II.2)Description

II.2.3)Place of performance

NUTS code: ES511 Barcelona

Main site or place of performance:

Barcelonès

II.2.4)Description of the procurement:

Consultar la documentación técnica asociada a la licitación.

II.2.5)Award criteria

Price is not the only award criterion and all criteria are stated only in the procurement documents

II.2.6)Estimated value

Value excluding VAT: 288 413.60 EUR

II.2.7)Duration of the contract, framework agreement or dynamic purchasing system

Duration in days: 40

This contract is subject to renewal: no

II.2.10)Information about variants

Variants will be accepted: no

II.2.11)Information about options

Options: no

II.2.13)Information about European Union funds

The procurement is related to a project and/or programme financed by European Union funds: no

II.2.14)Additional information

Section III: Legal, economic, financial and technical information

III.1)Conditions for participation

III.1.2)Economic and financial standing

Selection criteria as stated in the procurement documents

III.1.3)Technical and professional ability

Selection criteria as stated in the procurement documents

III.2)Conditions related to the contract

III.2.2)Contract performance conditions:

Las condiciones de ejecución son las que se indican en el Pliego de Cláusulas Administrativas de la licitación.

Section IV: Procedure

IV.1)Description

IV.1.1)Type of procedure

Open procedure

IV.1.3)Information about a framework agreement or a dynamic purchasing system

IV.1.8)Information about the Government Procurement Agreement (GPA)

The procurement is covered by the Government Procurement Agreement: yes

IV.2)Administrative information

IV.2.2)Time limit for receipt of tenders or requests to participate

Date: 10/01/2022

Local time: 13:00

IV.2.3)Estimated date of dispatch of invitations to tender or to participate to selected candidates

IV.2.4)Languages in which tenders or requests to participate may be submitted:

Catalan, Spanish

IV.2.6)Minimum time frame during which the tenderer must maintain the tender

Tender must be valid until: 25/05/2022

IV.2.7)Conditions for opening of tenders

Date: 15/02/2022

Local time: 10:05

Place:

Reunión interna.

Information about authorised persons and opening procedure:

Reunión interna.

Section VI: Complementary information

VI.1)Information about recurrence

This is a recurrent procurement: no

VI.2)Information about electronic workflows

Electronic ordering will be used

Electronic invoicing will be accepted

VI.3)Additional information:

La presentación se realizará electrónicamente mediante la aplicación de «Sobre Digital», accesible en el espacio virtual de esta licitación, en la dirección web (http://contractaciopublica.gencat.cat/perfil/Infraestructures&gt).

La apertura del sobre núm. 2 (propuesta técnica) se realizará de manera interna a las 12:05 horas del día 25 de enero de 2022.

La apertura del sobre núm. 3 (propuesta económica) se realizará de manera interna a las 10:05 horas del día 15 de febrero de 2022.

VI.4)Procedures for review

VI.4.1)Review body

Official name: Tribunal Català de Contractes del Sector Públic
Postal address: Carrer del Foc, 57
Town: Barcelona
Postal code: 08038
Country: Spain
Telephone: +34 93316200

VI.4.3)Review procedure

Precise information on deadline(s) for review procedures:

Contra este acuerdo se puede interponer recurso especial en materia de contratación, de conformidad con lo que establece el artículo 44 y siguientes de la LCSP y el Real decreto 814/2015, de 11 de septiembre, por el que se aprueba el Reglamento de los procedimientos especiales de revisión de decisiones en materia contractual y de organización del Tribunal Administrativo Central de Recursos Contractuales.

Este recurso tiene carácter potestativo, es gratuito para los recurrentes, se podrá interponer ante el Tribunal Catalán de Contratos del Sector Público, previamente o alternativamente, a la interposición del recurso contencioso administrativo, de conformidad con la Ley 29/1998, de 13 de junio, reguladora de la jurisdicción contencioso administrativa.

VI.5)Date of dispatch of this notice:

02/12/2021




Permalink


Open invitation to tender, deadline 07/03/2022, for technical assistance for coordination of safety and health works at the Zona Universitària - Sagrera Meridiana section of Metro Line 9 in Barcelona. For tender documents please click here. The value of the contract is EUR 930,841.38, excluding VAT. Duration of the contract will be 40 months. Contact Infraestructures de la Generalitat de Catalunya SAU, att.ne Xavier Fernandez Urban, Barcelona, tel +34 934444444, fax +34 934444488, email xfernandez@infraestructures.cat. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=069002-2022. Ref.n. CSS. TM-00509.4F.  06/22.

 

Spain-Barcelona: Civil engineering consultancy services

2022/S 027-069002

Contract notice

Services

Legal Basis:
Directive 2014/24/EU

Section I: Contracting authority

I.1)Name and addresses
Official name: Infraestructures de la Generalitat de Catalunya, SAU
National registration number: A-59.377.135
Postal address: Calle dels Vergós, 36-42
Town: Barcelona
NUTS code: ES511 Barcelona
Postal code: 08017
Country: Spain
Contact person: Xavier Fernández Urbán
E-mail: xfernandez@infraestructures.cat
Telephone: +34 934444444
Fax: +34 934444488
Internet address(es):
Main address: http://infraestructures.gencat.cat/
Address of the buyer profile: https://contractaciopublica.gencat.cat/perfil/Infraestructures
I.5)Main activity
General public services

Section II: Object

II.1)Scope of the procurement
II.1.1)Title:

Contrato servicios para la asistencia técnica conjunta de coordinación de seguridad y salud de las obras tramo Zona Universitaria – Sagrera Meridiana de la línea 9 de Metro de Barcelona. TM-00509.4F

Reference number: CSS. TM-00509.4F
II.1.2)Main CPV code
71311000 Civil engineering consultancy services
II.1.3)Type of contract
Services
II.1.5)Estimated total value
Value excluding VAT: 930 841.38 EUR
II.1.6)Information about lots
This contract is divided into lots: no
II.2)Description
II.2.3)Place of performance
NUTS code: ES511 Barcelona
II.2.6)Estimated value
Value excluding VAT: 930 841.38 EUR
II.2.7)Duration of the contract, framework agreement or dynamic purchasing system
Duration in months: 40
This contract is subject to renewal: no

Section IV: Procedure

IV.2)Administrative information
IV.2.2)Time limit for receipt of tenders or requests to participate
Date: 07/03/2022
Local time: 13:00
IV.2.3)Estimated date of dispatch of invitations to tender or to participate to selected candidates
IV.2.4)Languages in which tenders or requests to participate may be submitted:
Catalan, Spanish

Section VI: Complementary information

VI.5)Date of dispatch of this notice:
03/02/2022



Permalink


Postponed from 07/03/2022 to 14/03/2022 the deadline of the open invitation to tender for technical assistance for coordination of safety and health works at the Zona Universitària - Sagrera Meridiana section of Metro Line 9 in Barcelona. For tender documents please click here. The value of the contract is EUR 930,841.38, excluding VAT. Duration of the contract will be 40 months. Contact Infraestructures de la Generalitat de Catalunya SAU, att.ne Xavier Fernandez Urban, Barcelona, tel +34 934444444, fax +34 934444488, email xfernandez@infraestructures.cat. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=122914-2022. Ref.n. CSS. TM-00509.4F.  10/22. 

 




Permalink


Open invitation to tender, deadline 04/04/2022, for the construction management during the building of internal structures, track and catenary accessories for tunnel 3. on the Zona Universitària - Sagrera Meridiana section of Metro Line 9 in Barcelona. For tender documents please click here. The value of the contract is EUR 2.34 million, excluding VAT. Duration of the contract will be 34 months. Contact Infraestructures de la Generalitat de Catalunya SAU, attn Asun Aspas Blasco, Barcelona, tel +34 934444444, fax +34 934444488, email maaspas@infraestructures.cat. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=124621-2022. Ref.n. DO.TM-00509.4E.  12/22.

 

Spain-Barcelona: Construction project management services


2022/S 048-124621

Contract notice

Services

Legal Basis:
Directive 2014/24/EU

Section I: Contracting authority

I.1)Name and addresses
Official name: Infraestructures de la Generalitat de Catalunya, SAU
National registration number: A-59.377.135
Postal address: Calle dels Vergós, 36-42
Town: Barcelona
NUTS code: ES511 Barcelona
Postal code: 08017
Country: Spain
Contact person: Asun Aspas Blasco
E-mail: maaspas@infraestructures.cat
Telephone: +34 934444444
Fax: +34 934444488
Internet address(es):
Main address: http://infraestructures.gencat.cat/
Address of the buyer profile: https://contractaciopublica.gencat.cat/perfil/Infraestructures
I.5)Main activity
General public services

Section II: Object

II.1)Scope of the procurement
II.1.1)Title:


Dirección de las obras de Línea 9 del Metro de Barcelona. Tramo 3º. Zona Universitaria – Sagrera Meridiana. Complementos de estructura interior, vía y catenaria del túnel 3.


Reference number: DO.TM-00509.4E
II.1.2)Main CPV code
71541000 Construction project management services
II.1.3)Type of contract
Services
II.1.5)Estimated total value
Value excluding VAT: 2 342 155.20 EUR
II.1.6)Information about lots
This contract is divided into lots: no
II.2)Description
II.2.3)Place of performance
NUTS code: ES511 Barcelona
II.2.6)Estimated value
Value excluding VAT: 2 342 155.20 EUR
II.2.7)Duration of the contract, framework agreement or dynamic purchasing system
Duration in months: 40
This contract is subject to renewal: no

Section IV: Procedure

IV.2)Administrative information
IV.2.2)Time limit for receipt of tenders or requests to participate
Date: 04/04/2022
Local time: 13:00
IV.2.3)Estimated date of dispatch of invitations to tender or to participate to selected candidates
IV.2.4)Languages in which tenders or requests to participate may be submitted:
Catalan, Spanish

Section VI: Complementary information

VI.5)Date of dispatch of this notice:
04/03/2022



Permalink


UTE Auscultación L9 Barcelona from Alcobendas have secured the EUR 4.67 million contract, excluding VAT,  to provide technical assistance for auscultation (sound tests) of the works for the construction of metro Line 9 in Barcelona. Contact Infraestructures de la Generalitat de Catalunya, attn Xavier Fernandez Urban, Barcelona, tel +34 934444444, fax +34 934444488, email xfernandez@infraestructures.cat. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=185898-2022. Ref.n. ATDO. TM-00509.AU. 14/22.



Permalink


DAC Enviro SL from Barcellona secured the EUR 247,428 contract, excluding VAT, for environmental technical assistance for tunnel works and additional works in the Zona Universitària - Sagrera Meridiana section of Metro Line 9 in Barcelona. Contact Infraestructures de la Generalitat de Catalunya SAU, att.ne Xavier Fernandez Urban, Barcelona, tel +34 934444444, fax +34 934444488, email mhernandez@infraestructures.cat. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=524566-2022. Ref.n. ATAM. TM-00509.4F. 39/22. 



Permalink

Spain, Barajas - es/47

Airport Services

Work commencing on one-year construction programme for $75 million, 1.47 km-long two-level, three-lane cut-and-cover extension to new airport terminal. Upper level for passenger transport and lower level for baggage movements. Visit www.aena.es 14/01.Award of one-year contract to Constructora Hispanica SA for construction of 1.45 km, two-level extension to service tunnel, value $7.5 million. Visit www.aena.es 20/01.



Permalink