On 26th November, a new record was set by a CREG TBM by boring 1318.7 m/month, The Gripper TBM with 8.03 m boring diameter has reached this new record while working on the Yinsong water supply Tunnel Lot. 4. The same TBM set a record back in May 2016 which was 1226 m/month.
The tunnel is 23km long and to date 16.657 km have been completed at an average rate of 710m/month. Since boring began, this TBM has passed 39 fault zones, 54 karst caves, as well as dealing with a large water inflow of 500 m³/h. The TBM and site team have had to contend with complex geology and hard working conditions at times in the winter it was -30℃. They have performed outstandingly well and have been highly praised for what they have achieved so far. For further information on CREG TBM please visit their website.
23.04.2024 Austria
23.04.2024 Slovenia
25.04.2024 Austria
30.04.2024 Germany
07.05.2024 Switzerland
07.05.2024 Poland
13.05.2024 India
15.05.2024 Czech Republic
15.05.2024 Macedonia
16.05.2024 Finland
17.05.2024 Finland
24.05.2024 Switzerland
31.05.2024 Switzerland
07.06.2024 Canada
15.12.2024 Austria